1517 W 27TH ST 90007
Certificate Information: 1517 W 27TH ST 90007
- Application / Permit
- 21014-10000-00058
- Plan Check / Job No.
- B21LA00156
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING SINGLE FAMILY DWELLING. REMODEL EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 7/21/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | MANUEL MONTUFAR |
| Corrections Issued | 2/18/2021 | MANUEL MONTUFAR |
| Quality Review Completed | 2/22/2021 | EUGENE BARBEAU |
| Building Plans Picked Up | 3/2/2021 | APPLICANT |
| Applicant returned to address corrections | 4/20/2022 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 5/12/2022 | MANUEL MONTUFAR |
| Plan Check Approved | 7/14/2022 | MANUEL MONTUFAR |
| Issued | 7/21/2022 | APPLICANT |
| CofO in Progress | 8/21/2023 | KATHRYN BUTTERWORTH |
| CofO Issued | 8/23/2023 | DEROLD HAUFF |
| Permit Finaled | 8/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/26/2021 | ELAINE LEI |
| CPC | Cleared | 3/31/2021 | MAXFIELD VERMY |
| ZI | Cleared | 4/27/2021 | MAXFIELD VERMY |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2021 | THAN WIN |
| HPOZ | Cleared | 3/17/2022 | LYDIA CHAPMAN |
| Miscellaneous | Cleared | 3/17/2022 | LYDIA CHAPMAN |
| Miscellaneous | Cleared | 3/17/2022 | LYDIA CHAPMAN |
Contact Information
| Contractor | K & C Remodeling Inc; Lic. No.: 1081750-B | 1287 MONTECITO DR LOS ANGELES, CA 90031 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/27/2022 | Approved | KATHRYN BUTTERWORTH |
| Deputy Drilled-In Anchors | 8/26/2022 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 8/31/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 8/31/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 8/31/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 9/1/2022 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 2/22/2023 | Partial Approval | CHARLES BOGHOSKHAN |
| METHANE-Barrier | 2/22/2023 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| METHANE-Subgrade | 2/22/2023 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 3/3/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 3/3/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 3/3/2023 | Approved | KATHRYN BUTTERWORTH |
| Deputy Methane Barrier | 3/8/2023 | Conditional Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Wood Frame | 3/13/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Deputy Methane Barrier | 3/21/2023 | Conditional Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 3/23/2023 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 3/23/2023 | Approved | KATHRYN BUTTERWORTH |
| Wood Frame | 3/23/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Drilled-In Anchors | 3/24/2023 | Conditional Approval | KATHRYN BUTTERWORTH |
| Deputy Methane Barrier | 3/24/2023 | Conditional Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Wood Frame | 3/28/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 4/12/2023 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 4/12/2023 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 4/12/2023 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 4/12/2023 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Rough | 4/12/2023 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 4/12/2023 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 4/21/2023 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 4/21/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Shower Pan | 4/21/2023 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 4/27/2023 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 4/27/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 5/4/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 7/13/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 7/13/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 7/13/2023 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Final | 7/13/2023 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 7/13/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 7/13/2023 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 7/13/2023 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 7/21/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 7/21/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 7/21/2023 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 7/21/2023 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 8/16/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 8/16/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 8/16/2023 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 8/18/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Final | 8/18/2023 | OK to Issue CofO | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 8/18/2023 | SGSOV Approved | KATHRYN BUTTERWORTH |