5319 1-2 N BEN AVE 91607
Certificate Information: 5319 1-2 N BEN AVE 91607
- Application / Permit
- 21010-30000-06605
- Plan Check / Job No.
- B21WL05656
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- new 3-story Duplex with atached garage (front building)
- Permit Issued
- Issued on 10/2/2023
- Issuing Office
- Current Status
- CofO Issued on 10/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2021 | TARIK SAOUD |
| Corrections Issued | 1/2/2022 | TARIK SAOUD |
| Quality Review Completed | 1/7/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 1/7/2022 | APPLICANT |
| Assigned to Zoning Architect | 3/24/2023 | JASON BRAVO |
| Applicant returned to address corrections | 7/12/2023 | YASHAR EMAMI |
| Plan Check Approved | 7/26/2023 | YASHAR EMAMI |
| Issued | 10/2/2023 | APPLICANT |
| CofO in Progress | 9/23/2024 | CHRISTOPHER ROJAS |
| CofO Issued | 10/1/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/1/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/10/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/25/2022 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 5/5/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 8/25/2022 | CARLOS AGUILERA |
| Frnt yard landscape/Water mgmt | Cleared | 6/30/2023 | JAZMIN ROQUE |
| Specific Plan | Cleared | 6/30/2023 | JAZMIN ROQUE |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Onward Builders Llc; Lic. No.: 1084275-B | 750 N SAN VICENTE BLVD STE 800 WEST HOLLYWOOD, CA 90069 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 10/12/2023 | Partial Approval | MISAEL ESPARZA |
| Underground Mechanical | 10/12/2023 | Corrections Issued | MISAEL ESPARZA |
| Deputy Reinf. Concrete | 10/18/2023 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 10/20/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Underground Mechanical | 10/20/2023 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 10/27/2023 | Approved | ROBERT GOLD |
| Deputy Steel/Welding | 10/30/2023 | Conditional Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2024 | Corrections Issued | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2024 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 2/26/2024 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 2/26/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 3/1/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/14/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 3/14/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 3/14/2024 | Approved | DAVID ANDERSON |
| Shower Pan | 3/14/2024 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 3/14/2024 | Approved | DAVID ANDERSON |
| Insulation | 3/19/2024 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 3/19/2024 | Approved | KIRK SANDERS |
| Insulation | 3/22/2024 | Not Ready for Inspection | KIRK SANDERS |
| Insulation | 3/27/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 3/29/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 9/10/2024 | Approved | MISAEL ESPARZA |
| Gas Test | 9/10/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 9/10/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 9/10/2024 | Partial Approval | MISAEL ESPARZA |
| Service/Power Release | 9/10/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/12/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 9/12/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 9/12/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 9/20/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Gas Test | 9/20/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 9/20/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 9/20/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 9/20/2024 | Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 9/20/2024 | Approved | CHRISTOPHER ROJAS |