121 W 119TH ST 90061

Certificate Information: 121 W 119TH ST 90061

Application / Permit
21014-10000-00134
Plan Check / Job No.
B21LA00451
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERSION OF DETACHED GARAGE INTO ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 3/31/2021
Issuing Office
Current Status
CofO Issued on 12/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2021 APPLICANT
Assigned to Plan Check Engineer 1/20/2021 RAHEL BEYENE
Corrections Issued 1/21/2021 RAHEL BEYENE
Plan Check Approved 2/9/2021 RICARDO RAMIREZ
Issued 3/31/2021 APPLICANT
Building Plans Picked Up 5/13/2021 APPLICANT
CofO in Progress 11/30/2021 EUGENE CASSIDY
Permit Finaled 12/4/2021 DEROLD HAUFF
CofO Issued 12/4/2021 DEROLD HAUFF
Permit Finaled 12/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/28/2021 THOMAS LANG
Roof/Waste drainage to street Cleared 1/28/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/1/2021 THOMAS LANG
Sewer availability Cleared 2/1/2021 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/21/2021 Approved JESUS PINEDA
Footing/Foundation/Slab 5/25/2021 Approved JOHN KLARIN
PLUMBING-Rough 5/25/2021 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 6/21/2021 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 6/21/2021 Not Ready for Inspection EUGENE CASSIDY
Gas Test 6/21/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 6/21/2021 Approved EUGENE CASSIDY
Shower Pan 6/21/2021 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 6/21/2021 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 6/22/2021 Corrections Issued JOHN KLARIN
Green Building Rough 6/22/2021 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 7/8/2021 Corrections Issued EUGENE CASSIDY
Gas Test 7/8/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 7/8/2021 Approved EUGENE CASSIDY
Shower Pan 7/8/2021 Approved EUGENE CASSIDY
Wood Frame 7/8/2021 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 7/22/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 7/22/2021 Partial Approval EUGENE CASSIDY
Wood Frame 7/22/2021 Corrections Issued EUGENE CASSIDY
HVAC-Rough 7/27/2021 Approved EUGENE CASSIDY
Wood Frame 7/27/2021 Approved EUGENE CASSIDY
Insulation 7/29/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 7/29/2021 Partial Approval EUGENE CASSIDY
Drywall Nailing 8/5/2021 Approved EUGENE CASSIDY
Green Building Rough 8/5/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 8/5/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/15/2021 Approved EUGENE CASSIDY
Final 9/15/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 9/15/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/15/2021 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 9/15/2021 Not Ready for Inspection EUGENE CASSIDY
Final 9/22/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 9/22/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/22/2021 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 9/22/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 10/1/2021 Approved EUGENE CASSIDY
Final 10/1/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 10/1/2021 Approved EUGENE CASSIDY
HVAC-Final 10/1/2021 Approved EUGENE CASSIDY
PLUMBING-Final 10/1/2021 Approved EUGENE CASSIDY
Final 11/29/2021 OK to Issue CofO EUGENE CASSIDY