5253 N AGNES AVE 1-2 91607

Certificate Information: 5253 N AGNES AVE 1-2 91607

Application / Permit
21010-30000-06204
Plan Check / Job No.
B21WL05256
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 3-story duplex (3,772 sf) w./ att. 2-car garages (379 sf) and 2 roof deck areas (12'-11" x 12'-3" each) at front of the lot ; Unit A = 1,925 sf ; Unit B = 1,847 sf ;
Permit Issued
Issued on 12/12/2022
Issuing Office
Current Status
CofO Issued on 5/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 REZA HAGHIGHAT
Corrections Issued 12/11/2021 REZA HAGHIGHAT
Quality Review Completed 12/20/2021 TARIK SAOUD
Plan Check Approved 9/8/2022 REZA HAGHIGHAT
Building Plans Picked Up 9/9/2022 APPLICANT
Issued 12/12/2022 APPLICANT
CofO in Progress 5/9/2025 JAVIER RAMOS JR
CofO in Progress 5/14/2025 JUAN VALENZUELA
CofO in Progress 5/20/2025 JUAN VALENZUELA
CofO Issued 5/21/2025 RUBEN SALAS
Permit Finaled 5/21/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/13/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 12/13/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 12/14/2021 DAGOVERTO GUERRERO
ZA Case Cleared 12/27/2021 LOUIS ORTEGA
Hydrant and Access approval Cleared 3/5/2022 GILBERT URREA
Low Impact Development Cleared 3/29/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/30/2022 DAGOVERTO GUERRERO
Frnt yard landscape/Water mgmt Cleared 8/22/2022 NELSON RODRIGUEZ
Prkng lot landscape/Water mgmt Cleared 8/22/2022 NELSON RODRIGUEZ
Specific Plan Cleared 8/22/2022 NELSON RODRIGUEZ
ZI Cleared 8/22/2022 NELSON RODRIGUEZ
ZI Cleared 8/22/2022 NELSON RODRIGUEZ

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/26/2023 Approved JACK KARGODORIAN
Underground Mechanical 1/26/2023 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 2/16/2023 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/8/2023 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 5/25/2023 Corrections Issued THOMAS FINNILA
HVAC-Rough 5/30/2023 No Access for Inspection JACK KARGODORIAN
PLUMBING-Rough 5/30/2023 No Access for Inspection JACK KARGODORIAN
PLUMBING-Rough 6/2/2023 Corrections Issued JACK KARGODORIAN
HVAC-Rough 9/1/2023 Approved JACK KARGODORIAN
PLUMBING-Rough 9/1/2023 Approved JACK KARGODORIAN
Wood Frame 9/1/2023 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 9/22/2023 Approved JACK KARGODORIAN
ELECTRICAL-Rough 9/22/2023 Approved JACK KARGODORIAN
Green Building Rough 9/22/2023 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 9/22/2023 Approved JACK KARGODORIAN
Wood Frame 9/22/2023 Approved JACK KARGODORIAN
Deck 10/31/2023 No Access for Inspection JOHN COLEMAN
Deck 11/1/2023 Approved JOHN COLEMAN
Insulation 11/9/2023 Corrections Issued JOHN COLEMAN
Insulation 11/15/2023 Approved MISAEL ESPARZA
Drywall Nailing 12/12/2023 Approved DAVID MATSON
Drywall Nailing 12/12/2023 Not Ready for Inspection DAVID MATSON
Interior/Exterior Lathing 2/13/2024 Approved KIRK SANDERS
Underground Mechanical 6/28/2024 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 7/3/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Sewer 7/5/2024 Corrections Issued ROBERT GOLD
Underground Mechanical 7/5/2024 Partial Approval ROBERT GOLD
ELECTRICAL-Final 12/23/2024 Corrections Issued JACK KARGODORIAN
HVAC-Final 12/26/2024 No Access for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 1/7/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 1/7/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Final 1/8/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 1/10/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Final 1/23/2025 Partial Inspection CHRISTOPHER ROJAS
HVAC-Final 1/23/2025 Partial Inspection CHRISTOPHER ROJAS
HVAC-Final 1/29/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 1/29/2025 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 2/7/2025 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Final 2/7/2025 Partial Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 2/18/2025 Partial Inspection CHRISTOPHER ROJAS
Final 2/18/2025 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 2/18/2025 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Final 2/18/2025 Partial Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 2/24/2025 Partial Inspection CHRISTOPHER ROJAS
Final 2/24/2025 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 2/24/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Final 2/24/2025 Partial Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 3/3/2025 Approved CHRISTOPHER ROJAS
Final 3/3/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 3/3/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 5/2/2025 Approved JAVIER RAMOS JR
Final 5/2/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 5/2/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/2/2025 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 5/2/2025 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 5/2/2025 Approved JAVIER RAMOS JR
Final 5/9/2025 Corrections Issued JAVIER RAMOS JR
Service/Power Release 5/9/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Corrections Issued JUAN VALENZUELA
Final 5/20/2025 OK to Issue CofO JUAN VALENZUELA