2122 E 103RD ST 90002
Certificate Information: 2122 E 103RD ST 90002
- Application / Permit
- 21010-30000-06366
- Plan Check / Job No.
- B21WL05376
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New two story single family dwelling
- Permit Issued
- Issued on 9/12/2022
- Issuing Office
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | MARJAN SHENASI |
| Corrections Issued | 12/20/2021 | MARJAN SHENASI |
| Quality Review Completed | 12/27/2021 | TARIK SAOUD |
| Plan Check Approved | 8/16/2022 | HOOMAN HAJIZADEH |
| Issued | 9/12/2022 | APPLICANT |
| Building Plans Picked Up | 9/15/2022 | APPLICANT |
| CofO in Progress | 7/18/2023 | JOHN KLARIN |
| CofO in Progress | 9/5/2023 | JOHN KLARIN |
| Permit Finaled | 9/5/2023 | ANSON MAGLASANG |
| CofO Issued | 9/5/2023 | ANSON MAGLASANG |
| Permit Finaled | 9/5/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 1/11/2022 | MAX LODER |
| Permit | Cleared | 1/11/2022 | JOSE HERNANDEZ |
| Redevelopment Project Area | Cleared | 1/11/2022 | GRACIELA ACOSTA |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | JOSE HERNANDEZ |
| Low Impact Development | Cleared | 5/27/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 6/1/2022 | JOSE HERNANDEZ |
| Hydrant and Access approval | Cleared | 6/16/2022 | MICHAEL GILLISSIE |
| Sewer availability | Cleared | 7/29/2022 | HUGO LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/26/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 9/26/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 10/5/2022 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 10/5/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 10/21/2022 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/23/2022 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 11/23/2022 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 11/23/2022 | Not Ready for Inspection | JOHN KLARIN |
| HVAC-Rough | 11/23/2022 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 11/23/2022 | Not Ready for Inspection | JOHN KLARIN |
| Verify Sprinkler Sign Off | 11/23/2022 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 11/29/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Rough | 11/29/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 11/29/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/16/2022 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 12/16/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 12/16/2022 | Approved | JOHN KLARIN |
| HVAC-Rough | 12/16/2022 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 12/16/2022 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 12/16/2022 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 12/23/2022 | Approved | JOHN KLARIN |
| HVAC-Rough | 12/23/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 12/23/2022 | Approved | JOHN KLARIN |
| Wood Frame | 12/23/2022 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/28/2022 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/4/2023 | Approved | JOHN KLARIN |
| Insulation | 1/4/2023 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 1/4/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 1/11/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 1/11/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 7/5/2023 | Approved | JOHN KLARIN |
| Gas Test | 7/5/2023 | Approved | JOHN KLARIN |
| HVAC-Final | 7/5/2023 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Final | 7/5/2023 | Approved | JOHN KLARIN |
| Service/Power Release | 7/5/2023 | Not Ready for Inspection | JOHN KLARIN |
| Final | 7/10/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 7/10/2023 | Approved | JOHN KLARIN |
| Green Building Final | 7/10/2023 | Approved | JOHN KLARIN |
| HVAC-Final | 7/10/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 7/10/2023 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 7/10/2023 | Approved | JOHN KLARIN |
| Pre-Inspection | 7/12/2023 | Approved | JOHN KLARIN |
| Final | 7/17/2023 | OK to Issue CofO | JOHN KLARIN |
| Service/Power Release | 7/17/2023 | Approved | JOHN KLARIN |
| Final | 9/5/2023 | OK to Issue CofO | JOHN KLARIN |