541 S WESTGATE AVE 90049
Certificate Information: 541 S WESTGATE AVE 90049
- Application / Permit
- 21010-30000-06808
- Plan Check / Job No.
- B21WL05769
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-Story S.F.D w/Attached Garage
- Permit Issued
- Issued on 8/10/2022
- Issuing Office
- Current Status
- CofO Issued on 2/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | DAVID CASTILLO |
| Corrections Issued | 1/31/2022 | DAVID CASTILLO |
| Quality Review Completed | 2/22/2022 | CHIHARU SUZUKI |
| Plan Check Approved | 7/14/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 8/5/2022 | APPLICANT |
| Issued | 8/10/2022 | APPLICANT |
| CofO in Progress | 2/11/2026 | JUAN VALENZUELA |
| Permit Finaled | 2/11/2026 | RICHARD STEINBACH |
| CofO Issued | 2/11/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/11/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 2/22/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 2/23/2022 | JOSE HERNANDEZ |
| Specific Plan | Cleared | 2/23/2022 | FREDDY GARCIA |
| Hydrant and Access approval | Cleared | 4/15/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 6/22/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/27/2022 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 7/14/2022 | DAVID CASTILLO |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Bowers,, Erik George; Lic. No.: L8571 | 7745 JELLICO AVENUE NORTHRIDGE, CA 91325 |
| Engineer | Le,, Thang Huu; Lic. No.: C63174 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/15/2023 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 11/29/2023 | Conditional Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 1/16/2024 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 2/6/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/6/2025 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 2/24/2025 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 2/24/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 2/24/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 2/24/2025 | Partial Approval | TEMISTOCLES CAAL |
| Special/Order Compliance | 2/24/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 2/24/2025 | Approved | TEMISTOCLES CAAL |
| Insulation | 3/4/2025 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 3/10/2025 | Partial Approval | HERBERT GIRON |
| Drywall Nailing | 3/13/2025 | Approved | KIRK SANDERS |
| Pre-Inspection | 5/30/2025 | Partial Inspection | ARAM AVEDISIAN |
| Shower Pan | 6/3/2025 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 7/11/2025 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 9/9/2025 | Corrections Issued | HERBERT GIRON |
| Gas Test | 9/12/2025 | Approved | HERBERT GIRON |
| HVAC-Final | 9/19/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 9/23/2025 | Approved | HERBERT GIRON |
| HVAC-Final | 9/23/2025 | Approved | HERBERT GIRON |
| PLUMBING-Final | 9/24/2025 | Approved | HERBERT GIRON |
| Final | 10/14/2025 | Corrections Issued | HERBERT GIRON |
| Final | 10/16/2025 | Not Ready for Inspection | HERBERT GIRON |
| Footing/Foundation/Slab | 10/16/2025 | Approved | HERBERT GIRON |
| Green Building Final | 10/16/2025 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 10/16/2025 | SGSOV Approved | HERBERT GIRON |
| Service/Power Release | 10/16/2025 | Not Ready for Inspection | HERBERT GIRON |
| Smoke Detectors | 10/16/2025 | Approved | HERBERT GIRON |
| Final | 2/11/2026 | OK to Issue CofO | JUAN VALENZUELA |
| Service/Power Release | 2/11/2026 | Approved | JUAN VALENZUELA |