833 N MCCADDEN PL 1-3 90038
Certificate Information: 833 N MCCADDEN PL 1-3 90038
- Application / Permit
- 21010-30000-06363
- Plan Check / Job No.
- B21WL05372
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- new 3 story Duplex with attached ADU (Front building)
- Permit Issued
- Issued on 8/2/2022
- Issuing Office
- Current Status
- CofO Issued on 11/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2021 | TARIK SAOUD |
| Corrections Issued | 12/21/2021 | TARIK SAOUD |
| Quality Review Completed | 12/23/2021 | CHIHARU SUZUKI |
| Plan Check Approved | 7/14/2022 | TARIK SAOUD |
| Issued | 8/2/2022 | APPLICANT |
| Building Plans Picked Up | 8/4/2022 | APPLICANT |
| CofO in Progress | 11/28/2023 | BRIAN SULLIVAN |
| Permit Finaled | 11/30/2023 | DEROLD HAUFF |
| CofO Issued | 11/30/2023 | DEROLD HAUFF |
| Permit Finaled | 11/30/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/28/2021 | CHRISTOPHER ROCHA |
| Permit | Cleared | 12/28/2021 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2021 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 12/30/2021 | CHRISTOPHER ROCHA |
| Hydrant and Access approval | Cleared | 3/15/2022 | MATTHEW CRAIG |
| Frnt yard landscape/Water mgmt | Cleared | 5/16/2022 | RYAN LY |
| Low Impact Development | Cleared | 7/1/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 8/1/2022 | CHRISTOPHER ROCHA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Xiao,, Qiang; Lic. No.: S5289 | 1520 BROOKHOLLOW #45 SANTA ANA, CA 92705 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/6/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 9/21/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Underground Mechanical | 10/11/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 10/18/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 11/29/2022 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 2/6/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2023 | Partial Approval | RAUL BARAJAS |
| Deputy Wood Construction | 2/13/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 3/7/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 3/20/2023 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 3/20/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 3/20/2023 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 3/23/2023 | Conditional Approval | BRIAN SULLIVAN |
| Insulation | 3/31/2023 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 3/31/2023 | Partial Approval | BRIAN SULLIVAN |
| Shower Pan | 3/31/2023 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 4/14/2023 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 4/14/2023 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 4/24/2023 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 7/17/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Final | 7/17/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Final | 7/17/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Final | 8/17/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Service/Power Release | 8/17/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 8/28/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Final | 8/28/2023 | Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 9/7/2023 | Partial Inspection | JOAQUIN GREENOUGH |
| Service/Power Release | 9/18/2023 | Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 10/10/2023 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 11/27/2023 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 11/27/2023 | Approved | BRIAN SULLIVAN |
| Final | 11/27/2023 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 11/27/2023 | Approved | BRIAN SULLIVAN |
| Green Building Final | 11/27/2023 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 11/27/2023 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 11/27/2023 | Approved | BRIAN SULLIVAN |
| METHANE-Barrier | 11/27/2023 | Approved | BRIAN SULLIVAN |
| METHANE-Final | 11/27/2023 | Approved | BRIAN SULLIVAN |
| METHANE-Rough | 11/27/2023 | Approved | BRIAN SULLIVAN |
| METHANE-Subgrade | 11/27/2023 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 11/27/2023 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 11/27/2023 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 11/27/2023 | Approved | BRIAN SULLIVAN |
| Final | 11/28/2023 | OK to Issue CofO | BRIAN SULLIVAN |