833 N MCCADDEN PL 1-3 90038

Certificate Information: 833 N MCCADDEN PL 1-3 90038

Application / Permit
21010-30000-06363
Plan Check / Job No.
B21WL05372
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
new 3 story Duplex with attached ADU (Front building)
Permit Issued
Issued on 8/2/2022
Issuing Office
Current Status
CofO Issued on 11/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2021 APPLICANT
Assigned to Plan Check Engineer 12/17/2021 TARIK SAOUD
Corrections Issued 12/21/2021 TARIK SAOUD
Quality Review Completed 12/23/2021 CHIHARU SUZUKI
Plan Check Approved 7/14/2022 TARIK SAOUD
Issued 8/2/2022 APPLICANT
Building Plans Picked Up 8/4/2022 APPLICANT
CofO in Progress 11/28/2023 BRIAN SULLIVAN
Permit Finaled 11/30/2023 DEROLD HAUFF
CofO Issued 11/30/2023 DEROLD HAUFF
Permit Finaled 11/30/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/28/2021 CHRISTOPHER ROCHA
Permit Cleared 12/28/2021 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 12/30/2021 CHRISTOPHER ROCHA
Sewer availability Cleared 12/30/2021 CHRISTOPHER ROCHA
Hydrant and Access approval Cleared 3/15/2022 MATTHEW CRAIG
Frnt yard landscape/Water mgmt Cleared 5/16/2022 RYAN LY
Low Impact Development Cleared 7/1/2022 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/1/2022 CHRISTOPHER ROCHA

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Xiao,, Qiang; Lic. No.: S5289 1520 BROOKHOLLOW #45      SANTA ANA, CA 92705

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/6/2022 Partial Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 9/21/2022 Corrections Issued JOAQUIN GREENOUGH
Underground Mechanical 10/11/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Deputy Wood Construction 10/18/2022 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 11/29/2022 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 2/6/2023 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Partial Approval RAUL BARAJAS
Deputy Wood Construction 2/13/2023 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 3/1/2023 Corrections Issued JOAQUIN GREENOUGH
Deputy Wood Construction 3/7/2023 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 3/20/2023 Approved BRIAN SULLIVAN
HVAC-Rough 3/20/2023 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 3/20/2023 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 3/23/2023 Conditional Approval BRIAN SULLIVAN
Insulation 3/31/2023 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 3/31/2023 Partial Approval BRIAN SULLIVAN
Shower Pan 3/31/2023 Approved BRIAN SULLIVAN
Drywall Nailing 4/14/2023 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 4/14/2023 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 4/24/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Final 7/17/2023 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Final 7/17/2023 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 7/17/2023 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Final 8/17/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Service/Power Release 8/17/2023 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Final 8/28/2023 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Final 8/28/2023 Approved JOAQUIN GREENOUGH
Service/Power Release 9/7/2023 Partial Inspection JOAQUIN GREENOUGH
Service/Power Release 9/18/2023 Approved JOAQUIN GREENOUGH
Service/Power Release 10/10/2023 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 11/27/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Final 11/27/2023 Approved BRIAN SULLIVAN
Final 11/27/2023 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 11/27/2023 Approved BRIAN SULLIVAN
Green Building Final 11/27/2023 Approved BRIAN SULLIVAN
Green Building Rough 11/27/2023 Approved BRIAN SULLIVAN
HVAC-Final 11/27/2023 Approved BRIAN SULLIVAN
METHANE-Barrier 11/27/2023 Approved BRIAN SULLIVAN
METHANE-Final 11/27/2023 Approved BRIAN SULLIVAN
METHANE-Rough 11/27/2023 Approved BRIAN SULLIVAN
METHANE-Subgrade 11/27/2023 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 11/27/2023 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 11/27/2023 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 11/27/2023 Approved BRIAN SULLIVAN
Final 11/28/2023 OK to Issue CofO BRIAN SULLIVAN