4443 N KRAFT AVE 91602
Certificate Information: 4443 N KRAFT AVE 91602
- Application / Permit
- 21014-10000-00082
- Plan Check / Job No.
- B21LA00256
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD (N) PATIO ( 5FT X 18 FT) TO & (E) GARAGE AND CONVERSION TO ADU
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- CofO Issued on 10/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2021 | TSE MING HUANG |
| Corrections Issued | 1/11/2021 | TSE MING HUANG |
| Plan Check Approved | 5/5/2021 | SINA KHOSRAVI |
| Issued | 4/26/2022 | APPLICANT |
| Building Plans Picked Up | 5/18/2022 | APPLICANT |
| CofO in Progress | 10/11/2022 | THOMAS FINNILA |
| CofO Issued | 10/12/2022 | MICHAEL SMITH |
| Permit Finaled | 10/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/3/2021 | ADRIAN CASTRO |
| ZI | Cleared | 2/8/2021 | RUBEN VASQUEZ |
| Address approval | Cleared | 2/19/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/22/2021 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 3/11/2021 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 4/27/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/27/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Norcio Construction Inc; Lic. No.: 1006731-B | 1756 CLINTON STREET LOS ANGELES, CA 90026 |
| Engineer | Truong,, Phong Lap; Lic. No.: C70784 | 20493 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/20/2022 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 5/25/2022 | Corrections Issued | DAVID MATSON |
| Footing/Foundation/Slab | 5/31/2022 | Approved | DAVID MATSON |
| PLUMBING-Rough | 5/31/2022 | Not Ready for Inspection | DAVID MATSON |
| Special/Order Compliance | 5/31/2022 | Not Ready for Inspection | DAVID MATSON |
| Underground Mechanical | 5/31/2022 | Partial Approval | DAVID MATSON |
| ELECTRICAL-Rough | 6/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 6/21/2022 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/30/2022 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 6/30/2022 | Conditional Approval | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 7/1/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2022 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 7/5/2022 | Approved | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 7/7/2022 | Partial Approval | MATT KELLERMAN |
| Deputy Wood Construction | 7/7/2022 | Partial Approval | MATT KELLERMAN |
| ELECTRICAL-Rough | 7/7/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 7/7/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 7/12/2022 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 7/12/2022 | Approved | THOMAS FINNILA |
| Shower Pan | 7/14/2022 | Approved | THOMAS FINNILA |
| Insulation | 7/18/2022 | Approved | THOMAS FINNILA |
| Green Building Rough | 7/22/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 7/22/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 9/7/2022 | Corrections Issued | DAVID ANDERSON |
| Service/Power Release | 9/7/2022 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/28/2022 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 9/28/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 9/28/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 9/28/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 9/28/2022 | Approved | GREGG CUMMINGS |
| HVAC-Final | 9/28/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| MERV13>=Final | 9/28/2022 | Approved | GREGG CUMMINGS |
| MERV13>=Rough | 9/28/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 9/28/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 9/28/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 9/28/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 10/7/2022 | Approved | THOMAS FINNILA |
| Final | 10/7/2022 | OK to Issue CofO | THOMAS FINNILA |
| Service/Power Release | 10/7/2022 | Approved | THOMAS FINNILA |