10836 1/2 W ROSCOE BLVD 91352

Certificate Information: 10836 1/2 W ROSCOE BLVD 91352

Application / Permit
21014-10000-00090
Plan Check / Job No.
B21LA00295
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO ADU WITH AN ADDITION (1-STORY) PER ORDINANCE
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
CofO Issued on 2/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 CARLOS MONTES
Corrections Issued 2/9/2021 CARLOS MONTES
Quality Review Completed 2/23/2021 HERNAN ARREOLA
Plan Check Approved 4/21/2021 CARLOS MONTES
Issued 4/22/2021 APPLICANT
CofO in Progress 1/19/2022 JENNIFER RABUCHIN
CofO Issued 2/7/2022 MICHAEL SMITH
Permit Finaled 2/7/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/26/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 2/26/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/24/2021 ADRIAN CASTRO
Sewer availability Cleared 3/24/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/28/2021 Corrections Issued BEAU COLLINS
PLUMBING-Rough 4/28/2021 Not Ready for Inspection BEAU COLLINS
Excavation/Setback/Form/Re-Bar 5/21/2021 Partial Approval JOHN HAYES
Underground Mechanical 5/21/2021 Approved JOHN HAYES
Excavation/Setback/Form/Re-Bar 5/25/2021 Approved DAVID MATSON
Drywall Nailing 6/28/2021 Partial Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/28/2021 Partial Approval MICHEL ABAJAN
Green Building Rough 6/28/2021 Partial Inspection MICHEL ABAJAN
Wood Frame 7/22/2021 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 8/2/2021 No Access for Inspection WILLIAM KUEHN
ELECTRICAL-Rough 8/2/2021 No Access for Inspection WILLIAM KUEHN
Green Building Rough 8/2/2021 No Access for Inspection WILLIAM KUEHN
MERV13>=Rough 8/2/2021 No Access for Inspection WILLIAM KUEHN
PLUMBING-Rough 8/2/2021 No Access for Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 8/3/2021 Partial Inspection WILLIAM KUEHN
Rough-Elec/Plmb/HVAC 8/3/2021 Approved WILLIAM KUEHN
Green Building Rough 8/10/2021 Approved WILLIAM KUEHN
Insulation 8/10/2021 Approved WILLIAM KUEHN
Interior/Exterior Lathing 8/10/2021 Partial Approval WILLIAM KUEHN
Underground Mechanical 8/10/2021 Partial Approval WILLIAM KUEHN
Drywall Nailing 8/19/2021 Approved WILLIAM KUEHN
BUILDING-Rough-Frame 9/17/2021 Approved WILLIAM KUEHN
Final 9/17/2021 No Access for Inspection WILLIAM KUEHN
Footing/Foundation/Slab 9/17/2021 Approved WILLIAM KUEHN
Green Building Final 9/17/2021 Not Ready for Inspection WILLIAM KUEHN
MERV13>=Final 9/17/2021 Approved WILLIAM KUEHN
MERV13>=Rough 9/17/2021 Approved WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 9/17/2021 SGSOV Not Ready WILLIAM KUEHN
Smoke Detectors 9/17/2021 Not Ready for Inspection WILLIAM KUEHN
Final 10/14/2021 Corrections Issued WILLIAM KUEHN
Green Building Final 10/14/2021 Not Ready for Inspection WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 10/14/2021 SGSOV Not Ready WILLIAM KUEHN
Smoke Detectors 10/14/2021 Not Ready for Inspection WILLIAM KUEHN
Final 1/12/2022 Corrections Issued MATTHEW NELSON
Green Building Final 1/12/2022 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 1/12/2022 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 1/12/2022 Approved MATTHEW NELSON
ELECTRICAL-Final 1/18/2022 Approved JENNIFER RABUCHIN
Final 1/18/2022 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 1/18/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 1/18/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/18/2022 SGSOV Approved JENNIFER RABUCHIN