2317 E FERNLEAF ST 90031

Certificate Information: 2317 E FERNLEAF ST 90031

Application / Permit
21010-30000-06673
Plan Check / Job No.
B21WL05706
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 1-story SFD (1,559 sf) w./ att. 2-car garage (331 sf)
Permit Issued
Issued on 5/13/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 REZA HAGHIGHAT
Corrections Issued 1/2/2022 REZA HAGHIGHAT
Quality Review Completed 1/10/2022 TARIK SAOUD
Building Plans Picked Up 1/27/2022 APPLICANT
Plan Check Approved 5/10/2022 REZA HAGHIGHAT
Issued 5/13/2022 APPLICANT
CofO in Progress 4/24/2023 THOMAS LOGRASSO
Permit Finaled 5/6/2023 DEROLD HAUFF
CofO Issued 5/6/2023 DEROLD HAUFF
Permit Finaled 5/6/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/4/2022 CELINA MORENO
Permit Cleared 1/4/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/6/2022 CELINA MORENO
Sewer availability Cleared 1/6/2022 CELINA MORENO
ZI Cleared 1/20/2022 MAXFIELD VERMY
Low Impact Development Cleared 2/28/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 3/1/2022 CELINA MORENO
Hydrant and Access approval Cleared 3/4/2022 DWAYNE LAURENT
Trees in Parkway Cleared 4/19/2022 ADALBERTO VERA

Contact Information

Architect , ; Lic. No.: C34496 9856 VIDOR DRIVE      LOS ANGELES, CA 90035
Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo A; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/15/2022 Partial Inspection THOMAS LOGRASSO
PLUMBING-Rough 6/23/2022 Partial Approval KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 6/30/2022 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 6/30/2022 Approved THOMAS LOGRASSO
Sewer 8/3/2022 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 10/7/2022 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 10/7/2022 Corrections Issued THOMAS LOGRASSO
Green Building Rough 10/7/2022 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 10/7/2022 Approved THOMAS LOGRASSO
MERV13>=Rough 10/7/2022 Approved THOMAS LOGRASSO
PLUMBING-Rough 10/7/2022 Approved THOMAS LOGRASSO
Verify Sprinkler Sign Off 10/7/2022 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 10/14/2022 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 10/14/2022 Approved THOMAS LOGRASSO
Green Building Rough 10/14/2022 Not Ready for Inspection THOMAS LOGRASSO
Verify Sprinkler Sign Off 10/14/2022 Approved THOMAS LOGRASSO
Insulation 10/17/2022 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 10/21/2022 Approved THOMAS LOGRASSO
Drywall Nailing 10/21/2022 Approved THOMAS LOGRASSO
Green Building Rough 10/21/2022 Approved THOMAS LOGRASSO
Insulation 10/21/2022 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 10/21/2022 Approved THOMAS LOGRASSO
Shower Pan 10/21/2022 Approved THOMAS LOGRASSO
Underground Mechanical 2/9/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 3/9/2023 Corrections Issued THOMAS LOGRASSO
Gas Test 3/9/2023 Approved THOMAS LOGRASSO
Green Building Final 3/9/2023 Approved THOMAS LOGRASSO
MERV13>=Final 3/9/2023 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 3/9/2023 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 3/9/2023 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 3/9/2023 Approved THOMAS LOGRASSO
ELECTRICAL-Final 3/13/2023 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Final 3/13/2023 Approved THOMAS LOGRASSO
PLUMBING-Final 3/13/2023 Approved THOMAS LOGRASSO
Service/Power Release 3/13/2023 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 3/20/2023 Approved THOMAS LOGRASSO
Service/Power Release 3/20/2023 Approved THOMAS LOGRASSO
Final 4/24/2023 OK to Issue CofO THOMAS LOGRASSO