1517 W 27TH ST 90007

Certificate Information: 1517 W 27TH ST 90007

Application / Permit
21014-10000-00058
Plan Check / Job No.
B21LA00156
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISTING SINGLE FAMILY DWELLING. REMODEL EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 7/21/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 MANUEL MONTUFAR
Corrections Issued 2/18/2021 MANUEL MONTUFAR
Quality Review Completed 2/22/2021 EUGENE BARBEAU
Building Plans Picked Up 3/2/2021 APPLICANT
Applicant returned to address corrections 4/20/2022 MANUEL MONTUFAR
Applicant returned to address corrections 5/12/2022 MANUEL MONTUFAR
Plan Check Approved 7/14/2022 MANUEL MONTUFAR
Issued 7/21/2022 APPLICANT
CofO in Progress 8/21/2023 KATHRYN BUTTERWORTH
CofO Issued 8/23/2023 DEROLD HAUFF
Permit Finaled 8/23/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/26/2021 ELAINE LEI
CPC Cleared 3/31/2021 MAXFIELD VERMY
ZI Cleared 4/27/2021 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 10/14/2021 THAN WIN
HPOZ Cleared 3/17/2022 LYDIA CHAPMAN
Miscellaneous Cleared 3/17/2022 LYDIA CHAPMAN
Miscellaneous Cleared 3/17/2022 LYDIA CHAPMAN

Contact Information

Contractor K & C Remodeling Inc; Lic. No.: 1081750-B 1287 MONTECITO DR      LOS ANGELES, CA 90031
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/27/2022 Approved KATHRYN BUTTERWORTH
Deputy Drilled-In Anchors 8/26/2022 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 8/31/2022 Partial Approval KATHRYN BUTTERWORTH
METHANE-Barrier 8/31/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Subgrade 8/31/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 9/1/2022 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 2/22/2023 Partial Approval CHARLES BOGHOSKHAN
METHANE-Barrier 2/22/2023 Not Ready for Inspection CHARLES BOGHOSKHAN
METHANE-Subgrade 2/22/2023 Not Ready for Inspection CHARLES BOGHOSKHAN
Footing/Foundation/Slab 3/3/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Barrier 3/3/2023 Corrections Issued KATHRYN BUTTERWORTH
METHANE-Subgrade 3/3/2023 Approved KATHRYN BUTTERWORTH
Deputy Methane Barrier 3/8/2023 Conditional Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 3/13/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Wood Frame 3/13/2023 Corrections Issued KATHRYN BUTTERWORTH
Deputy Methane Barrier 3/21/2023 Conditional Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 3/23/2023 Approved KATHRYN BUTTERWORTH
METHANE-Barrier 3/23/2023 Approved KATHRYN BUTTERWORTH
Wood Frame 3/23/2023 Partial Approval KATHRYN BUTTERWORTH
Deputy Drilled-In Anchors 3/24/2023 Conditional Approval KATHRYN BUTTERWORTH
Deputy Methane Barrier 3/24/2023 Conditional Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 3/28/2023 Partial Approval KATHRYN BUTTERWORTH
Wood Frame 3/28/2023 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 4/12/2023 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 4/12/2023 Approved KATHRYN BUTTERWORTH
Green Building Rough 4/12/2023 Approved KATHRYN BUTTERWORTH
HVAC-Rough 4/12/2023 Approved KATHRYN BUTTERWORTH
METHANE-Rough 4/12/2023 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 4/12/2023 Approved KATHRYN BUTTERWORTH
Insulation 4/21/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 4/21/2023 Partial Approval KATHRYN BUTTERWORTH
Shower Pan 4/21/2023 Approved KATHRYN BUTTERWORTH
Drywall Nailing 4/27/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 4/27/2023 Corrections Issued KATHRYN BUTTERWORTH
Interior/Exterior Lathing 5/4/2023 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Final 7/13/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 7/13/2023 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 7/13/2023 Approved KATHRYN BUTTERWORTH
HVAC-Final 7/13/2023 Approved KATHRYN BUTTERWORTH
PLUMBING-Final 7/13/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 7/13/2023 SGSOV Not Ready KATHRYN BUTTERWORTH
Smoke Detectors 7/13/2023 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 7/21/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 7/21/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Final 7/21/2023 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 7/21/2023 SGSOV Not Ready KATHRYN BUTTERWORTH
ELECTRICAL-Final 8/16/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 8/16/2023 Corrections Issued KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 8/16/2023 SGSOV Not Ready KATHRYN BUTTERWORTH
ELECTRICAL-Final 8/18/2023 Partial Approval KATHRYN BUTTERWORTH
Final 8/18/2023 OK to Issue CofO KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 8/18/2023 SGSOV Approved KATHRYN BUTTERWORTH