7628 N MORELLA AVE #1-2 91605

Certificate Information: 7628 N MORELLA AVE #1-2 91605

Application / Permit
21010-30000-06642
Plan Check / Job No.
B21WL05686
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 3-stories Duplex and attached carport. 1 of 6
Permit Issued
Issued on 10/11/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2021 APPLICANT
Assigned to Plan Check Engineer 2/3/2022 SAM CHANG
Corrections Issued 2/14/2022 SAM CHANG
Quality Review Completed 2/15/2022 EUGENE BARBEAU
Building Plans Picked Up 2/24/2022 APPLICANT
Applicant returned to address corrections 8/25/2022 SAM CHANG
Plan Check Approved 9/2/2022 SAM CHANG
Issued 10/11/2022 APPLICANT
CofO in Progress 12/30/2024 JEFFREY PARD
CofO in Progress 12/30/2024 JOHN JANSON
CofO Issued 1/17/2025 JOHN JANSON
Permit Finaled 1/17/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/8/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/8/2022 CARLOS AGUILERA
Permit Cleared 3/8/2022 CARLOS AGUILERA
Trees in Parkway Cleared 4/6/2022 ADALBERTO VERA
Clean Up Green Up Cleared 4/14/2022 DANG NGUYEN
Sewer availability Cleared 4/20/2022 CARLOS AGUILERA
Frnt yard landscape/Water mgmt Cleared 4/27/2022 DANG NGUYEN
Opn space landscape/Water mgmt Cleared 4/27/2022 DANG NGUYEN
Hydrant and Access approval Cleared 7/15/2022 GILBERT URREA
Low Impact Development Cleared 8/5/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 8/8/2022 CARLOS AGUILERA
Green Code Cleared 8/25/2022 SAM CHANG

Contact Information

Architect Hrd, Arch Inc.; Lic. No.: C35150       ,
Contractor Golden Point Construction; Lic. No.: 965193-B 731 EAST 75TH STREET      LOS ANGELES, CA 90001
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

JOSEPH SAGEN, (818) 774-4353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/17/2022 Partial Approval CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 11/21/2022 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 11/21/2022 Corrections Issued JEFFREY PARD
PLUMBING-Rough 11/21/2022 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 11/22/2022 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Approved JEFFREY PARD
ELECTRICAL-Rough 8/30/2023 Approved JEFFREY PARD
PLUMBING-Rough 8/30/2023 Corrections Issued JEFFREY PARD
Interior/Exterior Lathing 9/5/2023 Approved JEFFREY PARD
Interior/Exterior Lathing 9/6/2023 Approved JEFFREY PARD
BUILDING-Rough-Frame 9/15/2023 Approved JEFFREY PARD
Green Building Rough 9/15/2023 Approved JEFFREY PARD
HVAC-Rough 9/15/2023 Approved JEFFREY PARD
Verify Sprinkler Sign Off 9/15/2023 Approved JEFFREY PARD
Insulation 9/19/2023 Approved JEFFREY PARD
Drywall Nailing 10/24/2023 Approved JEFFREY PARD
Gas Test 12/11/2023 Approved JEFFREY PARD
ELECTRICAL-Final 8/28/2024 Not Ready for Inspection JEFFREY PARD
PLUMBING-Final 8/28/2024 Approved JEFFREY PARD
HVAC-Final 9/19/2024 Approved JEFFREY PARD
ELECTRICAL-Final 9/24/2024 Approved JEFFREY PARD
ELECTRICAL-Final 10/1/2024 Approved JEFFREY PARD
Special/Order Compliance 10/22/2024 Approved JEFFREY PARD
Special/Order Compliance 11/4/2024 Approved JEFFREY PARD
Final 11/5/2024 Not Ready for Inspection JEFFREY PARD
Green Building Final 11/5/2024 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 11/5/2024 SGSOV Approved JEFFREY PARD
Service/Power Release 11/5/2024 Not Ready for Inspection JEFFREY PARD
Smoke Detectors 11/5/2024 Approved JEFFREY PARD
Final 11/7/2024 Not Ready for Inspection JEFFREY PARD
Service/Power Release 11/7/2024 Approved JEFFREY PARD
Final 11/13/2024 Corrections Issued JEFFREY PARD
Final 12/27/2024 OK to Issue CofO JEFFREY PARD