724 W 118TH ST 90044
Certificate Information: 724 W 118TH ST 90044
- Application / Permit
- 21014-10000-00129
- Plan Check / Job No.
- B21LA00437
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED ADDTITION TO AND CONVERSION OF GARAGE TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 7/12/2021
- Issuing Office
- Current Status
- CofO Issued on 11/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2021 | SINA KHOSRAVI |
| Corrections Issued | 1/20/2021 | SINA KHOSRAVI |
| Building Plans Picked Up | 2/3/2021 | APPLICANT |
| Plan Check Approved | 4/26/2021 | GEORGE ALVAREZ |
| Issued | 7/12/2021 | APPLICANT |
| CofO in Progress | 11/1/2022 | JOHN KLARIN |
| Permit Finaled | 11/4/2022 | RONALD MYRICK |
| CofO Issued | 11/4/2022 | RONALD MYRICK |
| Permit Finaled | 11/4/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 2/8/2021 | CHINH DINH |
| Roof/Waste drainage to street | Cleared | 2/8/2021 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2021 | CHINH DINH |
| Sewer availability | Cleared | 2/16/2021 | CHINH DINH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cardoza,, Jesse Adam; Lic. No.: C82846 | 6531 AMY AVENUE GARDEN GROVE, CA 92845 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 12/1/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 12/1/2021 | Partial Approval | EUGENE CASSIDY |
| Sewer | 12/1/2021 | Partial Approval | EUGENE CASSIDY |
| METHANE-Barrier | 12/7/2021 | Approved | EUGENE CASSIDY |
| Sewer | 12/7/2021 | Approved | EUGENE CASSIDY |
| Deputy Drilled-In Anchors | 12/9/2021 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 12/13/2021 | Conditional Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 12/13/2021 | Conditional Approval | EUGENE CASSIDY |
| METHANE-Subgrade | 12/13/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2022 | Partial Approval | EUGENE CASSIDY |
| HVAC-Rough | 2/4/2022 | Approved | AMY COLIN |
| METHANE-Rough | 2/4/2022 | Approved | AMY COLIN |
| PLUMBING-Rough | 2/4/2022 | Partial Approval | AMY COLIN |
| Interior/Exterior Lathing | 2/24/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 2/24/2022 | Approved | JOHN KLARIN |
| Gas Test | 4/29/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 4/29/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Gas Test | 5/5/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/5/2022 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/25/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/25/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 5/25/2022 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 5/25/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 6/9/2022 | Approved | SHAVONNE ESPINOZA |
| HVAC-Rough | 6/9/2022 | Approved | SHAVONNE ESPINOZA |
| Insulation | 6/9/2022 | Approved | SHAVONNE ESPINOZA |
| Drywall Nailing | 6/27/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/11/2022 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 10/13/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/13/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 10/13/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 10/13/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| MERV13>=Final | 10/13/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 10/13/2022 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 10/13/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/24/2022 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 10/24/2022 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 10/24/2022 | SGSOV Approved | ANSON MAGLASANG |
| Service/Power Release | 10/24/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| ELECTRICAL-Final | 10/31/2022 | Approved | JOHN KLARIN |
| Final | 10/31/2022 | OK to Issue CofO | JOHN KLARIN |