1341 N BENTON WAY 90026

Certificate Information: 1341 N BENTON WAY 90026

Application / Permit
21010-30000-06545
Plan Check / Job No.
B21WL05630
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
(N) DETACHED 1-CAR GARAGE
Permit Issued
Issued on 6/29/2022
Issuing Office
Current Status
CofO Issued on 7/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/18/2022 APPLICANT
Assigned to Plan Check Engineer 2/3/2022 DANIEL YIP
Corrections Issued 2/7/2022 DANIEL YIP
Quality Review Completed 2/9/2022 KEN GILL
Plan Check Approved 4/18/2022 DANIEL YIP
No Progress 4/18/2022 DANIEL YIP
Building Plans Picked Up 4/26/2022 APPLICANT
Plan Check Approved 6/28/2022 DANIEL YIP
Issued 6/29/2022 APPLICANT
CofO in Progress 7/11/2023 THOMAS LOGRASSO
Permit Finaled 7/18/2023 DEROLD HAUFF
CofO Issued 7/18/2023 DEROLD HAUFF
Permit Finaled 7/18/2023 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/24/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 2/24/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 2/24/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 2/24/2022 JEANIE LAM
Permit Cleared 2/24/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/25/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 4/13/2022 JEANIE LAM
Grading Pre-Inspection Cleared 4/18/2022 DANIEL YIP
Construction near power lines Cleared 6/3/2022 RIDWAN HARDY

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/29/2022 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 9/2/2022 Not Ready for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 9/7/2022 Not Ready for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 9/12/2022 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 10/7/2022 Approved THOMAS LOGRASSO
Deputy Wood Construction 10/7/2022 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 10/7/2022 Approved THOMAS LOGRASSO
Drywall Nailing 10/17/2022 Approved THOMAS LOGRASSO
Green Building Rough 10/17/2022 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 10/17/2022 Approved THOMAS LOGRASSO
Final 3/21/2023 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 3/21/2023 Approved THOMAS LOGRASSO
Green Building Final 3/21/2023 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 3/21/2023 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 3/21/2023 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 3/21/2023 Approved THOMAS LOGRASSO
Final 3/31/2023 Corrections Issued THOMAS LOGRASSO
Service/Power Release 3/31/2023 Not Required THOMAS LOGRASSO
Final 4/5/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 7/10/2023 OK to Issue CofO THOMAS LOGRASSO