152-152 1/2 W 46TH ST 90037

Certificate Information: 152-152 1/2 W 46TH ST 90037

Application / Permit
21010-30000-06924
Plan Check / Job No.
B21WL05799
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 2-story duplex with attached 1-car garage in front and 2-car garage in the back
Permit Issued
Issued on 11/18/2022
Issuing Office
Current Status
CofO Issued on 5/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2022 APPLICANT
Assigned to Plan Check Engineer 2/3/2022 KAVIAN REFAHI
Corrections Issued 2/7/2022 KAVIAN REFAHI
Quality Review Completed 2/14/2022 FELIX FIGUEROA
Applicant returned to address corrections 9/8/2022 KAVIAN REFAHI
Plan Check Approved 9/14/2022 KAVIAN REFAHI
Building Plans Picked Up 9/14/2022 APPLICANT
Issued 11/18/2022 APPLICANT
CofO in Progress 5/23/2024 ALEJANDRO DE ARTOLA
CofO Issued 5/29/2024 DEROLD HAUFF
Permit Finaled 5/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/23/2022 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 3/24/2022 ERIK BEASLEY
Sewer availability Cleared 3/24/2022 ERIK BEASLEY
Hydrant and Access approval Cleared 4/5/2022 LARRY REDDEN
Low Impact Development Cleared 8/1/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 8/3/2022 ERIK BEASLEY

Contact Information

Contractor Cswf Construction Inc; Lic. No.: 1021458-B 15831 SAN JOSE AVE      LA PUENTE, CA
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/23/2022 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 12/23/2022 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 1/12/2023 Corrections Issued BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 1/13/2023 Approved BRENDAN MORELLI
Special/Order Compliance 1/13/2023 Partial Inspection RUBEN SALAS
Sewer 1/27/2023 Corrections Issued BRENDAN MORELLI
Sewer 1/30/2023 Corrections Issued BRENDAN MORELLI
Sewer 2/1/2023 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 2/9/2023 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 3/31/2023 Corrections Issued MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Partial Approval BRENDAN MORELLI
HVAC-Rough 4/13/2023 Approved BRENDAN MORELLI
PLUMBING-Rough 4/13/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 4/19/2023 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 4/19/2023 Approved BRENDAN MORELLI
Green Building Rough 4/19/2023 Not Ready for Inspection BRENDAN MORELLI
Verify Sprinkler Sign Off 4/19/2023 Approved BRENDAN MORELLI
Wood Frame 4/19/2023 Not Ready for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 4/25/2023 Approved BRENDAN MORELLI
Green Building Rough 4/25/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 4/25/2023 Partial Approval BRENDAN MORELLI
Interior/Exterior Lathing 5/17/2023 Approved BRENDAN MORELLI
PLUMBING-Rough 5/17/2023 Approved BRENDAN MORELLI
Insulation 6/1/2023 Approved BRENDAN MORELLI
Drywall Nailing 6/8/2023 Corrections Issued BRENDAN MORELLI
Drywall Nailing 6/13/2023 Corrections Issued BRENDAN MORELLI
Drywall Nailing 6/16/2023 Approved RUBEN SALAS
Footing/Foundation/Slab 10/20/2023 Not Ready for Inspection ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/22/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/22/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 4/22/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 4/22/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 4/22/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 4/22/2024 SGSOV Not Ready ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 5/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/10/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 5/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 5/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 5/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/15/2024 Approved ALEJANDRO DE ARTOLA
Final 5/15/2024 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 5/15/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 5/15/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 5/15/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 5/15/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 5/15/2024 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 5/15/2024 Approved ALEJANDRO DE ARTOLA
Final 5/16/2024 Corrections Issued ANTHONY EGSON
Gas Test 5/16/2024 Approved ANTHONY EGSON
PLUMBING-Final 5/16/2024 Approved ANTHONY EGSON
Service/Power Release 5/16/2024 Corrections Issued ANTHONY EGSON
Pre-Inspection 5/17/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 5/21/2024 OK to Issue CofO ALEJANDRO DE ARTOLA
Service/Power Release 5/21/2024 Approved ALEJANDRO DE ARTOLA