988 N HYPERION AVE 90029

Certificate Information: 988 N HYPERION AVE 90029

Application / Permit
21014-10000-00051
Plan Check / Job No.
B21LA00125
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-STORY ADDITION TO (E) 1-STORY SFD.
Permit Issued
Issued on 12/9/2022
Issuing Office
Metro
Current Status
Issued on 12/9/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/8/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 CHUNG-WEN CHUANG
Corrections Issued 2/16/2021 CHUNG-WEN CHUANG
Quality Review Completed 2/19/2021 JASON HEALEY
Building Plans Picked Up 2/26/2021 APPLICANT
Applicant returned to address corrections 6/3/2022 CHUNG-WEN CHUANG
Applicant returned to address corrections 8/4/2022 CHUNG-WEN CHUANG
Applicant returned to address corrections 11/4/2022 CHUNG-WEN CHUANG
Plan Check Approved 12/6/2022 CHUNG-WEN CHUANG
Issued 12/9/2022 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/24/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 3/24/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 3/24/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 3/24/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 3/24/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/15/2021 AVALYN KAMACHI
Disturb/Remove Protected Trees Cleared 10/3/2022 ADALBERTO VERA
Low Impact Development Cleared 10/13/2022 LUIS LUVANO
Roof/Waste drainage to street Cleared 10/17/2022 CINDY QI
GPI Written Notices Cleared 11/4/2022 JASON HEALEY
Grading Pre-Inspection Cleared 11/4/2022 CHUNG-WEN CHUANG

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 3/31/2023 Approved THOMAS LOGRASSO
Special/Order Compliance 4/5/2023 Approved FREDDIE RIVERA
Pre-Inspection 6/13/2023 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 8/15/2023 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 8/30/2023 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 9/6/2023 Partial Approval FREDDIE RIVERA
Wood Frame 9/6/2023 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 12/19/2023 Approved SCOTT FINNILA
HVAC-Rough 12/19/2023 Partial Approval SCOTT FINNILA
PLUMBING-Rough 12/19/2023 Approved SCOTT FINNILA
HVAC-Rough 12/21/2023 Partial Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 12/29/2023 Not Ready for Inspection THOMAS LOGRASSO
Wood Frame 12/29/2023 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 1/4/2024 Partial Approval SCOTT FINNILA
HVAC-Rough 1/4/2024 Approved SCOTT FINNILA
BUILDING-Rough-Frame 2/12/2024 Approved SCOTT FINNILA
Green Building Rough 2/12/2024 Approved SCOTT FINNILA
Insulation 3/4/2024 Approved SCOTT FINNILA
Drywall Nailing 4/2/2024 Approved SCOTT FINNILA
Interior/Exterior Lathing 4/30/2024 Partial Approval SCOTT FINNILA
Shower Pan 4/30/2024 Approved SCOTT FINNILA
Final 3/10/2026 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 3/10/2026 Approved SCOTT FINNILA
Green Building Final 3/10/2026 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 3/10/2026 SGSOV Approved SCOTT FINNILA
Smoke Detectors 3/10/2026 Corrections Issued SCOTT FINNILA