206-206 1/2 N UNION AVE 90026
Certificate Information: 206-206 1/2 N UNION AVE 90026
- Application / Permit
- 21010-30000-06848
- Plan Check / Job No.
- B21WL05776
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 3 Story Duplex (Building C) and private garage Fire Sprinklers required.
- Permit Issued
- Issued on 5/4/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 2/17/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 2/18/2022 | SEAN DANG |
| Building Plans Picked Up | 2/24/2022 | APPLICANT |
| Plan Check Approved | 4/7/2023 | ARSALAN SHABESTARI |
| Issued | 5/4/2023 | APPLICANT |
| CofO in Progress | 1/14/2026 | HAMIK HARTOUNIAN |
| No Progress | 1/14/2026 | DEROLD HAUFF |
| CofO in Progress | 1/14/2026 | DEROLD HAUFF |
| No Progress | 1/27/2026 | OSVALDO PARAMO |
| CofO in Progress | 1/27/2026 | OSVALDO PARAMO |
| CofO in Progress | 1/27/2026 | OSVALDO PARAMO |
| Permit Finaled | 1/27/2026 | DEROLD HAUFF |
| CofO Issued | 1/27/2026 | DEROLD HAUFF |
| Permit Finaled | 1/27/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/7/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 3/8/2022 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 4/14/2022 | KURT CORRAL |
| ZA Case | Cleared | 6/3/2022 | DANG NGUYEN |
| Frnt yard landscape/Water mgmt | Cleared | 8/8/2022 | RYAN LY |
| Low Impact Development | Cleared | 10/5/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 10/18/2022 | STEVE MELGAR |
| Permit | Cleared | 12/12/2022 | ALBERT TAM |
| GPI Written Notices | Cleared | 4/7/2023 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 4/7/2023 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 1/2/2024 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 1/2/2024 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 1/26/2024 | Approved | THOMAS LOGRASSO |
| METHANE-Barrier | 1/26/2024 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2024 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 3/5/2024 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2024 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Conditional Approval | SCOTT FINNILA |
| Special/Order Compliance | 7/9/2024 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Approved | LUIS CASTRO |
| HVAC-Rough | 10/17/2024 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 11/21/2024 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Rough | 11/21/2024 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 11/27/2024 | Approved | LUIS CASTRO |
| METHANE-Rough | 11/27/2024 | Approved | LUIS CASTRO |
| Shower Pan | 11/27/2024 | Not Ready for Inspection | LUIS CASTRO |
| BUILDING-Rough-Frame | 12/3/2024 | Approved | LUIS CASTRO |
| Green Building Rough | 12/3/2024 | Approved | LUIS CASTRO |
| Verify Sprinkler Sign Off | 12/3/2024 | Approved | LUIS CASTRO |
| Insulation | 12/16/2024 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 12/27/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 12/27/2024 | Approved | ALEX COLIN |
| Gas Test | 9/29/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 9/29/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 9/29/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 10/29/2025 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Final | 10/29/2025 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Final | 11/4/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 11/4/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 12/23/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/23/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 12/23/2025 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 12/23/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 12/23/2025 | Not Required | HAMIK HARTOUNIAN |
| Smoke Detectors | 12/23/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 1/8/2026 | Conditional Approval | HAMIK HARTOUNIAN |
| Smoke Detectors | 1/8/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 1/14/2026 | OK to Issue CofO | HAMIK HARTOUNIAN |