2330 E MEADOWVALE AVE 90031

Certificate Information: 2330 E MEADOWVALE AVE 90031

Application / Permit
21010-30000-06675
Plan Check / Job No.
B21WL05707
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(n) 1-story S.F.R. of type V w/ attached garage *** 1 of 2 ***
Permit Issued
Issued on 5/27/2022
Issuing Office
Current Status
CofO Issued on 3/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 FELIPE HERNANDEZ
Corrections Issued 1/4/2022 FELIPE HERNANDEZ
Quality Review Completed 2/2/2022 CHIHARU SUZUKI
Applicant returned to address corrections 4/29/2022 FELIPE HERNANDEZ
Plan Check Approved 5/25/2022 FELIPE HERNANDEZ
Issued 5/27/2022 APPLICANT
Building Plans Picked Up 5/31/2022 APPLICANT
CofO in Progress 2/28/2023 THOMAS LOGRASSO
CofO Issued 3/1/2023 DEROLD HAUFF
Permit Finaled 3/1/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/4/2022 JEANIE LAM
Permit Cleared 1/4/2022 JEANIE LAM
Sewer availability Cleared 1/4/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/5/2022 JEANIE LAM
Trees in Parkway Cleared 1/19/2022 ADALBERTO VERA
ZI Cleared 1/19/2022 ANACANY HURTADO
Hydrant and Access approval Cleared 3/4/2022 DWAYNE LAURENT
Low Impact Development Cleared 3/4/2022 TA ANH
Roof/Waste drainage to street Cleared 3/9/2022 AMAAN MALIK

Contact Information

Architect , ; Lic. No.: C34496       LOS ANGELES, CA
Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo A; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/24/2022 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 6/28/2022 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 7/6/2022 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 7/6/2022 Approved THOMAS LOGRASSO
Sewer 8/3/2022 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 9/21/2022 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 9/21/2022 Approved THOMAS LOGRASSO
Green Building Rough 9/21/2022 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 9/21/2022 Approved THOMAS LOGRASSO
MERV13>=Rough 9/21/2022 Approved THOMAS LOGRASSO
PLUMBING-Rough 9/21/2022 Approved THOMAS LOGRASSO
Verify Sprinkler Sign Off 9/21/2022 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 9/27/2022 Not Ready for Inspection THOMAS LOGRASSO
Insulation 9/27/2022 Conditional Approval THOMAS LOGRASSO
Interior/Exterior Lathing 9/27/2022 Partial Approval THOMAS LOGRASSO
Shower Pan 9/27/2022 Approved THOMAS LOGRASSO
Drywall Nailing 10/5/2022 Not Ready for Inspection THOMAS LOGRASSO
Green Building Rough 10/5/2022 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 10/5/2022 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 1/4/2023 Not Ready for Inspection THOMAS LOGRASSO
Drywall Nailing 1/4/2023 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 1/4/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 1/4/2023 Not Ready for Inspection THOMAS LOGRASSO
Gas Test 1/4/2023 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 1/4/2023 Approved THOMAS LOGRASSO
HVAC-Final 1/4/2023 Not Ready for Inspection THOMAS LOGRASSO
MERV13>=Final 1/4/2023 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Final 1/4/2023 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 1/4/2023 SGSOV Not Ready THOMAS LOGRASSO
Service/Power Release 1/4/2023 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 1/4/2023 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 2/1/2023 Approved THOMAS LOGRASSO
Drywall Nailing 2/1/2023 Approved THOMAS LOGRASSO
Final 2/1/2023 Corrections Issued THOMAS LOGRASSO
Gas Test 2/1/2023 Not Ready for Inspection THOMAS LOGRASSO
MERV13>=Final 2/1/2023 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 2/1/2023 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 2/1/2023 Not Ready for Inspection THOMAS LOGRASSO
Pre-Inspection 2/2/2023 Not Ready for Inspection THOMAS LOGRASSO
Gas Test 2/8/2023 Approved THOMAS LOGRASSO
Final 2/27/2023 OK to Issue CofO THOMAS LOGRASSO
Service/Power Release 2/27/2023 Approved THOMAS LOGRASSO