3580 S WASATCH AVE 90066
Certificate Information: 3580 S WASATCH AVE 90066
- Application / Permit
- 21010-30000-06503
- Plan Check / Job No.
- B21WL05562
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-Story S.F.D w/ Basement, Rooftop Deck, and Attached 2-Car Garage
- Permit Issued
- Issued on 5/26/2022
- Issuing Office
- Current Status
- CofO Issued on 2/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | DAVID CASTILLO |
| Corrections Issued | 1/13/2022 | DAVID CASTILLO |
| Quality Review Completed | 2/9/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 3/23/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 3/24/2022 | APPLICANT |
| Applicant returned to address corrections | 5/6/2022 | DAVID CASTILLO |
| Plan Check Approved | 5/17/2022 | DAVID CASTILLO |
| Issued | 5/26/2022 | APPLICANT |
| CofO in Progress | 12/13/2024 | JESUS PINEDA |
| CofO Issued | 2/28/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/28/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | NIKTA MOUSAVI |
| Address approval | Cleared | 1/28/2022 | NIKTA MOUSAVI |
| Frnt yard landscape/Water mgmt | Cleared | 2/1/2022 | RICHARD REASER |
| Permit | Cleared | 2/1/2022 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 2/1/2022 | NIKTA MOUSAVI |
| Hydrant and Access approval | Cleared | 2/25/2022 | LAURINDA MEADE |
| Miscellaneous | Cleared | 3/1/2022 | PEDRO AYALA |
| Low Impact Development | Cleared | 3/2/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/4/2022 | NIKTA MOUSAVI |
| Trees in Parkway | Cleared | 3/10/2022 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 3/23/2022 | DAVID CASTILLO |
| Grading Pre-Inspection | Cleared | 3/23/2022 | DAVID CASTILLO |
Contact Information
| Contractor | Martinko Construction Inc; Lic. No.: 990964-B | 10372 KESWICK AVENUE LOS ANGELES, CA 90064 |
| Engineer | Onishi,, Robert K; Lic. No.: S3705 | 4438 LINDBLADE DRIVE LOS ANGELES, CA 90066 |
| Engineer | Rowlands,, James; Lic. No.: GE740 | 10954 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
| Engineer | Vreeland,, Regan Edward; Lic. No.: L8503 | PO BOX 482 SANTA MONICA, CA 90406 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/21/2022 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 8/8/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 8/9/2022 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 8/19/2022 | Corrections Issued | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 8/23/2022 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 8/25/2022 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 8/26/2022 | Conditional Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/23/2022 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 10/21/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Deputy Grading | 10/24/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Steel/Welding | 11/22/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2022 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 2/6/2023 | Conditional Approval | JEREMY TODD |
| Deputy Reinf. Concrete | 2/8/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 2/17/2023 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/6/2023 | Approved | JESUS RODRIGUEZ |
| Gas Test | 7/6/2023 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 7/6/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/6/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Shower Pan | 7/13/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 8/7/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Shower Pan | 8/7/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/10/2023 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/23/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 8/23/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 8/23/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/23/2023 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 8/23/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 8/23/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 8/29/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Insulation | 9/7/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 9/7/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 10/2/2023 | Approved | TEMISTOCLES CAAL |
| Sewer | 1/8/2024 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 1/8/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 2/16/2024 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 2/23/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Reinforced Concrete Frame | 2/23/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 2/27/2024 | Conditional Approval | HERBERT GIRON |
| Masonry Wall/Backfill | 4/29/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Masonry Wall/Backfill | 5/9/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Masonry Wall/Backfill | 9/5/2024 | Partial Inspection | JESUS PINEDA |
| Gas Test | 10/11/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 10/11/2024 | SGSOV Approved | JESUS PINEDA |
| HVAC-Final | 10/17/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 10/18/2024 | Corrections Issued | JESUS PINEDA |
| Smoke Detectors | 10/18/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 10/21/2024 | Approved | MICHAEL ALLEN |
| Green Building Final | 10/23/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 10/23/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 10/24/2024 | Approved | JESUS PINEDA |
| Service/Power Release | 10/24/2024 | Not Ready for Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 11/7/2024 | Approved | JESUS PINEDA |
| Final | 11/7/2024 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 11/7/2024 | Approved | JESUS PINEDA |
| Service/Power Release | 11/7/2024 | Approved | JESUS PINEDA |
| Structural Steel Frame | 11/7/2024 | Approved | JESUS PINEDA |
| Final | 12/12/2024 | OK to Issue CofO | JESUS PINEDA |