837 1/2 W 51ST ST 90037

Certificate Information: 837 1/2 W 51ST ST 90037

Application / Permit
21010-30000-06944
Plan Check / Job No.
B21WL05810
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New ADU one story 664sf per CA Govt. Code 65852.2(e)(1)(B). Construction per WFPP.** see comments**
Permit Issued
Issued on 7/21/2022
Issuing Office
Current Status
CofO Issued on 7/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2021 APPLICANT
Assigned to Plan Check Engineer 1/6/2022 KAVIAN REFAHI
Corrections Issued 1/8/2022 KAVIAN REFAHI
Plan Check Approved 7/14/2022 RAHEL BEYENE
Issued 7/21/2022 APPLICANT
Building Plans Picked Up 8/2/2022 APPLICANT
CofO in Progress 7/9/2024 DAVID FEILER
CofO Issued 7/9/2024 DEROLD HAUFF
Permit Finaled 7/9/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/19/2022 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 1/26/2022 KHOUNG LE
Sewer availability Cleared 1/26/2022 KHOUNG LE
Hydrant and Access approval Cleared 3/11/2022 CINDY JOSSELYN
Low Impact Development Cleared 6/22/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 6/28/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/23/2022 Partial Approval SABAS ALONSO
Special/Order Compliance 1/26/2023 Corrections Issued SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 3/8/2023 Partial Approval SABAS ALONSO
Underground Mechanical 3/8/2023 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 3/31/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 3/31/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/24/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/28/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 4/28/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 7/7/2023 Corrections Issued ANTHONY EGSON
HVAC-Rough 7/7/2023 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 7/7/2023 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 8/18/2023 Approved STUART CHAPMAN
ELECTRICAL-Rough 8/18/2023 Approved STUART CHAPMAN
Green Building Rough 8/18/2023 Approved STUART CHAPMAN
HVAC-Rough 8/18/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/18/2023 Partial Approval STUART CHAPMAN
PLUMBING-Rough 8/18/2023 Approved STUART CHAPMAN
Insulation 8/28/2023 Corrections Issued ALIZAH MAYAGOITIA
Drywall Nailing 8/31/2023 Approved SABAS ALONSO
Insulation 8/31/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 9/11/2023 Approved SABAS ALONSO
Underground Mechanical 9/11/2023 Partial Approval SABAS ALONSO
Sewer 9/21/2023 Approved SABAS ALONSO
Underground Mechanical 9/21/2023 Approved SABAS ALONSO
Service/Power Release 3/11/2024 Corrections Issued DAVID FEILER
ELECTRICAL-Final 5/6/2024 Corrections Issued ANTHONY EGSON
Service/Power Release 5/6/2024 Not Ready for Inspection ANTHONY EGSON
Service/Power Release 5/7/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 5/9/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Final 5/9/2024 Corrections Issued CRAIG DAVIS
Final 5/20/2024 Not Ready for Inspection CRAIG DAVIS
Green Building Final 5/20/2024 Not Ready for Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 5/20/2024 SGSOV Not Ready CRAIG DAVIS
Service/Power Release 5/20/2024 Partial Approval CRAIG DAVIS
Smoke Detectors 5/20/2024 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Final 6/27/2024 Approved DAVID FEILER
Final 6/27/2024 Corrections Issued DAVID FEILER
Green Building Final 6/27/2024 Approved DAVID FEILER
HVAC-Final 6/27/2024 Approved DAVID FEILER
PLUMBING-Final 6/27/2024 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 6/27/2024 SGSOV Approved DAVID FEILER
Service/Power Release 6/27/2024 Not Required DAVID FEILER
Smoke Detectors 6/27/2024 Approved DAVID FEILER
Final 7/9/2024 OK to Issue CofO DAVID FEILER