2951 W ESTARA AVE 90065
Certificate Information: 2951 W ESTARA AVE 90065
- Application / Permit
- 21014-10000-00013
- Plan Check / Job No.
- B21LA00067
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW FRONT ATTACHED COVERED PATIO
- Permit Issued
- Issued on 9/19/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | SINA KHOSRAVI |
| Corrections Issued | 1/8/2021 | SINA KHOSRAVI |
| Building Plans Picked Up | 1/12/2021 | APPLICANT |
| Plan Check Approved | 8/17/2022 | JOSEPH RAFOLS |
| Issued | 9/19/2022 | APPLICANT |
| CofO in Progress | 1/21/2025 | THOMAS LOGRASSO |
| CofO Issued | 1/27/2025 | DEROLD HAUFF |
| Permit Finaled | 1/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 2/4/2021 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 2/5/2021 | BRIAN MILLER |
| Tenant Habitability Plan | Cleared | 8/1/2022 | ISMAEL HERNANDEZ |
| Supp. Use District POD/CDO/TDO | Cleared | 8/16/2022 | SPENCER WEJROWSKI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khanjian,, Hovik J; Lic. No.: C51609 | 326 S. SPARKS STREET BURBANK, CA 91506 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/17/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 11/22/2022 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 11/22/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 12/1/2022 | Approved | RUBEN SALAS |
| BUILDING-Rough-Frame | 1/11/2023 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/3/2023 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 2/3/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 3/21/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 3/21/2023 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 3/21/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 1/17/2025 | OK to Issue CofO | THOMAS LOGRASSO |