5319 S 4TH AVE 90043
Certificate Information: 5319 S 4TH AVE 90043
- Application / Permit
- 21014-10000-00005
- Plan Check / Job No.
- B21LA00020
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO REAR OF DWELLING.
- Permit Issued
- Issued on 2/18/2021
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2021 | TSE MING HUANG |
| Corrections Issued | 1/6/2021 | TSE MING HUANG |
| Plan Check Approved | 2/5/2021 | RICARDO RAMIREZ |
| Issued | 2/18/2021 | APPLICANT |
| Building Plans Picked Up | 4/20/2021 | APPLICANT |
| CofO in Progress | 8/23/2022 | HORACE FULTZ |
| Permit Finaled | 8/25/2022 | DEROLD HAUFF |
| CofO Issued | 8/25/2022 | DEROLD HAUFF |
| Permit Finaled | 8/25/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/28/2021 | THOMAS LANG |
| Sewer availability | Cleared | 1/28/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2021 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RAUL BARAJAS, (213) 202-3211 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/21/2021 | No Access for Inspection | DAVID FEILER |
| Pre-Inspection | 9/22/2021 | Partial Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 12/21/2021 | Approved | HORACE FULTZ |
| Footing/Foundation/Slab | 12/21/2021 | Approved | HORACE FULTZ |
| Special/Order Compliance | 1/10/2022 | No Violation (special insp) | AMY COLIN |
| ELECTRICAL-Rough | 1/14/2022 | Not Ready for Inspection | HORACE FULTZ |
| PLUMBING-Rough | 1/14/2022 | Approved | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2022 | Partial Approval | HORACE FULTZ |
| Insulation | 1/20/2022 | Partial Approval | HORACE FULTZ |
| Special/Order Compliance | 1/28/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 2/15/2022 | No Access for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/15/2022 | No Access for Inspection | LILIANA PORTILLO |
| Green Building Rough | 2/15/2022 | No Access for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 2/15/2022 | No Access for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 2/15/2022 | No Access for Inspection | LILIANA PORTILLO |
| Special/Order Compliance | 2/15/2022 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 2/16/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Rough | 2/16/2022 | Approved | HORACE FULTZ |
| Green Building Rough | 2/16/2022 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 2/16/2022 | Approved | HORACE FULTZ |
| Green Building Final | 2/23/2022 | Approved | HORACE FULTZ |
| Shower Pan | 2/23/2022 | Corrections Issued | HORACE FULTZ |
| Interior/Exterior Lathing | 3/1/2022 | Partial Approval | HORACE FULTZ |
| Shower Pan | 3/1/2022 | Corrections Issued | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Not Ready for Inspection | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2022 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 3/8/2022 | Partial Approval | HORACE FULTZ |
| Shower Pan | 3/8/2022 | Corrections Issued | HORACE FULTZ |
| Insulation | 3/15/2022 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 3/15/2022 | Approved | HORACE FULTZ |
| Shower Pan | 3/15/2022 | Corrections Issued | HORACE FULTZ |
| Drywall Nailing | 3/21/2022 | Approved | HORACE FULTZ |
| Shower Pan | 3/21/2022 | Not Ready for Inspection | HORACE FULTZ |
| Shower Pan | 3/25/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 5/5/2022 | Corrections Issued | HORACE FULTZ |
| PLUMBING-Final | 5/5/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 5/6/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 5/6/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 5/12/2022 | Approved | HORACE FULTZ |
| PLUMBING-Final | 5/12/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 5/23/2022 | Approved | HORACE FULTZ |
| Service/Power Release | 5/23/2022 | Approved | HORACE FULTZ |
| Final | 8/17/2022 | OK to Issue CofO | HORACE FULTZ |
| PLUMBING-Final | 8/17/2022 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Approved | HORACE FULTZ |
| Smoke Detectors | 8/17/2022 | Approved | HORACE FULTZ |
| HVAC-Final | 8/23/2022 | Approved | HORACE FULTZ |