20247-20249 W KINZIE ST 91311

Certificate Information: 20247-20249 W KINZIE ST 91311

Application / Permit
21014-10000-00061
Plan Check / Job No.
B20LA24353
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
**eplan** CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 5/26/2021
Issuing Office
Current Status
CofO Issued on 6/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 VU NGUYEN
Corrections Issued 2/16/2021 VU NGUYEN
Quality Review Completed 2/19/2021 EUGENE BARBEAU
Applicant returned to address corrections 5/13/2021 VU NGUYEN
Plan Check Approved 5/18/2021 VU NGUYEN
Issued 5/26/2021 APPLICANT
CofO in Progress 5/27/2022 JEFFREY PARD
Permit Finaled 6/17/2022 JOHN JANSON
CofO Issued 6/17/2022 JOHN JANSON
Permit Finaled 6/17/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/4/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/4/2021 ADRIAN CASTRO
Sewer availability Cleared 5/4/2021 ADRIAN CASTRO

Contact Information

Architect Korn,, Gregory Ian; Lic. No.: NA30451       ,
Contractor Thompson Alan; Lic. No.: 932852-B 997 CAMINO LA MAIDA      THOUSAND OAKS, CA 91360

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/20/2021 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 8/2/2021 Partial Approval JEFFREY PARD
Deputy Drilled-In Anchors 8/18/2021 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 8/23/2021 Approved JEFFREY PARD
Footing/Foundation/Slab 9/22/2021 Approved RONALD COWAN
ELECTRICAL-Rough 1/19/2022 Partial Approval DAVID SCANTLIN
HVAC-Rough 1/19/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 1/19/2022 Partial Approval DAVID SCANTLIN
Insulation 1/28/2022 Partial Approval JEFFREY PARD
Drywall Nailing 3/9/2022 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 3/9/2022 Approved JEFFREY PARD
Gas Test 3/9/2022 Approved JEFFREY PARD
PLUMBING-Rough 3/9/2022 Approved JEFFREY PARD
Wood Frame 4/6/2022 Approved JEFFREY PARD
Drywall Nailing 4/12/2022 Approved JEFFREY PARD
Interior/Exterior Lathing 4/12/2022 Approved JEFFREY PARD
BUILDING-Rough-Frame 5/24/2022 Approved JEFFREY PARD
Final 5/24/2022 Corrections Issued JEFFREY PARD
Green Building Final 5/24/2022 Corrections Issued JEFFREY PARD
Green Building Rough 5/24/2022 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 5/24/2022 SGSOV Approved JEFFREY PARD
Smoke Detectors 5/24/2022 Approved JEFFREY PARD
Final 5/27/2022 OK to Issue CofO JEFFREY PARD
Green Building Final 5/27/2022 Approved JEFFREY PARD