2806 S BARRY AVE 90064
Certificate Information: 2806 S BARRY AVE 90064
- Application / Permit
- 21010-30000-06701
- Plan Check / Job No.
- B21WL05741
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and 2-story S.F.D. addition w/ roof trusses
- Permit Issued
- Issued on 5/11/2022
- Issuing Office
- Current Status
- CofO Issued on 4/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2022 | HOOMAN HAJIZADEH |
| Corrections Issued | 1/13/2022 | HOOMAN HAJIZADEH |
| Quality Review Completed | 2/4/2022 | CHIHARU SUZUKI |
| Plan Check Approved | 4/29/2022 | HOOMAN HAJIZADEH |
| Issued | 5/11/2022 | APPLICANT |
| Building Plans Picked Up | 5/12/2022 | APPLICANT |
| CofO in Progress | 4/5/2023 | JOHNNY MIRANDA |
| Permit Finaled | 4/14/2023 | DANIEL ORRANTE |
| CofO Issued | 4/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 1/15/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 1/17/2022 | JOSE HERNANDEZ |
| Low Impact Development | Cleared | 3/11/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/13/2022 | JOSE RODRIGUEZ |
| Trees in Parkway | Cleared | 4/21/2022 | ADALBERTO VERA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Gomez A Landscaping Designs; Lic. No.: 1011989-C27 | P O BOX 1387 SIMI VALLEY, CA 93062 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/14/2022 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/21/2022 | Partial Approval | JOHNNY MIRANDA |
| Underground Mechanical | 6/21/2022 | Partial Approval | JOHNNY MIRANDA |
| Sewer | 6/28/2022 | Approved | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 6/29/2022 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 6/29/2022 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 7/14/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Deputy Wood Construction | 8/8/2022 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Wood Construction | 8/10/2022 | Conditional Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2022 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 8/17/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 8/23/2022 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Corrections Issued | JOHNNY MIRANDA |
| Deputy Wood Construction | 8/24/2022 | Approved | MICHAEL PELHAM |
| HVAC-Rough | 8/25/2022 | Approved | JOHNNY MIRANDA |
| Shower Pan | 8/26/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 9/7/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 9/7/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/8/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Insulation | 9/27/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/27/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Insulation | 9/30/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/30/2022 | Partial Approval | JOHNNY MIRANDA |
| Pre-Inspection | 9/30/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 10/12/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 10/12/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 10/12/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 2/21/2023 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 2/21/2023 | Approved | JOHNNY MIRANDA |
| Final | 2/21/2023 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 2/21/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Final | 2/21/2023 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 2/21/2023 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 2/21/2023 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 2/21/2023 | Approved | JOHNNY MIRANDA |
| Gas Test | 3/22/2023 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 3/22/2023 | Approved | JOHNNY MIRANDA |
| Final | 4/4/2023 | OK to Issue CofO | JOHNNY MIRANDA |
| Gas Test | 4/4/2023 | Approved | JOHNNY MIRANDA |
| Green Building Final | 4/4/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 4/4/2023 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 4/11/2023 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 4/13/2023 | Approved | MICHAEL PELHAM |