20919 S NORMANDIE AVE 90501

Certificate Information: 20919 S NORMANDIE AVE 90501

Application / Permit
21014-10000-00003
Plan Check / Job No.
B21LA00017
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING GARAGE TO BE CONVERTED INTO AN ADU AND ADDITION TO THE GARAGE.
Permit Issued
Issued on 8/25/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2021 APPLICANT
Assigned to Plan Check Engineer 4/21/2021 SAMUEL GONZALEZ
Corrections Issued 4/21/2021 SAMUEL GONZALEZ
Building Plans Picked Up 5/18/2021 APPLICANT
Plan Check Approved 8/22/2022 RAHEL BEYENE
Issued 8/25/2022 APPLICANT
CofO in Progress 3/1/2024 EUGENE CASSIDY
Permit Finaled 3/1/2024 ANSON MAGLASANG
CofO Issued 3/1/2024 ANSON MAGLASANG
Permit Finaled 3/1/2024 ANSON MAGLASANG

Permit Application Clearance Information

ZA Case Cleared 3/29/2022 MAYELA VILLA
Construction near power lines Cleared 4/25/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 5/11/2022 JOHN CONNEALLY
Address approval Cleared 6/8/2022 ERIK BEASLEY
Roof/Waste drainage to street Cleared 6/8/2022 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 8/1/2022 CINDY QI
Sewer availability Cleared 8/1/2022 CINDY QI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/2/2022 Approved JOHN KLARIN
PLUMBING-Rough 1/5/2023 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 1/13/2023 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 1/13/2023 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 1/30/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 3/3/2023 Corrections Issued EUGENE CASSIDY
Green Building Rough 3/3/2023 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 3/20/2023 Corrections Issued EUGENE CASSIDY
Green Building Rough 3/20/2023 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 3/20/2023 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 4/4/2023 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 4/4/2023 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 6/30/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/4/2023 Approved EUGENE CASSIDY
Green Building Rough 8/4/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 8/4/2023 Approved EUGENE CASSIDY
Insulation 8/10/2023 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 8/10/2023 Partial Approval EUGENE CASSIDY
Insulation 8/14/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 8/14/2023 Partial Approval EUGENE CASSIDY
Drywall Nailing 8/29/2023 Corrections Issued EUGENE CASSIDY
Drywall Nailing 9/6/2023 Approved EUGENE CASSIDY
Drywall Nailing 10/2/2023 Approved EUGENE CASSIDY
Shower Pan 10/2/2023 Corrections Issued EUGENE CASSIDY
Shower Pan 11/1/2023 Corrections Issued EUGENE CASSIDY
Shower Pan 11/8/2023 Approved EUGENE CASSIDY
Gas Test 1/12/2024 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 1/12/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 2/13/2024 Corrections Issued EUGENE CASSIDY
Final 2/23/2024 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 2/23/2024 Approved EUGENE CASSIDY
Green Building Final 2/23/2024 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 2/23/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 2/29/2024 Approved EUGENE CASSIDY
Final 2/29/2024 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 2/29/2024 Approved EUGENE CASSIDY
Service/Power Release 2/29/2024 Not Required EUGENE CASSIDY