2370 S PROSSER AVE 90064
Certificate Information: 2370 S PROSSER AVE 90064
- Application / Permit
- 21014-10000-00097
- Plan Check / Job No.
- B21LA00315
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND PARTIAL REMODEL TO EXISTING SFD
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 9/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | STARR CHEN |
| Corrections Issued | 1/23/2021 | STARR CHEN |
| Quality Review Completed | 2/4/2021 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 8/9/2021 | STARR CHEN |
| Applicant returned to address corrections | 10/29/2021 | STARR CHEN |
| Plan Check Approved | 11/15/2021 | STARR CHEN |
| Issued | 3/2/2022 | APPLICANT |
| Building Plans Picked Up | 3/10/2022 | APPLICANT |
| CofO in Progress | 9/6/2023 | CARLOS MATAMOROS |
| Permit Finaled | 9/12/2023 | DANIEL ORRANTE |
| CofO Issued | 9/12/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/12/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2021 | DINAH GARIN |
| Sewer availability | Cleared | 3/18/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 4/5/2021 | PATRICK MISCHLICH |
| Low Impact Development | Cleared | 7/4/2021 | MARTIN FRAGOSO |
| Specific Plan | Cleared | 8/19/2021 | DYLAN SITTIG |
| Specific Plan | Cleared | 8/26/2021 | KEVIN ARUCAN |
| Roof/Waste drainage to street | Cleared | 9/17/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 10/29/2021 | STARR CHEN |
Contact Information
| Contractor | New Bear Wind Inc; Lic. No.: 1059216-B | 4207 VIA ABBY MONTCLAIR, CA 91763 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/7/2022 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 4/22/2022 | Corrections Issued | BRENDAN LOONEY |
| METHANE-Barrier | 4/22/2022 | Approved | BRENDAN LOONEY |
| METHANE-Subgrade | 4/22/2022 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 5/3/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 5/5/2022 | Approved | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 5/16/2022 | Conditional Approval | BRENDAN LOONEY |
| Wood Frame | 7/11/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/1/2022 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/1/2022 | Approved | STEPHANIE SWANSON |
| Deputy Wood Construction | 9/2/2022 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 9/6/2022 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 9/28/2022 | Approved | STEPHANIE SWANSON |
| Wood Frame | 9/28/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 12/8/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 12/8/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 12/8/2022 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/4/2023 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/4/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 1/4/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/4/2023 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 2/6/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 2/23/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 2/23/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 2/23/2023 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/1/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/1/2023 | Partial Approval | STEPHANIE SWANSON |
| Green Building Rough | 3/1/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 3/1/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/1/2023 | Approved | STEPHANIE SWANSON |
| Special/Order Compliance | 3/1/2023 | Partial Inspection | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 4/7/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/7/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 4/7/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 4/7/2023 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/20/2023 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/20/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 4/20/2023 | Approved | STEPHANIE SWANSON |
| Insulation | 4/20/2023 | Approved | STEPHANIE SWANSON |
| METHANE-Rough | 4/20/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/21/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 4/21/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 5/11/2023 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 5/11/2023 | Approved | BRENDAN LOONEY |
| Shower Pan | 5/18/2023 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 5/24/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Shower Pan | 5/24/2023 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 5/31/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Shower Pan | 5/31/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 6/6/2023 | Approved | MICHAEL PELHAM |
| Shower Pan | 6/6/2023 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Final | 8/18/2023 | Corrections Issued | STEPHANIE SWANSON |
| Final | 8/18/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 8/18/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 8/18/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 8/18/2023 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 8/18/2023 | SGSOV Not Ready | STEPHANIE SWANSON |
| Smoke Detectors | 8/18/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 8/29/2023 | Corrections Issued | STEPHANIE SWANSON |
| Final | 8/29/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 8/29/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 8/29/2023 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 8/29/2023 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 8/29/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 9/5/2023 | Approved | CARLOS MATAMOROS |
| Final | 9/5/2023 | OK to Issue CofO | CARLOS MATAMOROS |
| HVAC-Final | 9/5/2023 | Approved | CARLOS MATAMOROS |