3438 1/2 W GARDEN AVE 90039
Certificate Information: 3438 1/2 W GARDEN AVE 90039
- Application / Permit
- 21014-10000-00016
- Plan Check / Job No.
- B20LA24343
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADU addition. convert existing 2 car garage and add 2 story addition (2-STORY) DETACHED ADU PER ORDINANCE
- Permit Issued
- Issued on 4/3/2024
- Issuing Office
- Current Status
- CofO Issued on 8/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | CARLOS MONTES |
| Corrections Issued | 2/11/2021 | CARLOS MONTES |
| Quality Review Completed | 2/23/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 9/29/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 3/4/2024 | CARLOS MONTES |
| Plan Check Approved | 3/15/2024 | CARLOS MONTES |
| Issued | 4/3/2024 | APPLICANT |
| CofO in Progress | 8/29/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 8/29/2025 | DEROLD HAUFF |
| CofO Issued | 8/29/2025 | DEROLD HAUFF |
| Permit Finaled | 8/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 3/15/2021 | RENZ SORIANO |
| Low Impact Development | Cleared | 3/24/2022 | TA ANH |
| ZI | Cleared | 4/21/2022 | MAXFIELD VERMY |
| Roof/Waste drainage to street | Cleared | 7/27/2023 | NEIL TUANO |
Contact Information
| Contractor | Gaeta Jose Luis; Lic. No.: 809569-B | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
| Engineer | Chavez,, Eduardo; Lic. No.: NA76372 | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/8/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Underground Mechanical | 4/26/2024 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 5/3/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 5/7/2024 | Approved | THOMAS LOGRASSO |
| Deputy Wood Construction | 6/14/2024 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2024 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 7/17/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 9/3/2024 | Conditional Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 9/3/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 9/6/2024 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 12/10/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/12/2024 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 12/12/2024 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/12/2024 | Partial Approval | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 12/12/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 12/19/2024 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 1/17/2025 | Partial Approval | THOMAS LOGRASSO |
| Insulation | 1/17/2025 | Approved | THOMAS LOGRASSO |
| Shower Pan | 2/19/2025 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 2/24/2025 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 5/1/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Final | 5/8/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Pre-Inspection | 5/8/2025 | Partial Inspection | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 5/22/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 5/22/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 5/22/2025 | Corrections Issued | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 5/30/2025 | Partial Approval | DAVID WILLIAMS |
| HVAC-Final | 5/30/2025 | Partial Approval | DAVID WILLIAMS |
| PLUMBING-Final | 5/30/2025 | Partial Approval | DAVID WILLIAMS |
| PLUMBING-Rough | 5/30/2025 | Partial Approval | DAVID WILLIAMS |
| Service/Power Release | 5/30/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 6/18/2025 | Approved | NICHOLAS LOPEZ |
| Final | 6/18/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 6/18/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Final | 6/18/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 6/18/2025 | Approved | NICHOLAS LOPEZ |
| Final | 6/26/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/26/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Pre-Inspection | 7/2/2025 | Partial Approval | NICHOLAS LOPEZ |
| Final | 7/8/2025 | Conditional Approval | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/8/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 8/28/2025 | Approved | NICHOLAS LOPEZ |
| Final | 8/28/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| HVAC-Final | 8/28/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 8/28/2025 | Approved | NICHOLAS LOPEZ |
| Service/Power Release | 8/28/2025 | Approved | NICHOLAS LOPEZ |