20919 S NORMANDIE AVE 90501
Certificate Information: 20919 S NORMANDIE AVE 90501
- Application / Permit
- 21014-10000-00003
- Plan Check / Job No.
- B21LA00017
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EXISTING GARAGE TO BE CONVERTED INTO AN ADU AND ADDITION TO THE GARAGE.
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 4/21/2021 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 5/18/2021 | APPLICANT |
| Plan Check Approved | 8/22/2022 | RAHEL BEYENE |
| Issued | 8/25/2022 | APPLICANT |
| CofO in Progress | 3/1/2024 | EUGENE CASSIDY |
| Permit Finaled | 3/1/2024 | ANSON MAGLASANG |
| CofO Issued | 3/1/2024 | ANSON MAGLASANG |
| Permit Finaled | 3/1/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| ZA Case | Cleared | 3/29/2022 | MAYELA VILLA |
| Construction near power lines | Cleared | 4/25/2022 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 5/11/2022 | JOHN CONNEALLY |
| Address approval | Cleared | 6/8/2022 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 6/8/2022 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2022 | CINDY QI |
| Sewer availability | Cleared | 8/1/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/2/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 1/5/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 1/13/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 1/13/2023 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 1/30/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/3/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 3/3/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/20/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 3/20/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 3/20/2023 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/4/2023 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 4/4/2023 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 6/30/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/4/2023 | Approved | EUGENE CASSIDY |
| Green Building Rough | 8/4/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 8/4/2023 | Approved | EUGENE CASSIDY |
| Insulation | 8/10/2023 | Partial Approval | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/10/2023 | Partial Approval | EUGENE CASSIDY |
| Insulation | 8/14/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/14/2023 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 8/29/2023 | Corrections Issued | EUGENE CASSIDY |
| Drywall Nailing | 9/6/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 10/2/2023 | Approved | EUGENE CASSIDY |
| Shower Pan | 10/2/2023 | Corrections Issued | EUGENE CASSIDY |
| Shower Pan | 11/1/2023 | Corrections Issued | EUGENE CASSIDY |
| Shower Pan | 11/8/2023 | Approved | EUGENE CASSIDY |
| Gas Test | 1/12/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 1/12/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/13/2024 | Corrections Issued | EUGENE CASSIDY |
| Final | 2/23/2024 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/23/2024 | Approved | EUGENE CASSIDY |
| Green Building Final | 2/23/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/23/2024 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 2/23/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/29/2024 | Approved | EUGENE CASSIDY |
| Final | 2/29/2024 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 2/29/2024 | Approved | EUGENE CASSIDY |
| Service/Power Release | 2/29/2024 | Not Required | EUGENE CASSIDY |