206-206 1/2 N UNION AVE 90026

Certificate Information: 206-206 1/2 N UNION AVE 90026

Application / Permit
21010-30000-06848
Plan Check / Job No.
B21WL05776
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
3 Story Duplex (Building C) and private garage Fire Sprinklers required.
Permit Issued
Issued on 5/4/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2021 APPLICANT
Assigned to Plan Check Engineer 2/3/2022 ARSALAN SHABESTARI
Corrections Issued 2/17/2022 ARSALAN SHABESTARI
Quality Review Completed 2/18/2022 SEAN DANG
Building Plans Picked Up 2/24/2022 APPLICANT
Plan Check Approved 4/7/2023 ARSALAN SHABESTARI
Issued 5/4/2023 APPLICANT
CofO in Progress 1/14/2026 HAMIK HARTOUNIAN
No Progress 1/14/2026 DEROLD HAUFF
CofO in Progress 1/14/2026 DEROLD HAUFF
No Progress 1/27/2026 OSVALDO PARAMO
CofO in Progress 1/27/2026 OSVALDO PARAMO
CofO in Progress 1/27/2026 OSVALDO PARAMO
Permit Finaled 1/27/2026 DEROLD HAUFF
CofO Issued 1/27/2026 DEROLD HAUFF
Permit Finaled 1/27/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/7/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 3/8/2022 TREVOR QUAN
Sewer availability Cleared 3/8/2022 TREVOR QUAN
Hydrant and Access approval Cleared 4/14/2022 KURT CORRAL
ZA Case Cleared 6/3/2022 DANG NGUYEN
Frnt yard landscape/Water mgmt Cleared 8/8/2022 RYAN LY
Low Impact Development Cleared 10/5/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 10/18/2022 STEVE MELGAR
Permit Cleared 12/12/2022 ALBERT TAM
GPI Written Notices Cleared 4/7/2023 ARSALAN SHABESTARI
Grading Pre-Inspection Cleared 4/7/2023 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 1/2/2024 Approved THOMAS LOGRASSO
PLUMBING-Rough 1/2/2024 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 1/26/2024 Approved THOMAS LOGRASSO
METHANE-Barrier 1/26/2024 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 3/5/2024 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 3/5/2024 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 3/19/2024 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/30/2024 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Conditional Approval SCOTT FINNILA
Special/Order Compliance 7/9/2024 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/30/2024 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/4/2024 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 10/17/2024 Approved LUIS CASTRO
HVAC-Rough 10/17/2024 Approved LUIS CASTRO
ELECTRICAL-Rough 11/21/2024 Corrections Issued LUIS CASTRO
PLUMBING-Rough 11/21/2024 Approved LUIS CASTRO
ELECTRICAL-Rough 11/27/2024 Approved LUIS CASTRO
METHANE-Rough 11/27/2024 Approved LUIS CASTRO
Shower Pan 11/27/2024 Not Ready for Inspection LUIS CASTRO
BUILDING-Rough-Frame 12/3/2024 Approved LUIS CASTRO
Green Building Rough 12/3/2024 Approved LUIS CASTRO
Verify Sprinkler Sign Off 12/3/2024 Approved LUIS CASTRO
Insulation 12/16/2024 Approved HAMIK HARTOUNIAN
Drywall Nailing 12/27/2024 Approved ALEX COLIN
Interior/Exterior Lathing 12/27/2024 Approved ALEX COLIN
Gas Test 9/29/2025 Approved HAMIK HARTOUNIAN
HVAC-Final 9/29/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Final 9/29/2025 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Final 10/29/2025 Corrections Issued FREDDIE RIVERA
PLUMBING-Final 10/29/2025 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Final 11/4/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Final 11/4/2025 Approved HAMIK HARTOUNIAN
Final 12/23/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/23/2025 Approved HAMIK HARTOUNIAN
Green Building Final 12/23/2025 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 12/23/2025 SGSOV Approved HAMIK HARTOUNIAN
Service/Power Release 12/23/2025 Not Required HAMIK HARTOUNIAN
Smoke Detectors 12/23/2025 Corrections Issued HAMIK HARTOUNIAN
Final 1/8/2026 Conditional Approval HAMIK HARTOUNIAN
Smoke Detectors 1/8/2026 Approved HAMIK HARTOUNIAN
Final 1/14/2026 OK to Issue CofO HAMIK HARTOUNIAN