1200 N GETTY CENTER DR 90049
Certificate Information: 1200 N GETTY CENTER DR 90049
- Application / Permit
- 21010-30000-06875
- Plan Check / Job No.
- B21WL05786
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- NEW RESTROOM BUILDING FOR GETTY CENTER AND STRIPING OF NEW PARKING LOTS A & B
- Permit Issued
- Issued on 9/14/2023
- Issuing Office
- Current Status
- CofO Issued on 8/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | TARIK SAOUD |
| Corrections Issued | 2/16/2022 | TARIK SAOUD |
| Quality Review Completed | 3/4/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
| Applicant returned to address corrections | 8/28/2023 | REZA HAGHIGHAT |
| Plan Check Approved | 9/14/2023 | REZA HAGHIGHAT |
| Issued | 9/14/2023 | APPLICANT |
| CofO in Progress | 8/21/2025 | DANIEL VARNUM |
| Permit Finaled | 8/26/2025 | DAVID TSAU |
| CofO Issued | 8/26/2025 | DAVID TSAU |
| Permit Finaled | 8/26/2025 | DAVID TSAU |
Permit Application Clearance Information
| ZA Case | Cleared | 4/13/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 4/13/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 4/13/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 4/13/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 4/13/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 4/13/2022 | DANIEL CORONADO |
| ZI | Cleared | 4/21/2022 | DANIEL CORONADO |
| Specific Plan | Cleared | 5/9/2022 | PEDRO AYALA |
| Drainage to Storm Drain | Cleared | 6/15/2022 | HISASHI KOBAYAKAWA |
| Watercourse | Cleared | 6/15/2022 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2022 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 6/28/2022 | HISASHI KOBAYAKAWA |
| DAS Clearance | Cleared | 6/2/2023 | TARIK SAOUD |
| Hydrant and Access approval | Cleared | 6/8/2023 | KURT CORRAL |
| Miscellaneous | Cleared | 8/17/2023 | LOUIS ORTEGA |
| Prkng lot landscape/Water mgmt | Cleared | 8/17/2023 | LOUIS ORTEGA |
| Low Impact Development | Cleared | 8/24/2023 | SARAH YOUSSEF |
| Green Code | Cleared | 9/8/2023 | RICHARD GARCIA |
| Grading Pre-Inspection | Cleared | 9/14/2023 | TARIK SAOUD |
Contact Information
| Architect | Fisher,, Frederick Burt; Lic. No.: C10281 | 12248 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
| Contractor | Rudolph & Sletten Inc; Lic. No.: 198069-B | 120 CONSTITUTION DRIVE MENLO PARK, CA 94025 |
| Engineer | Davis,, Richard Hays; Lic. No.: C48082 | 2015 CANTATA DR LOS ANGELES, CA 90068 |
| Engineer | Nishi,, Thomas Yoshimasa; Lic. No.: S4030 | 1615 BUCKINGHAM RD LOS ANGELES, CA 90019 |
Inspector Information
| DANIEL VARNUM, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/13/2023 | Partial Approval | CASIMIR BRITTON |
| Deputy Reinf. Concrete | 7/23/2024 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 7/23/2024 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 7/24/2024 | Approved | DERRICK SPENCER |
| Green Building Rough | 8/9/2024 | Approved | DERRICK SPENCER |
| Verify Sprinkler Sign Off | 8/9/2024 | Approved | DERRICK SPENCER |
| Wood Frame | 8/9/2024 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/27/2024 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/28/2024 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/30/2024 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 9/5/2024 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 9/18/2024 | Conditional Approval | DANIEL VARNUM |
| Masonry Wall/Backfill | 9/18/2024 | Partial Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 9/19/2024 | Conditional Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 9/20/2024 | Conditional Approval | ALAN NOVAK |
| Drywall Nailing | 9/26/2024 | Approved | DANIEL VARNUM |
| Light Gage Steel Frame | 9/26/2024 | Approved | DANIEL VARNUM |
| Footing/Foundation/Slab | 10/7/2024 | Partial Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 10/16/2024 | Partial Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 11/26/2024 | Approved | DANIEL VARNUM |
| Deputy Reinf. Concrete | 3/6/2025 | Conditional Approval | DANIEL VARNUM |
| Special/Order Compliance | 3/6/2025 | Partial Inspection | DANIEL VARNUM |
| Pre-Inspection | 4/4/2025 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 6/3/2025 | SGSOV Not Ready | DANIEL VARNUM |
| Final | 6/4/2025 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 6/30/2025 | Partial Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 6/30/2025 | Approved | DANIEL VARNUM |
| Green Building Final | 6/30/2025 | Approved | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 6/30/2025 | SGSOV No Gas | DANIEL VARNUM |
| Smoke Detectors | 6/30/2025 | Approved | DANIEL VARNUM |
| Deputy Reinf. Concrete | 8/21/2025 | Conditional Approval | DANIEL VARNUM |
| Final | 8/21/2025 | OK to Issue CofO | DANIEL VARNUM |