2456 N SUNDOWN DR 90065

Certificate Information: 2456 N SUNDOWN DR 90065

Application / Permit
21014-10000-00042
Plan Check / Job No.
B21LA00114
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND AND 3RD FLOOR ADDITION (3-STORY) TO (E) SFD (1-STORY)
Permit Issued
Issued on 11/30/2021
Issuing Office
Current Status
Issued on 11/30/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/6/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 CARLOS MONTES
Corrections Issued 2/5/2021 CARLOS MONTES
Quality Review Completed 2/17/2021 GARO TELMI
Building Plans Picked Up 2/23/2021 APPLICANT
Applicant returned to address corrections 8/23/2021 CARLOS MONTES
Applicant returned to address corrections 11/17/2021 CARLOS MONTES
Plan Check Approved 11/29/2021 CARLOS MONTES
Issued 11/30/2021 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/13/2021 CARLOS MONTES
BHO/Hillside ordinance Cleared 7/15/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 7/15/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 7/15/2021 RENZ SORIANO
Sewer availability Cleared 7/15/2021 RENZ SORIANO
Miscellaneous Cleared 8/9/2021 RICHARD REASER
Specific Plan Cleared 8/9/2021 RICHARD REASER
Distance to fire station Cleared 10/2/2021 RUEL COLE
Hydrant and Access approval Cleared 10/2/2021 RUEL COLE
Low Impact Development Cleared 11/17/2021 JULIAN SUNG
Roof/Waste drainage to street Cleared 11/18/2021 WALLIE JONG

Contact Information

Architect Neilson,, Jeffrey William; Lic. No.: C36101 2456 SUNDOWN DRIVE      LOS ANGELES, CA 90065
Contractor Owner-Builder       ,
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 560 31ST ST      MANHATTAN BEACH, CA 90266

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/15/2023 Corrections Issued HAMIK HARTOUNIAN
Pre-Inspection 2/15/2023 Partial Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 2/27/2023 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 4/3/2023 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 4/3/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Structural Steel Frame 4/3/2023 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/4/2023 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 6/21/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 6/21/2023 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/10/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 7/10/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 7/10/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 7/13/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/25/2024 Partial Approval HAMIK HARTOUNIAN
Insulation 1/25/2024 Approved HAMIK HARTOUNIAN
Wood Frame 1/25/2024 Approved HAMIK HARTOUNIAN
Special/Order Compliance 3/5/2024 Partial Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/22/2025 Approved DAVID WILLIAMS
PLUMBING-Rough 3/19/2026 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 4/17/2026 Approved NICHOLAS LOPEZ
Green Building Rough 4/17/2026 Approved NICHOLAS LOPEZ
HVAC-Rough 4/17/2026 Approved NICHOLAS LOPEZ
Insulation 5/1/2026 Approved NICHOLAS LOPEZ