401 N BEACHWOOD DR 90004

Certificate Information: 401 N BEACHWOOD DR 90004

Application / Permit
21014-10000-00114
Plan Check / Job No.
B21LA00395
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**eplan** CONVERT DETACHED GARAGE TO ADU AND ADDITION
Permit Issued
Issued on 3/15/2021
Issuing Office
Current Status
CofO Issued on 12/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 ARSALAN SHABESTARI
Corrections Issued 1/23/2021 ARSALAN SHABESTARI
Quality Review Completed 1/29/2021 HERNAN ARREOLA
Applicant returned to address corrections 2/22/2021 ARSALAN SHABESTARI
Plan Check Approved 3/11/2021 ARSALAN SHABESTARI
Issued 3/15/2021 APPLICANT
CofO in Progress 12/9/2021 CRAIG DAVIS
Permit Finaled 12/13/2021 DEROLD HAUFF
CofO Issued 12/13/2021 DEROLD HAUFF
Permit Finaled 12/13/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/5/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 2/5/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 2/8/2021 RENZ SORIANO
Sewer availability Cleared 2/18/2021 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/27/2021 Not Ready for Inspection GREGG CUMMINGS
Footing/Foundation/Slab 4/5/2021 Partial Approval CHRIS CHRISTENSEN
METHANE-Barrier 4/5/2021 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 4/5/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 4/5/2021 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/20/2021 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 4/20/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 4/20/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/10/2021 Partial Approval CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 5/10/2021 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 5/18/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/25/2021 Approved ROBERT VORHIS
Green Building Rough 5/25/2021 Approved ROBERT VORHIS
Insulation 5/25/2021 Approved ROBERT VORHIS
METHANE-Rough 5/25/2021 Approved ROBERT VORHIS
Drywall Nailing 6/7/2021 Approved JESUS PINEDA
Interior/Exterior Lathing 7/16/2021 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Final 8/9/2021 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Final 8/24/2021 Approved ARTHUR SARGSYAN
HVAC-Final 8/24/2021 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Final 8/24/2021 Not Ready for Inspection ARTHUR SARGSYAN
Final 8/31/2021 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 8/31/2021 Approved CHRIS CHRISTENSEN
Green Building Final 8/31/2021 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 8/31/2021 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 8/31/2021 Approved CHRIS CHRISTENSEN
Final 9/9/2021 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 9/9/2021 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/9/2021 SGSOV Approved CHRIS CHRISTENSEN
Final 11/23/2021 Conditional Approval MASHEL JONGERT
Green Building Final 11/23/2021 Approved MASHEL JONGERT
Final 12/9/2021 OK to Issue CofO CRAIG DAVIS