724 W 118TH ST 90044

Certificate Information: 724 W 118TH ST 90044

Application / Permit
21014-10000-00129
Plan Check / Job No.
B21LA00437
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED ADDTITION TO AND CONVERSION OF GARAGE TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 7/12/2021
Issuing Office
Current Status
CofO Issued on 11/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2021 APPLICANT
Assigned to Plan Check Engineer 1/19/2021 SINA KHOSRAVI
Corrections Issued 1/20/2021 SINA KHOSRAVI
Building Plans Picked Up 2/3/2021 APPLICANT
Plan Check Approved 4/26/2021 GEORGE ALVAREZ
Issued 7/12/2021 APPLICANT
CofO in Progress 11/1/2022 JOHN KLARIN
Permit Finaled 11/4/2022 RONALD MYRICK
CofO Issued 11/4/2022 RONALD MYRICK
Permit Finaled 11/4/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 2/8/2021 CHINH DINH
Roof/Waste drainage to street Cleared 2/8/2021 CHINH DINH
Eng Process Fee Ord 176,300 Cleared 2/16/2021 CHINH DINH
Sewer availability Cleared 2/16/2021 CHINH DINH

Contact Information

Contractor Owner-Builder       ,
Engineer Cardoza,, Jesse Adam; Lic. No.: C82846 6531 AMY AVENUE      GARDEN GROVE, CA 92845

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 12/1/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 12/1/2021 Partial Approval EUGENE CASSIDY
Sewer 12/1/2021 Partial Approval EUGENE CASSIDY
METHANE-Barrier 12/7/2021 Approved EUGENE CASSIDY
Sewer 12/7/2021 Approved EUGENE CASSIDY
Deputy Drilled-In Anchors 12/9/2021 Approved JOHN KLARIN
Excavation/Setback/Form/Re-Bar 12/13/2021 Conditional Approval EUGENE CASSIDY
Footing/Foundation/Slab 12/13/2021 Conditional Approval EUGENE CASSIDY
METHANE-Subgrade 12/13/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Partial Approval EUGENE CASSIDY
HVAC-Rough 2/4/2022 Approved AMY COLIN
METHANE-Rough 2/4/2022 Approved AMY COLIN
PLUMBING-Rough 2/4/2022 Partial Approval AMY COLIN
Interior/Exterior Lathing 2/24/2022 Approved JOHN KLARIN
PLUMBING-Rough 2/24/2022 Approved JOHN KLARIN
Gas Test 4/29/2022 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 4/29/2022 Corrections Issued ALIZAH MAYAGOITIA
Gas Test 5/5/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 5/5/2022 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 5/25/2022 Conditional Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 5/25/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 5/25/2022 Approved ALIZAH MAYAGOITIA
MERV13>=Rough 5/25/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 6/9/2022 Approved SHAVONNE ESPINOZA
HVAC-Rough 6/9/2022 Approved SHAVONNE ESPINOZA
Insulation 6/9/2022 Approved SHAVONNE ESPINOZA
Drywall Nailing 6/27/2022 Approved JOHN KLARIN
PLUMBING-Rough 7/11/2022 Partial Approval ANSON MAGLASANG
BUILDING-Rough-Frame 10/13/2022 Approved ALIZAH MAYAGOITIA
Final 10/13/2022 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 10/13/2022 Approved ALIZAH MAYAGOITIA
Green Building Final 10/13/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
MERV13>=Final 10/13/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 10/13/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 10/13/2022 Approved ALIZAH MAYAGOITIA
Final 10/24/2022 Corrections Issued ANSON MAGLASANG
Green Building Final 10/24/2022 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 10/24/2022 SGSOV Approved ANSON MAGLASANG
Service/Power Release 10/24/2022 Not Ready for Inspection ANSON MAGLASANG
ELECTRICAL-Final 10/31/2022 Approved JOHN KLARIN
Final 10/31/2022 OK to Issue CofO JOHN KLARIN