10567 W HOLMAN AVE 90024
Certificate Information: 10567 W HOLMAN AVE 90024
- Application / Permit
- 21010-30000-06689
- Plan Check / Job No.
- B21WL05720
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- build new 1 story 800sft adu per state law
- Permit Issued
- Issued on 1/19/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2022 | YASHAR EMAMI |
| Corrections Issued | 1/13/2022 | YASHAR EMAMI |
| Quality Review Completed | 2/7/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 4/26/2022 | YASHAR EMAMI |
| Applicant returned to address corrections | 11/7/2022 | YASHAR EMAMI |
| Building Plans Picked Up | 11/8/2022 | APPLICANT |
| Applicant returned to address corrections | 11/29/2022 | YASHAR EMAMI |
| Plan Check Approved | 1/18/2023 | YASHAR EMAMI |
| Issued | 1/19/2023 | APPLICANT |
| CofO in Progress | 11/3/2025 | ANDREW NAVE |
| Permit Finaled | 11/4/2025 | RICHARD STEINBACH |
| CofO Issued | 11/4/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/4/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/18/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2022 | CINDY QI |
| Sewer availability | Cleared | 7/19/2022 | CINDY QI |
| Construction near power lines | Cleared | 9/18/2022 | RIDWAN HARDY |
| Specific Plan | Cleared | 10/12/2022 | EDUARDO HERMOSO |
| Hydrant and Access approval | Cleared | 10/20/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 10/24/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 10/24/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tagudar,, Fred; Lic. No.: C33612 | 255 W 5TH ST APT 706 SAN PEDRO, CA 90731 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Methane Barrier | 5/19/2023 | Conditional Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 5/23/2023 | Corrections Issued | JESUS PINEDA |
| METHANE-Barrier | 5/23/2023 | Corrections Issued | JESUS PINEDA |
| METHANE-Subgrade | 5/23/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 5/23/2023 | Corrections Issued | JESUS PINEDA |
| Special/Order Compliance | 5/23/2023 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 5/25/2023 | Conditional Approval | JESUS PINEDA |
| METHANE-Subgrade | 5/25/2023 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 5/25/2023 | Partial Approval | JESUS PINEDA |
| Pre-Inspection | 5/25/2023 | Partial Inspection | RICHARD STEINBACH |
| Sewer | 5/25/2023 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 6/15/2023 | Partial Inspection | JESUS PINEDA |
| METHANE-Subgrade | 6/15/2023 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 7/5/2023 | Approved | JEREMY TODD |
| METHANE-Barrier | 7/5/2023 | Approved | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Corrections Issued | BEN MOLSTAD |
| METHANE-Rough | 11/14/2023 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 12/5/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Gas Test | 12/5/2023 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 12/5/2023 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 12/11/2023 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 12/13/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 12/13/2023 | Not Ready for Inspection | BEN MOLSTAD |
| METHANE-Rough | 12/13/2023 | Conditional Approval | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 12/13/2023 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 1/2/2024 | Approved | BEN MOLSTAD |
| Shower Pan | 1/2/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 1/22/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 1/22/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 1/22/2024 | Corrections Issued | BEN MOLSTAD |
| METHANE-Rough | 1/22/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 1/25/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/30/2024 | Corrections Issued | BEN MOLSTAD |
| Special/Order Compliance | 1/30/2024 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 2/12/2024 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 2/21/2024 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 2/21/2024 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 2/21/2024 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 2/28/2024 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 2/28/2024 | Partial Approval | ASHLEY THOMPSON |
| Shower Pan | 2/28/2024 | Corrections Issued | ASHLEY THOMPSON |
| Final | 10/29/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 10/29/2024 | Approved | KIRK SANDERS |
| METHANE-Final | 10/29/2024 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/29/2024 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 10/29/2024 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 10/29/2024 | Approved | KIRK SANDERS |
| Final | 12/2/2024 | Not Ready for Inspection | KIRK SANDERS |
| METHANE-Final | 12/2/2024 | Corrections Issued | KIRK SANDERS |
| Service/Power Release | 12/2/2024 | Not Ready for Inspection | KIRK SANDERS |
| Final | 2/3/2025 | Corrections Issued | KIRK SANDERS |
| METHANE-Final | 2/3/2025 | Corrections Issued | KIRK SANDERS |
| Service/Power Release | 2/3/2025 | Not Ready for Inspection | KIRK SANDERS |
| Final | 3/14/2025 | Not Ready for Inspection | KIRK SANDERS |
| METHANE-Final | 3/14/2025 | Approved | KIRK SANDERS |
| Service/Power Release | 3/14/2025 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 10/29/2025 | Approved | MICHAEL ALLEN |
| Final | 10/29/2025 | Conditional Approval | MICHAEL ALLEN |
| HVAC-Final | 10/29/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 10/29/2025 | Approved | MICHAEL ALLEN |
| Service/Power Release | 10/29/2025 | Approved | MICHAEL ALLEN |
| Final | 11/3/2025 | OK to Issue CofO | ANDREW NAVE |