10567 W HOLMAN AVE 90024

Certificate Information: 10567 W HOLMAN AVE 90024

Application / Permit
21010-30000-06689
Plan Check / Job No.
B21WL05720
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
build new 1 story 800sft adu per state law
Permit Issued
Issued on 1/19/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2021 APPLICANT
Assigned to Plan Check Engineer 1/7/2022 YASHAR EMAMI
Corrections Issued 1/13/2022 YASHAR EMAMI
Quality Review Completed 2/7/2022 CHIHARU SUZUKI
Applicant returned to address corrections 4/26/2022 YASHAR EMAMI
Applicant returned to address corrections 11/7/2022 YASHAR EMAMI
Building Plans Picked Up 11/8/2022 APPLICANT
Applicant returned to address corrections 11/29/2022 YASHAR EMAMI
Plan Check Approved 1/18/2023 YASHAR EMAMI
Issued 1/19/2023 APPLICANT
CofO in Progress 11/3/2025 ANDREW NAVE
Permit Finaled 11/4/2025 RICHARD STEINBACH
CofO Issued 11/4/2025 RICHARD STEINBACH
Permit Finaled 11/4/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 7/18/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 7/19/2022 CINDY QI
Sewer availability Cleared 7/19/2022 CINDY QI
Construction near power lines Cleared 9/18/2022 RIDWAN HARDY
Specific Plan Cleared 10/12/2022 EDUARDO HERMOSO
Hydrant and Access approval Cleared 10/20/2022 KURT CORRAL
Low Impact Development Cleared 10/24/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 10/24/2022 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Tagudar,, Fred; Lic. No.: C33612 255 W 5TH ST APT 706      SAN PEDRO, CA 90731
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Methane Barrier 5/19/2023 Conditional Approval JESUS PINEDA
Footing/Foundation/Slab 5/23/2023 Corrections Issued JESUS PINEDA
METHANE-Barrier 5/23/2023 Corrections Issued JESUS PINEDA
METHANE-Subgrade 5/23/2023 Corrections Issued JESUS PINEDA
PLUMBING-Rough 5/23/2023 Corrections Issued JESUS PINEDA
Special/Order Compliance 5/23/2023 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 5/25/2023 Conditional Approval JESUS PINEDA
METHANE-Subgrade 5/25/2023 Partial Approval JESUS PINEDA
PLUMBING-Rough 5/25/2023 Partial Approval JESUS PINEDA
Pre-Inspection 5/25/2023 Partial Inspection RICHARD STEINBACH
Sewer 5/25/2023 Approved JESUS PINEDA
Footing/Foundation/Slab 6/15/2023 Partial Inspection JESUS PINEDA
METHANE-Subgrade 6/15/2023 Approved JESUS PINEDA
Footing/Foundation/Slab 7/5/2023 Approved JEREMY TODD
METHANE-Barrier 7/5/2023 Approved JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Corrections Issued BEN MOLSTAD
METHANE-Rough 11/14/2023 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 12/5/2023 Not Ready for Inspection BEN MOLSTAD
Gas Test 12/5/2023 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 12/5/2023 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 12/11/2023 Corrections Issued BEN MOLSTAD
BUILDING-Rough-Frame 12/13/2023 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 12/13/2023 Not Ready for Inspection BEN MOLSTAD
METHANE-Rough 12/13/2023 Conditional Approval BEN MOLSTAD
Verify Sprinkler Sign Off 12/13/2023 Approved BEN MOLSTAD
Interior/Exterior Lathing 1/2/2024 Approved BEN MOLSTAD
Shower Pan 1/2/2024 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 1/22/2024 Corrections Issued BEN MOLSTAD
Green Building Rough 1/22/2024 Approved BEN MOLSTAD
HVAC-Rough 1/22/2024 Corrections Issued BEN MOLSTAD
METHANE-Rough 1/22/2024 Approved BEN MOLSTAD
BUILDING-Rough-Frame 1/25/2024 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/30/2024 Corrections Issued BEN MOLSTAD
Special/Order Compliance 1/30/2024 Partial Approval ASHLEY THOMPSON
Insulation 2/12/2024 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 2/21/2024 Approved ASHLEY THOMPSON
Drywall Nailing 2/21/2024 Partial Approval ASHLEY THOMPSON
Insulation 2/21/2024 Approved ASHLEY THOMPSON
Drywall Nailing 2/28/2024 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 2/28/2024 Partial Approval ASHLEY THOMPSON
Shower Pan 2/28/2024 Corrections Issued ASHLEY THOMPSON
Final 10/29/2024 Corrections Issued KIRK SANDERS
Green Building Final 10/29/2024 Approved KIRK SANDERS
METHANE-Final 10/29/2024 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 10/29/2024 SGSOV Approved KIRK SANDERS
Service/Power Release 10/29/2024 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 10/29/2024 Approved KIRK SANDERS
Final 12/2/2024 Not Ready for Inspection KIRK SANDERS
METHANE-Final 12/2/2024 Corrections Issued KIRK SANDERS
Service/Power Release 12/2/2024 Not Ready for Inspection KIRK SANDERS
Final 2/3/2025 Corrections Issued KIRK SANDERS
METHANE-Final 2/3/2025 Corrections Issued KIRK SANDERS
Service/Power Release 2/3/2025 Not Ready for Inspection KIRK SANDERS
Final 3/14/2025 Not Ready for Inspection KIRK SANDERS
METHANE-Final 3/14/2025 Approved KIRK SANDERS
Service/Power Release 3/14/2025 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Final 10/29/2025 Approved MICHAEL ALLEN
Final 10/29/2025 Conditional Approval MICHAEL ALLEN
HVAC-Final 10/29/2025 Approved MICHAEL ALLEN
PLUMBING-Final 10/29/2025 Approved MICHAEL ALLEN
Service/Power Release 10/29/2025 Approved MICHAEL ALLEN
Final 11/3/2025 OK to Issue CofO ANDREW NAVE