511 N SAN PASCUAL AVE 90042

Certificate Information: 511 N SAN PASCUAL AVE 90042

Application / Permit
21014-10000-00053
Plan Check / Job No.
B21LA00130
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO EXISTING SFD
Permit Issued
Issued on 11/4/2022
Issuing Office
Metro
Current Status
Issued on 11/4/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/5/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 CRYSTEL MAALOUF
Corrections Issued 2/4/2021 CRYSTEL MAALOUF
Quality Review Completed 2/25/2021 WING SUEN
Plan Check Approved 6/16/2022 CRYSTEL MAALOUF
Issued 11/4/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/8/2022 CINDY QI
Sewer availability Cleared 3/8/2022 CINDY QI
Hydrant and Access approval Cleared 3/28/2022 LAURINDA MEADE
Low Impact Development Cleared 5/23/2022 KHAING AYE
Roof/Waste drainage to street Cleared 6/9/2022 CINDY QI
GPI Written Notices Cleared 6/10/2022 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 6/10/2022 CRYSTEL MAALOUF
Zoning Information File Cleared 6/14/2022 DANIEL SCHNEIDEREIT

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/28/2023 Partial Approval AMY COLIN
Footing/Foundation/Slab 6/28/2023 Partial Approval AMY COLIN
Deputy Reinf. Concrete 7/6/2023 Conditional Approval AMY COLIN
Footing/Foundation/Slab 7/19/2023 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Partial Approval AMY COLIN
PLUMBING-Rough 8/4/2023 Partial Approval AMY COLIN
Underground Mechanical 8/4/2023 Not Ready for Inspection AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 9/13/2023 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Approved ROY SPAULDING
Special/Order Compliance 11/6/2023 Corrections Issued ROY SPAULDING
BUILDING-Rough-Frame 11/27/2023 Partial Approval ROY SPAULDING
ELECTRICAL-Rough 11/27/2023 Corrections Issued ROY SPAULDING
Green Building Rough 11/27/2023 Approved ROY SPAULDING
HVAC-Rough 11/27/2023 Approved ROY SPAULDING
MERV13>=Rough 11/27/2023 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 11/27/2023 Approved ROY SPAULDING
BUILDING-Rough-Frame 2/8/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 2/8/2024 Approved ROY SPAULDING
MERV13>=Rough 2/8/2024 Approved ROY SPAULDING
Insulation 2/14/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 2/28/2024 Approved ALIZAH MAYAGOITIA
Sewer 7/3/2024 Approved ALIZAH MAYAGOITIA
Shower Pan 7/3/2024 Approved ALIZAH MAYAGOITIA
Underground Mechanical 7/3/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 8/5/2024 Corrections Issued ANTHONY RAMOS
Interior/Exterior Lathing 8/7/2024 Approved ALIZAH MAYAGOITIA
Gas Test 11/20/2024 Approved THOMAS LOGRASSO
Service/Power Release 11/20/2024 Corrections Issued THOMAS LOGRASSO
Service/Power Release 11/25/2024 Approved ALIZAH MAYAGOITIA