3055-3057 S MOUNTAIN VIEW AVE 90066

Certificate Information: 3055-3057 S MOUNTAIN VIEW AVE 90066

Application / Permit
21010-30000-06626
Plan Check / Job No.
B21WL05676
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-story SFD with roof deck, attached 2-car garage and attached ADU in the front of SFD per CA G.C.S. 65852.2(e)(1)(A).
Permit Issued
Issued on 9/1/2022
Issuing Office
Current Status
CofO Issued on 11/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 JAHANSHAH POURHASSAN
Corrections Issued 1/6/2022 JAHANSHAH POURHASSAN
Quality Review Completed 2/2/2022 CHIHARU SUZUKI
Applicant returned to address corrections 8/16/2022 JAHANSHAH POURHASSAN
Plan Check Approved 8/24/2022 JAHANSHAH POURHASSAN
Issued 9/1/2022 APPLICANT
Building Plans Picked Up 9/6/2022 APPLICANT
CofO in Progress 11/13/2024 DANIEL VERA
Permit Finaled 11/19/2024 RICHARD STEINBACH
CofO Issued 11/19/2024 RICHARD STEINBACH
Permit Finaled 11/19/2024 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 2/24/2022 FREDDY GARCIA
Permit Cleared 3/5/2022 JOSE HERNANDEZ
Address approval Cleared 3/7/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 3/8/2022 JOSE HERNANDEZ
Sewer availability Cleared 3/8/2022 JOSE HERNANDEZ
Hydrant and Access approval Cleared 3/16/2022 CINDY JOSSELYN
Trees in Parkway Cleared 4/5/2022 ADALBERTO VERA
Low Impact Development Cleared 4/29/2022 NICK RAYGOZA
Roof/Waste drainage to street Cleared 4/30/2022 JOSE HERNANDEZ

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26940 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Haddad,, Raymond M; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Landreth,, Jeffrey; Lic. No.: M34736 2505 RALSTON LANE      REDONDO BEACH, CA 90278
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789
Engineer Nguyen,, Huan; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/22/2023 Partial Approval JOHNNY MIRANDA
Underground Mechanical 6/22/2023 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 6/28/2023 Conditional Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 6/30/2023 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 6/30/2023 Approved JOHNNY MIRANDA
Sewer 7/14/2023 Approved JESUS PINEDA
Underground Mechanical 7/14/2023 Approved JESUS PINEDA
Deputy Wood Construction 7/26/2023 Approved RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 7/26/2023 Partial Approval RICHARD STEINBACH
Deputy Wood Construction 9/14/2023 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 9/15/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 10/4/2023 Corrections Issued JESUS PINEDA
HVAC-Rough 10/4/2023 Corrections Issued JESUS PINEDA
HVAC-Rough 10/10/2023 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 10/12/2023 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/12/2023 Approved JESUS PINEDA
HVAC-Rough 10/12/2023 Approved JESUS PINEDA
PLUMBING-Rough 10/12/2023 Approved JESUS PINEDA
Deputy Wood Construction 10/13/2023 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 10/27/2023 Approved CLAYTON GRAHAM
Green Building Rough 10/27/2023 Approved CLAYTON GRAHAM
Shower Pan 10/27/2023 Partial Approval CLAYTON GRAHAM
Special/Order Compliance 10/27/2023 Corrections Issued CLAYTON GRAHAM
Verify Sprinkler Sign Off 10/27/2023 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 11/6/2023 Partial Approval JESUS PINEDA
Insulation 1/30/2024 Approved JESUS PINEDA
Drywall Nailing 2/13/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 3/15/2024 Approved JESUS PINEDA
Deputy Reinf. Concrete 6/5/2024 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Final 9/30/2024 Approved DANIEL VERA
Gas Test 9/30/2024 Approved DANIEL VERA
Green Building Final 9/30/2024 Not Ready for Inspection DANIEL VERA
PLUMBING-Final 9/30/2024 Corrections Issued DANIEL VERA
SGSOV-Seismic Gas S/O Valve 9/30/2024 SGSOV Approved DANIEL VERA
Service/Power Release 9/30/2024 Approved DANIEL VERA
Smoke Detectors 9/30/2024 Approved DANIEL VERA
Verify Rec and Parks Fee Memo 9/30/2024 Not Ready for Inspection DANIEL VERA
Final 10/17/2024 Not Ready for Inspection DANIEL VERA
HVAC-Final 10/17/2024 Approved DANIEL VERA
PLUMBING-Final 10/17/2024 Approved DANIEL VERA
Final 11/4/2024 OK to Issue CofO DANIEL VERA
Green Building Final 11/4/2024 Approved DANIEL VERA