14045 W HERRON ST 91342

Certificate Information: 14045 W HERRON ST 91342

Application / Permit
21014-10000-00094
Plan Check / Job No.
B21LA00304
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached garage into ADU with addition per GCS 65852.2(e)(1)(D) and LAMC 12.22 A33(c), (d), and (g) . All work per engineered design.
Permit Issued
Issued on 4/12/2021
Issuing Office
Current Status
CofO Issued on 3/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2021 LAWRENCE QUIRANTE
Corrections Issued 1/14/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 3/10/2021 CRISTINA SALAZAR
Applicant returned to address corrections 3/23/2021 CRISTINA SALAZAR
Plan Check Approved 4/9/2021 FERNANDO FLORES
Issued 4/12/2021 APPLICANT
Building Plans Picked Up 4/14/2021 APPLICANT
CofO in Progress 9/9/2021 MISAEL ESPARZA
Permit Finaled 3/21/2022 RONALD MYRICK
CofO Issued 3/21/2022 RONALD MYRICK
Permit Finaled 3/21/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 1/26/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/8/2021 ADRIAN CASTRO
Sewer availability Cleared 3/8/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/12/2021 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 6/2/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 6/8/2021 Approved MISAEL ESPARZA
PLUMBING-Rough 6/8/2021 Partial Approval MISAEL ESPARZA
Reinforced Concrete Frame 6/8/2021 Partial Inspection MISAEL ESPARZA
Deputy Drilled-In Anchors 6/16/2021 No Result Entered KENNETH KUROWSKI
Wood Frame 6/18/2021 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 6/28/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 6/28/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 6/28/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 6/28/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 7/13/2021 Approved MISAEL ESPARZA
HVAC-Rough 7/13/2021 Corrections Issued MISAEL ESPARZA
Wood Frame 7/13/2021 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 7/15/2021 Approved MISAEL ESPARZA
Green Building Rough 7/15/2021 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 7/15/2021 Approved MISAEL ESPARZA
Insulation 7/20/2021 Not Ready for Inspection MISAEL ESPARZA
Insulation 7/22/2021 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 7/22/2021 Approved DEANDRE HOFFMAN
Drywall Nailing 7/27/2021 Approved WILLIAM WREN
Green Building Rough 7/27/2021 Approved WILLIAM WREN
Sewer 7/27/2021 Approved WILLIAM WREN
Shower Pan 7/27/2021 Approved WILLIAM WREN
Interior/Exterior Lathing 8/3/2021 Approved MISAEL ESPARZA
Gas Test 8/11/2021 Approved MISAEL ESPARZA
Service/Power Release 8/11/2021 Not Ready for Inspection MISAEL ESPARZA
Underground Mechanical 8/11/2021 Partial Approval MISAEL ESPARZA
Service/Power Release 8/19/2021 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 8/19/2021 Approved JENNIFER RABUCHIN
Final 9/7/2021 Corrections Issued MISAEL ESPARZA
Green Building Final 9/7/2021 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/7/2021 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 9/7/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 9/9/2021 Approved MISAEL ESPARZA
Final 9/9/2021 OK to Issue CofO MISAEL ESPARZA
Green Building Final 9/9/2021 Approved MISAEL ESPARZA
HVAC-Final 9/9/2021 Approved MISAEL ESPARZA
PLUMBING-Final 9/9/2021 Approved MISAEL ESPARZA
Smoke Detectors 9/9/2021 Approved MISAEL ESPARZA