225 N HOMEWOOD ROAD 90049

Certificate Information: 225 N HOMEWOOD ROAD 90049

Application / Permit
21010-30000-06940
Plan Check / Job No.
B21WL05808
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
(N) Recreational Room
Permit Issued
Issued on 7/28/2022
Issuing Office
Current Status
CofO Issued on 12/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2022 DAVID CASTILLO
Corrections Issued 1/27/2022 DAVID CASTILLO
Quality Review Completed 2/14/2022 CHIHARU SUZUKI
Applicant returned to address corrections 5/20/2022 DAVID CASTILLO
Applicant returned to address corrections 5/31/2022 DAVID CASTILLO
Applicant returned to address corrections 7/18/2022 DAVID CASTILLO
Plan Check Approved 7/28/2022 DAVID CASTILLO
Issued 7/28/2022 APPLICANT
Building Plans Picked Up 7/29/2022 APPLICANT
CofO in Progress 12/5/2023 KEVIN SARGSYAN
Permit Finaled 12/18/2023 DANIEL ORRANTE
CofO Issued 12/18/2023 DANIEL ORRANTE
Permit Finaled 12/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 5/2/2022 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 5/2/2022 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 5/2/2022 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 5/2/2022 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 5/2/2022 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 5/4/2022 DENNIS BRAGIN
Sewer availability Cleared 5/4/2022 DENNIS BRAGIN
Construction near power lines Cleared 5/17/2022 WALTER RAMIREZ
Hydrant and Access approval Cleared 5/20/2022 CINDY JOSSELYN
Low Impact Development Cleared 6/28/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 7/4/2022 DENNIS BRAGIN
Grading Pre-Inspection Cleared 7/18/2022 DAVID CASTILLO

Contact Information

Architect Rigo, De Righi, Fabio N; Lic. No.: C27735 226 S BEVERLY DRIVE #220      BEVERLY HILLS, CA 90212
Contractor Foster D A Construction; Lic. No.: 673613-B P O BOX 1699      THOUSAND OAKS, CA 91358
Engineer Khoury,, Nader Bulos; Lic. No.: C61402 1278 GLENNEYRE ST 201      LAGUNA BEACH, CA 92651
Engineer Tran,, Quang Tai; Lic. No.: C70929 355 N LANTANA ST 333      CAMARILLO, CA 93010

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/25/2022 Partial Inspection JUAN VALENZUELA
Underground Mechanical 8/30/2022 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 9/8/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 9/12/2022 Not Ready for Inspection BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 9/12/2022 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 9/13/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 9/15/2022 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 9/15/2022 Approved JUAN VALENZUELA
PLUMBING-Rough 12/2/2022 Approved JUAN VALENZUELA
ELECTRICAL-Rough 12/6/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 12/9/2022 Not Ready for Inspection DAVID FEILER
Sewer 12/9/2022 Approved DAVID FEILER
Underground Mechanical 12/9/2022 Partial Approval DAVID FEILER
ELECTRICAL-Rough 1/18/2023 Approved KEVIN SARGSYAN
PLUMBING-Rough 1/18/2023 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/16/2023 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 3/7/2023 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 3/7/2023 Not Ready for Inspection KEVIN SARGSYAN
Verify Sprinkler Sign Off 3/7/2023 Approved KEVIN SARGSYAN
Drywall Nailing 3/9/2023 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 3/13/2023 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 3/15/2023 Approved KEVIN SARGSYAN
Green Building Rough 3/15/2023 Approved KEVIN SARGSYAN
Insulation 3/16/2023 Approved KEVIN SARGSYAN
Drywall Nailing 3/20/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 5/4/2023 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 5/10/2023 Partial Approval MICHAEL PELHAM
Insulation 5/11/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 5/11/2023 Approved JESUS RODRIGUEZ
Final 11/29/2023 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 11/29/2023 Approved KEVIN SARGSYAN
Green Building Final 11/29/2023 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 11/29/2023 SGSOV Not Ready KEVIN SARGSYAN
Service/Power Release 11/29/2023 Not Required KEVIN SARGSYAN
Smoke Detectors 11/29/2023 Approved KEVIN SARGSYAN
Final 12/4/2023 OK to Issue CofO KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/4/2023 SGSOV Approved KEVIN SARGSYAN