5312 N HARTWICK ST 90041

Certificate Information: 5312 N HARTWICK ST 90041

Application / Permit
21014-10000-00080
Plan Check / Job No.
B21LA00249
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
GROUND FLOOR ADDITION AND 2ND FLOOR ADDITION TO AN EXISTING ONE STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 12/19/2021
Issuing Office
Current Status
CofO Issued on 12/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 VU NGUYEN
Corrections Issued 2/2/2021 VU NGUYEN
Quality Review Completed 2/4/2021 EUGENE BARBEAU
Applicant returned to address corrections 5/13/2021 VU NGUYEN
Applicant returned to address corrections 9/17/2021 VU NGUYEN
Plan Check Approved 10/26/2021 VU NGUYEN
Issued 12/19/2021 APPLICANT
Building Plans Picked Up 12/29/2021 APPLICANT
CofO in Progress 11/9/2022 CRAIG VAUGHAN
CofO Issued 12/12/2022 DEROLD HAUFF
Permit Finaled 12/12/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/28/2021 RENZ SORIANO
Sewer availability Cleared 6/28/2021 RENZ SORIANO
GPI Written Notices Cleared 9/18/2021 VU NGUYEN
Grading Pre-Inspection Cleared 9/18/2021 VU NGUYEN
Low Impact Development Cleared 9/29/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/4/2021 JEANIE LAM

Contact Information

Contractor A T S Design And Construction; Lic. No.: 971152-B 18432 AMIE AVENUE      TORRANCE, CA 90504
Engineer Truong,, Phong; Lic. No.: C70784 20439 E CRESTLINE DRIVE      WALNUT, CA 91789

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/28/2022 No Access for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 2/4/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 2/17/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 2/17/2022 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 2/24/2022 Partial Approval LILIANA PORTILLO
Insulation 2/24/2022 Partial Approval LILIANA PORTILLO
Deputy Drilled-In Anchors 2/25/2022 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/15/2022 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/15/2022 Partial Approval SCOTT FINNILA
Deputy Wood Construction 5/11/2022 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 5/12/2022 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 5/12/2022 Approved CRAIG VAUGHAN
Green Building Rough 5/12/2022 Approved CRAIG VAUGHAN
HVAC-Rough 5/12/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/12/2022 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 5/17/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/17/2022 Approved CRAIG VAUGHAN
Insulation 5/27/2022 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 5/27/2022 Approved CHARLES BOGHOSKHAN
Drywall Nailing 6/2/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 6/2/2022 Approved CRAIG VAUGHAN
Shower Pan 6/2/2022 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 8/2/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 8/9/2022 Approved CRAIG VAUGHAN
Final 10/11/2022 Corrections Issued CRAIG VAUGHAN
Green Building Final 10/11/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/11/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 10/11/2022 Approved CRAIG VAUGHAN
Final 10/17/2022 Corrections Issued CRAIG VAUGHAN
Gas Test 10/17/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 11/7/2022 Approved CRAIG VAUGHAN
Final 11/7/2022 OK to Issue CofO CRAIG VAUGHAN