1278-1280 S MEADOWBROOK AVE 90019
Certificate Information: 1278-1280 S MEADOWBROOK AVE 90019
- Application / Permit
- 21010-30000-06636
- Plan Check / Job No.
- B21WL05681
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (n) 2-story Duplex with new attached garages and roof trusses
- Permit Issued
- Issued on 5/31/2022
- Issuing Office
- Current Status
- CofO Issued on 12/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2021 | YASHAR EMAMI |
| Corrections Issued | 1/6/2022 | YASHAR EMAMI |
| Quality Review Completed | 2/3/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 5/3/2022 | YASHAR EMAMI |
| Applicant returned to address corrections | 5/12/2022 | YASHAR EMAMI |
| Plan Check Approved | 5/13/2022 | YASHAR EMAMI |
| Issued | 5/31/2022 | APPLICANT |
| Building Plans Picked Up | 6/1/2022 | APPLICANT |
| CofO in Progress | 6/20/2023 | JOSE AVILA |
| Permit Finaled | 12/5/2023 | DEROLD HAUFF |
| CofO Issued | 12/5/2023 | DEROLD HAUFF |
| Permit Finaled | 12/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2022 | JEANIE LAM |
| Permit | Cleared | 2/23/2022 | JEANIE LAM |
| Sewer availability | Cleared | 2/23/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 3/9/2022 | CHRIS VONG |
| Hydrant and Access approval | Cleared | 3/16/2022 | CINDY JOSSELYN |
| Roof/Waste drainage to street | Cleared | 4/13/2022 | JEANIE LAM |
| Trees in Parkway | Cleared | 4/19/2022 | ADALBERTO VERA |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | Gomez A Landscaping Designs; Lic. No.: 1011989-C27 | P O BOX 1387 SIMI VALLEY, CA 93062 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/15/2022 | Approved | JOSE AVILA |
| Deputy Methane Barrier | 7/18/2022 | Conditional Approval | JOSE AVILA |
| Deputy Methane Barrier | 7/27/2022 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 8/2/2022 | Corrections Issued | JOSE AVILA |
| METHANE-Barrier | 8/2/2022 | Corrections Issued | JOSE AVILA |
| METHANE-Subgrade | 8/2/2022 | Corrections Issued | JOSE AVILA |
| Deputy Reinf. Concrete | 8/3/2022 | Conditional Approval | JOSE AVILA |
| METHANE-Rough | 8/4/2022 | Not Ready for Inspection | JOSE AVILA |
| METHANE-Subgrade | 8/4/2022 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 8/8/2022 | Approved | JOSE AVILA |
| METHANE-Barrier | 8/8/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Approved | JOSE AVILA |
| Deputy Wood Construction | 8/30/2022 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 10/17/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 10/17/2022 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 10/17/2022 | Corrections Issued | JOSE AVILA |
| Deputy Wood Construction | 10/18/2022 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 10/21/2022 | Approved | JOSE AVILA |
| HVAC-Rough | 10/21/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 10/21/2022 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2022 | Corrections Issued | JOSE AVILA |
| Deputy Wood Construction | 10/31/2022 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 11/14/2022 | Corrections Issued | JOSE AVILA |
| Shower Pan | 11/14/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 12/1/2022 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 12/1/2022 | Corrections Issued | JOSE AVILA |
| METHANE-Rough | 12/1/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 12/1/2022 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 12/1/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 1/4/2023 | Approved | JOSE AVILA |
| Insulation | 1/6/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 1/6/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 1/10/2023 | Not Ready for Inspection | JOSE AVILA |
| Drywall Nailing | 1/17/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/17/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/19/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/19/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/19/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/3/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 4/21/2023 | Partial Inspection | JOSE AVILA |
| ELECTRICAL-Final | 5/2/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 5/2/2023 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 5/2/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 5/2/2023 | Approved | STUART CHAPMAN |
| Service/Power Release | 5/2/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 6/15/2023 | OK to Issue CofO | JOSE AVILA |
| Green Building Final | 6/15/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 6/15/2023 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 6/15/2023 | Approved | JOSE AVILA |
| Smoke Detectors | 6/15/2023 | Approved | JOSE AVILA |