621 1/2 W 43RD ST 90037
Certificate Information: 621 1/2 W 43RD ST 90037
- Application / Permit
- 21014-10000-00007
- Plan Check / Job No.
- B21LA00026
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED ADDITION TO AND CONVERSION OF GARAGE INTO ADU
- Permit Issued
- Issued on 7/21/2021
- Issuing Office
- Current Status
- Issued on 7/21/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2021 | TSE MING HUANG |
| Corrections Issued | 1/6/2021 | TSE MING HUANG |
| Plan Check Approved | 5/24/2021 | SINA KHOSRAVI |
| Issued | 7/21/2021 | APPLICANT |
| Building Plans Picked Up | 7/26/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/11/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 2/11/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2021 | JEANIE LAM |
| Sewer availability | Cleared | 2/16/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 3/9/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ruvalcaba,, Martin Eduardo; Lic. No.: C75838 | 5942 AUTRY AVE LAKEWOOD, CA 90712 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/17/2022 | Corrections Issued | SABAS ALONSO |
| Sewer | 3/17/2022 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 3/17/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 5/9/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/23/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 2/23/2023 | Corrections Issued | SABAS ALONSO |
| Gas Test | 2/23/2023 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 2/23/2023 | Approved | SABAS ALONSO |
| HVAC-Final | 2/23/2023 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 2/23/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 2/23/2023 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 2/23/2023 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 2/23/2023 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 2/23/2023 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/28/2023 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 2/28/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 2/28/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 3/9/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Partial Inspection | SABAS ALONSO |
| Insulation | 3/9/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 3/9/2023 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 4/6/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 4/6/2023 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 4/14/2023 | Approved | BRENDAN MORELLI |