121 W 119TH ST 90061
Certificate Information: 121 W 119TH ST 90061
- Application / Permit
- 21014-10000-00134
- Plan Check / Job No.
- B21LA00451
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERSION OF DETACHED GARAGE INTO ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 3/31/2021
- Issuing Office
- Current Status
- CofO Issued on 12/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2021 | RAHEL BEYENE |
| Corrections Issued | 1/21/2021 | RAHEL BEYENE |
| Plan Check Approved | 2/9/2021 | RICARDO RAMIREZ |
| Issued | 3/31/2021 | APPLICANT |
| Building Plans Picked Up | 5/13/2021 | APPLICANT |
| CofO in Progress | 11/30/2021 | EUGENE CASSIDY |
| Permit Finaled | 12/4/2021 | DEROLD HAUFF |
| CofO Issued | 12/4/2021 | DEROLD HAUFF |
| Permit Finaled | 12/4/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/28/2021 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 1/28/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2021 | THOMAS LANG |
| Sewer availability | Cleared | 2/1/2021 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/21/2021 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 5/25/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 5/25/2021 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 6/21/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Gas Test | 6/21/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 6/21/2021 | Approved | EUGENE CASSIDY |
| Shower Pan | 6/21/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Wood Frame | 6/21/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/22/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 6/22/2021 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 7/8/2021 | Corrections Issued | EUGENE CASSIDY |
| Gas Test | 7/8/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 7/8/2021 | Approved | EUGENE CASSIDY |
| Shower Pan | 7/8/2021 | Approved | EUGENE CASSIDY |
| Wood Frame | 7/8/2021 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/22/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/22/2021 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 7/22/2021 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Rough | 7/27/2021 | Approved | EUGENE CASSIDY |
| Wood Frame | 7/27/2021 | Approved | EUGENE CASSIDY |
| Insulation | 7/29/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/29/2021 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 8/5/2021 | Approved | EUGENE CASSIDY |
| Green Building Rough | 8/5/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/5/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/15/2021 | Approved | EUGENE CASSIDY |
| Final | 9/15/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 9/15/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 9/15/2021 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 9/15/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 9/22/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 9/22/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 9/22/2021 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 9/22/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/1/2021 | Approved | EUGENE CASSIDY |
| Final | 10/1/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 10/1/2021 | Approved | EUGENE CASSIDY |
| HVAC-Final | 10/1/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 10/1/2021 | Approved | EUGENE CASSIDY |
| Final | 11/29/2021 | OK to Issue CofO | EUGENE CASSIDY |