5981 W 76TH ST 90045

Certificate Information: 5981 W 76TH ST 90045

Application / Permit
21010-30000-06266
Plan Check / Job No.
B21WL05311
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
new 2-story S.F.D. with new two car garage and roof trusses
Permit Issued
Issued on 5/24/2022
Issuing Office
Current Status
CofO Issued on 5/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 FELIPE HERNANDEZ
Corrections Issued 12/13/2021 FELIPE HERNANDEZ
Quality Review Completed 12/23/2021 TARIK SAOUD
Plan Check Approved 5/13/2022 FELIPE HERNANDEZ
Issued 5/24/2022 APPLICANT
Building Plans Picked Up 5/25/2022 APPLICANT
CofO in Progress 5/10/2023 BOBBY KEY
Permit Finaled 5/11/2023 DANIEL ORRANTE
CofO Issued 5/11/2023 DANIEL ORRANTE
Permit Finaled 5/11/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/20/2022 HISASHI KOBAYAKAWA
Sewer availability Cleared 1/20/2022 HISASHI KOBAYAKAWA
Specific Plan Cleared 1/27/2022 VALERIA CEJA
Low Impact Development Cleared 2/2/2022 JONATAN VELASQUEZ
Roof/Waste drainage to street Cleared 2/3/2022 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 3/11/2022 LARRY REDDEN
Construction within easement Cleared 4/13/2022 RIDWAN HARDY
Permit Cleared 4/27/2022 HISASHI KOBAYAKAWA
Trees in Parkway Cleared 4/27/2022 ADALBERTO VERA
Grading Pre-Inspection Cleared 5/13/2022 FELIPE HERNANDEZ

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26940 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 6/30/2022 Approved BOBBY KEY
Underground Mechanical 6/30/2022 Approved BOBBY KEY
Excavation/Setback/Form/Re-Bar 8/5/2022 Approved BOBBY KEY
Footing/Foundation/Slab 8/5/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/1/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/16/2022 Partial Approval BOBBY KEY
Deputy Wood Construction 9/19/2022 Conditional Approval BOBBY KEY
PLUMBING-Rough 9/29/2022 Approved BOBBY KEY
ELECTRICAL-Rough 10/14/2022 Approved BOBBY KEY
HVAC-Rough 10/14/2022 Approved BOBBY KEY
Deputy Wood Construction 10/18/2022 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 10/25/2022 Approved BOBBY KEY
Shower Pan 10/25/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 11/23/2022 Approved BOBBY KEY
Green Building Rough 11/23/2022 Approved BOBBY KEY
Interior/Exterior Lathing 11/23/2022 Partial Approval BOBBY KEY
Verify Sprinkler Sign Off 11/23/2022 Approved BOBBY KEY
Insulation 12/2/2022 Approved DAVID FEILER
Drywall Nailing 12/13/2022 Approved BOBBY KEY
Interior/Exterior Lathing 12/13/2022 Approved BOBBY KEY
Interior/Exterior Lathing 12/14/2022 No Access for Inspection HERBERT GIRON
ELECTRICAL-Final 3/2/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 3/2/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 3/30/2023 Approved BOBBY KEY
HVAC-Final 3/30/2023 Conditional Approval BOBBY KEY
PLUMBING-Final 3/30/2023 Not Ready for Inspection BOBBY KEY
Service/Power Release 3/30/2023 Approved BOBBY KEY
PLUMBING-Final 4/3/2023 Not Ready for Inspection BOBBY KEY
Final 5/9/2023 Not Ready for Inspection BOBBY KEY
Green Building Final 5/9/2023 Approved BOBBY KEY
HVAC-Final 5/9/2023 Approved BOBBY KEY
PLUMBING-Final 5/9/2023 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/9/2023 SGSOV Approved BOBBY KEY
Smoke Detectors 5/9/2023 Approved BOBBY KEY
Final 5/10/2023 OK to Issue CofO BOBBY KEY
PLUMBING-Final 5/10/2023 Approved BOBBY KEY