1341 N BENTON WAY 90026
Certificate Information: 1341 N BENTON WAY 90026
- Application / Permit
- 21010-30000-06545
- Plan Check / Job No.
- B21WL05630
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- (N) DETACHED 1-CAR GARAGE
- Permit Issued
- Issued on 6/29/2022
- Issuing Office
- Current Status
- CofO Issued on 7/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2022 | DANIEL YIP |
| Corrections Issued | 2/7/2022 | DANIEL YIP |
| Quality Review Completed | 2/9/2022 | KEN GILL |
| Plan Check Approved | 4/18/2022 | DANIEL YIP |
| No Progress | 4/18/2022 | DANIEL YIP |
| Building Plans Picked Up | 4/26/2022 | APPLICANT |
| Plan Check Approved | 6/28/2022 | DANIEL YIP |
| Issued | 6/29/2022 | APPLICANT |
| CofO in Progress | 7/11/2023 | THOMAS LOGRASSO |
| Permit Finaled | 7/18/2023 | DEROLD HAUFF |
| CofO Issued | 7/18/2023 | DEROLD HAUFF |
| Permit Finaled | 7/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/24/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 2/24/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 2/24/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 2/24/2022 | JEANIE LAM |
| Permit | Cleared | 2/24/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 4/13/2022 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 4/18/2022 | DANIEL YIP |
| Construction near power lines | Cleared | 6/3/2022 | RIDWAN HARDY |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/29/2022 | Corrections Issued | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 9/2/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 9/7/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 9/12/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/7/2022 | Approved | THOMAS LOGRASSO |
| Deputy Wood Construction | 10/7/2022 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 10/7/2022 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 10/17/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 10/17/2022 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 10/17/2022 | Approved | THOMAS LOGRASSO |
| Final | 3/21/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/21/2023 | Approved | THOMAS LOGRASSO |
| Green Building Final | 3/21/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 3/21/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 3/21/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 3/21/2023 | Approved | THOMAS LOGRASSO |
| Final | 3/31/2023 | Corrections Issued | THOMAS LOGRASSO |
| Service/Power Release | 3/31/2023 | Not Required | THOMAS LOGRASSO |
| Final | 4/5/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 7/10/2023 | OK to Issue CofO | THOMAS LOGRASSO |