19609 W VICTORY BLVD 91335
Certificate Information: 19609 W VICTORY BLVD 91335
- Application / Permit
- 21010-30000-06702
- Plan Check / Job No.
- B21WL05744
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story ADU per LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 4/26/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2022 | HOOMAN HAJIZADEH |
| Corrections Issued | 2/10/2022 | HOOMAN HAJIZADEH |
| Quality Review Completed | 3/3/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 3/10/2023 | HOOMAN HAJIZADEH |
| Plan Check Approved | 3/16/2023 | HOOMAN HAJIZADEH |
| Issued | 4/26/2023 | APPLICANT |
| CofO in Progress | 12/9/2024 | ALEXANDER HANDY |
| No Progress | 1/10/2025 | HENRY KIM |
| CofO in Progress | 1/10/2025 | HENRY KIM |
| CofO Issued | 2/20/2025 | JOHN JANSON |
| Permit Finaled | 2/20/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/17/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/22/2022 | LEE GUILBEAUX |
| ZI | Cleared | 3/3/2022 | RYAN LY |
| Low Impact Development | Cleared | 6/27/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 7/7/2022 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shagirian,, Ashot; Lic. No.: C79415 | 11337 RUNNYMEDE ST SUN VALLEY, CA 91352 |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/19/2023 | Corrections Issued | HORACE FULTZ |
| Footing/Foundation/Slab | 5/19/2023 | Not Ready for Inspection | HORACE FULTZ |
| Sewer | 5/19/2023 | Not Ready for Inspection | HORACE FULTZ |
| Excavation/Setback/Form/Re-Bar | 6/2/2023 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 6/2/2023 | Approved | ALEXANDER HANDY |
| Gas Test | 6/2/2023 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 6/2/2023 | Partial Approval | ALEXANDER HANDY |
| Sewer | 6/2/2023 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 9/8/2023 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 9/8/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2023 | Corrections Issued | ALEXANDER HANDY |
| Green Building Rough | 9/8/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 9/8/2023 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 9/8/2023 | SGSOV Not Ready | ALEXANDER HANDY |
| Underground Mechanical | 9/8/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 9/8/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Wood Frame | 9/8/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Deputy Wood Construction | 9/12/2023 | Conditional Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 9/26/2023 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 9/26/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2023 | Partial Approval | ALEXANDER HANDY |
| Gas Test | 9/26/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Rough | 9/26/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 9/26/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Not Ready | ALEXANDER HANDY |
| Sewer | 9/26/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Underground Mechanical | 9/26/2023 | Approved | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 9/26/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Wood Frame | 9/26/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Rough | 10/4/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Interior/Exterior Lathing | 10/4/2023 | Corrections Issued | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 11/14/2023 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 11/14/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 11/14/2023 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 11/14/2023 | Approved | ALEXANDER HANDY |
| Grounding or Bonding | 12/8/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Insulation | 12/8/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 12/8/2023 | Approved | ALEXANDER HANDY |
| Service/Power Release | 12/8/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Drywall Nailing | 12/26/2023 | Approved | ALEXANDER HANDY |
| Shower Pan | 2/29/2024 | Corrections Issued | ALEXANDER HANDY |
| Shower Pan | 3/5/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 5/21/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 5/21/2024 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 5/21/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 5/21/2024 | SGSOV Approved | ALEXANDER HANDY |
| Service/Power Release | 5/21/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Smoke Detectors | 5/21/2024 | Approved | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 5/21/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 7/26/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 7/26/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 7/26/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 7/26/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Service/Power Release | 7/26/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Special/Order Compliance | 7/26/2024 | Partial Inspection | SCOTT SOBEL |
| BUILDING-Rough-Frame | 12/6/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 12/6/2024 | Approved | ALEXANDER HANDY |
| Final | 12/6/2024 | OK to Issue CofO | ALEXANDER HANDY |
| Footing/Foundation/Slab | 12/6/2024 | Approved | ALEXANDER HANDY |
| Green Building Final | 12/6/2024 | Approved | ALEXANDER HANDY |
| HVAC-Final | 12/6/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 12/6/2024 | Approved | ALEXANDER HANDY |
| Service/Power Release | 12/6/2024 | Approved | ALEXANDER HANDY |
| Special/Order Compliance | 12/27/2024 | Corrections Issued | ALEXANDER HANDY |