12725 W SUNSET BLVD 90049

Certificate Information: 12725 W SUNSET BLVD 90049

Application / Permit
21010-30000-06698
Plan Check / Job No.
B21WL05738
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 1-story S.F.D. w/ att. garage. Fully equipped w/fire sprinklers NFPA 13R
Permit Issued
Issued on 8/19/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2021 APPLICANT
Assigned to Plan Check Engineer 1/7/2022 ALFREDO JARA
Corrections Issued 1/11/2022 ALFREDO JARA
Quality Review Completed 2/7/2022 CHIHARU SUZUKI
Plan Check Approved 8/10/2022 ALFREDO JARA
Issued 8/19/2022 APPLICANT
CofO in Progress 3/3/2026 KEVIN SARGSYAN
Permit Finaled 3/16/2026 RICHARD STEINBACH
CofO Issued 3/16/2026 RICHARD STEINBACH
Permit Finaled 3/16/2026 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 2/28/2022 DINAH GARIN
Sewer availability Cleared 2/28/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/12/2022 DINAH GARIN
Trees in Parkway Cleared 4/19/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 5/2/2022 KURT CORRAL
Low Impact Development Cleared 5/4/2022 KHAING AYE
Roof/Waste drainage to street Cleared 5/10/2022 DINAH GARIN
GPI Written Notices Cleared 6/7/2022 ALFREDO JARA
Grading Pre-Inspection Cleared 6/7/2022 ALFREDO JARA

Contact Information

Architect Rios,, Mark William; Lic. No.: C15744 3101 W EXPOSITION PLACE      LOS ANGELES, CA 90018
Contractor Fort Hill Construction; Lic. No.: 414092-B 12711 VENTURA BLVD STE 390      STUDIO CITY, CA 91604
Engineer Kwan,, Denny Chi-Ho; Lic. No.: S4887 5638 NEWFIELDS LN      DUBLIN, CA 94568
Engineer White,, William Michael; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/15/2022 Partial Inspection JUAN VALENZUELA
Footing/Foundation/Slab 11/28/2022 Partial Inspection KENNETH NAGLE
Masonry Wall/Backfill 11/28/2022 Partial Inspection KENNETH NAGLE
Underground Mechanical 1/13/2023 Partial Inspection JUAN VALENZUELA
Sewer 5/2/2023 Corrections Issued KEVIN SARGSYAN
Sewer 5/10/2023 Approved KEVIN SARGSYAN
Underground Mechanical 5/15/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 5/18/2023 Partial Approval KEVIN SARGSYAN
HVAC-Rough 8/7/2023 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 8/16/2023 Partial Approval ARAM AVEDISIAN
Reinforced Concrete Frame 8/30/2023 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 9/12/2023 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 9/14/2023 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 9/14/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 9/18/2023 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 11/1/2023 Approved ARAM AVEDISIAN
Gas Test 11/21/2023 Partial Approval KEVIN SARGSYAN
Sewer 11/21/2023 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 12/4/2023 Partial Approval KEVIN SARGSYAN
Underground Mechanical 12/11/2023 Partial Approval KEVIN SARGSYAN
Gas Test 12/13/2023 Partial Approval KEVIN SARGSYAN
Underground Mechanical 12/13/2023 Approved KEVIN SARGSYAN
Drywall Nailing 1/18/2024 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/20/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/26/2024 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/10/2024 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Partial Approval EVAN COOPER
HVAC-Rough 8/5/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 8/6/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 8/8/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 8/26/2024 Approved KEVIN SARGSYAN
Drywall Nailing 9/19/2024 Partial Approval EVAN COOPER
Interior/Exterior Lathing 10/15/2024 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 10/25/2024 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 10/28/2024 Corrections Issued KEVIN SARGSYAN
Green Building Rough 10/28/2024 Not Ready for Inspection KEVIN SARGSYAN
Verify Sprinkler Sign Off 10/28/2024 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 11/6/2024 Approved JESUS RODRIGUEZ
Green Building Rough 11/6/2024 Approved JESUS RODRIGUEZ
Insulation 11/19/2024 Corrections Issued KEVIN SARGSYAN
Insulation 11/27/2024 Not Ready for Inspection KEVIN SARGSYAN
Insulation 12/4/2024 Approved KEVIN SARGSYAN
Shower Pan 12/10/2024 Approved KEVIN SARGSYAN
Drywall Nailing 12/11/2024 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 3/27/2025 Approved BOBBY KEY
ELECTRICAL-Final 11/21/2025 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 11/24/2025 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 11/25/2025 Partial Approval KEVIN SARGSYAN
HVAC-Final 12/4/2025 Corrections Issued KEVIN SARGSYAN
HVAC-Final 12/5/2025 Approved KEVIN SARGSYAN
PLUMBING-Final 12/5/2025 Approved KEVIN SARGSYAN
Service/Power Release 12/24/2025 Approved KENNETH NAGLE
ELECTRICAL-Final 12/29/2025 Approved KEVIN SARGSYAN
Final 3/3/2026 OK to Issue CofO KEVIN SARGSYAN
Green Building Final 3/3/2026 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/3/2026 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 3/3/2026 Approved KEVIN SARGSYAN