1807 1-3 S BELOIT AVE 90025
Certificate Information: 1807 1-3 S BELOIT AVE 90025
- Application / Permit
- 21010-30000-06607
- Plan Check / Job No.
- B21WL05657
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- new 3-story Duplex with an attached ADU. ADU per CA Govt Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/27/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 1/4/2022 | FELIPE HERNANDEZ |
| Quality Review Completed | 2/1/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 2/10/2022 | APPLICANT |
| Plan Check Approved | 5/25/2022 | FELIPE HERNANDEZ |
| Issued | 6/27/2022 | APPLICANT |
| CofO in Progress | 2/15/2024 | ASHLEY THOMPSON |
| Permit Finaled | 2/17/2024 | DANIEL ORRANTE |
| CofO Issued | 2/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/15/2022 | SAUL GARCIA |
| Permit | Cleared | 1/15/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 1/18/2022 | SAUL GARCIA |
| "Q" conditions | Cleared | 1/19/2022 | DYLAN SITTIG |
| ZI | Cleared | 1/19/2022 | DYLAN SITTIG |
| Low Impact Development | Cleared | 2/28/2022 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 3/7/2022 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 3/14/2022 | KURT CORRAL |
| Tenant Habitability Plan | Cleared | 4/7/2022 | PHILLIP MUNGUIA |
| DAS Clearance | Cleared | 4/19/2022 | FELIPE HERNANDEZ |
| Specific Plan | Cleared | 5/6/2022 | PEDRO AYALA |
| Trees in Parkway | Cleared | 5/6/2022 | ADALBERTO VERA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Safe Quake Construction; Lic. No.: 571102-B | 2088 S ATLANTIC BL #291 MONTEREY PARK, CA 91754 |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 11022 SANTA MONICA BLVD STE 440 LOS ANGELES, CA 90025 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/25/2022 | Approved | JOHN KIDWELL |
| Underground Mechanical | 8/25/2022 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 9/23/2022 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 10/11/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 10/11/2022 | Approved | MICHAEL PELHAM |
| METHANE-Barrier | 10/11/2022 | Approved | MICHAEL PELHAM |
| METHANE-Final | 10/11/2022 | Approved | MICHAEL PELHAM |
| METHANE-Rough | 10/11/2022 | Approved | MICHAEL PELHAM |
| METHANE-Subgrade | 10/11/2022 | Approved | MICHAEL PELHAM |
| Pre-Inspection | 10/11/2022 | Corrections Issued | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 10/14/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2022 | Partial Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2023 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2023 | Partial Approval | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 3/15/2023 | No Access for Inspection | CLAYTON GRAHAM |
| HVAC-Rough | 3/15/2023 | No Access for Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 3/15/2023 | No Access for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 3/16/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Final | 3/16/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 3/16/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Rough | 3/16/2023 | Corrections Issued | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 3/29/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 3/29/2023 | Conditional Approval | CLAYTON GRAHAM |
| Green Building Rough | 3/29/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 3/29/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| MERV13>=Rough | 3/29/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 3/29/2023 | Approved | CLAYTON GRAHAM |
| Verify Sprinkler Sign Off | 3/29/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 4/12/2023 | Conditional Approval | JEREMY TODD |
| ELECTRICAL-Rough | 4/12/2023 | Approved | JEREMY TODD |
| Green Building Rough | 4/12/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 4/12/2023 | Approved | JEREMY TODD |
| MERV13>=Rough | 4/12/2023 | Approved | JEREMY TODD |
| Verify Sprinkler Sign Off | 4/12/2023 | Corrections Issued | JEREMY TODD |
| Insulation | 4/19/2023 | Corrections Issued | CLAYTON GRAHAM |
| Insulation | 4/24/2023 | Approved | JESUS PINEDA |
| Drywall Nailing | 5/1/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/2/2023 | Approved | JESUS PINEDA |
| Shower Pan | 5/2/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 12/6/2023 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 12/6/2023 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 12/6/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Service/Power Release | 12/6/2023 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 12/13/2023 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 12/13/2023 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 12/13/2023 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Approved | CARLOS MATAMOROS |
| Green Building Final | 2/9/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 2/12/2024 | Approved | JESUS PINEDA |
| Final | 2/12/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 2/12/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 2/12/2024 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 2/12/2024 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 2/12/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 2/14/2024 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 2/14/2024 | Approved | ASHLEY THOMPSON |
| Final | 2/14/2024 | Conditional Approval | ASHLEY THOMPSON |
| Green Building Final | 2/14/2024 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 2/14/2024 | Approved | ASHLEY THOMPSON |
| MERV13>=Final | 2/14/2024 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 2/14/2024 | Approved | ASHLEY THOMPSON |
| Service/Power Release | 2/14/2024 | Approved | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 2/14/2024 | Approved | ASHLEY THOMPSON |