832 E 109TH ST 90059

Certificate Information: 832 E 109TH ST 90059

Application / Permit
21010-30000-06953
Plan Check / Job No.
B21WL05820
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW TWO STORY ADU per ordinace ATTACHED TO NEW 2 CAR GARAGE
Permit Issued
Issued on 9/16/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2022 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 YASHAR EMAMI
Corrections Issued 2/2/2022 YASHAR EMAMI
Quality Review Completed 2/22/2022 CHIHARU SUZUKI
Applicant returned to address corrections 7/13/2022 YASHAR EMAMI
Applicant returned to address corrections 8/18/2022 YASHAR EMAMI
Applicant returned to address corrections 8/30/2022 YASHAR EMAMI
Plan Check Approved 9/12/2022 YASHAR EMAMI
Building Plans Picked Up 9/13/2022 APPLICANT
Issued 9/16/2022 APPLICANT
CofO in Progress 4/25/2023 ANSON MAGLASANG
CofO Issued 4/25/2023 ANSON MAGLASANG
Permit Finaled 4/25/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 3/1/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 3/4/2022 CINDY QI
Sewer availability Cleared 3/22/2022 CINDY QI
Low Impact Development Cleared 5/31/2022 KHAING AYE
Roof/Waste drainage to street Cleared 6/1/2022 CINDY QI
Trees in Parkway Cleared 8/2/2022 ADALBERTO VERA

Contact Information

Contractor De La Rosa Construction; Lic. No.: 855010-B 3627 E FIRST STREET      LOS ANGELES, CA 90063
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/23/2022 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 9/23/2022 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 9/29/2022 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/20/2022 Approved JOHN KLARIN
Deputy Wood Construction 10/21/2022 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 10/28/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 10/28/2022 Approved JOHN KLARIN
Green Building Rough 10/28/2022 Approved JOHN KLARIN
HVAC-Rough 10/28/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 10/28/2022 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 10/28/2022 Approved JOHN KLARIN
Rough-Elec/Plmb/HVAC 10/28/2022 Approved JOHN KLARIN
Insulation 11/1/2022 Approved JOHN KLARIN
Insulation 11/2/2022 Not Ready for Inspection JOHN KLARIN
Drywall Nailing 11/7/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 11/7/2022 Approved JOHN KLARIN
Shower Pan 11/7/2022 Approved JOHN KLARIN
Final 2/15/2023 Corrections Issued JOHN KLARIN
Green Building Final 2/15/2023 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 2/15/2023 SGSOV Approved JOHN KLARIN
Smoke Detectors 2/15/2023 Approved JOHN KLARIN
Final 3/2/2023 Not Ready for Inspection JOHN KLARIN
Green Building Final 3/2/2023 Approved JOHN KLARIN
ELECTRICAL-Final 3/6/2023 Approved JOHN KLARIN
Final 3/6/2023 Corrections Issued JOHN KLARIN
HVAC-Final 3/6/2023 Approved JOHN KLARIN
PLUMBING-Final 3/6/2023 Approved JOHN KLARIN
Service/Power Release 3/6/2023 Approved JOHN KLARIN
Final 4/25/2023 OK to Issue CofO ANSON MAGLASANG