7226 S EL MANOR AVE 90045
Certificate Information: 7226 S EL MANOR AVE 90045
- Application / Permit
- 21010-30000-06186
- Plan Check / Job No.
- B21WL05236
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 6/21/2023
- Issuing Office
- Current Status
- CofO Issued on 2/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2021 | SERGIO SILVA |
| Corrections Issued | 12/24/2021 | SERGIO SILVA |
| Quality Review Completed | 1/3/2022 | TARIK SAOUD |
| Applicant returned to address corrections | 5/6/2022 | SERGIO SILVA |
| Applicant returned to address corrections | 6/21/2022 | SERGIO SILVA |
| Building Plans Picked Up | 7/1/2022 | APPLICANT |
| Applicant returned to address corrections | 12/19/2022 | SERGIO SILVA |
| Plan Check Approved | 1/30/2023 | SERGIO SILVA |
| Issued | 6/21/2023 | APPLICANT |
| CofO in Progress | 2/20/2025 | TEMISTOCLES CAAL |
| Permit Finaled | 2/20/2025 | RICHARD STEINBACH |
| CofO Issued | 2/20/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/20/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 4/30/2022 | SAUL GARCIA |
| Permit | Cleared | 4/30/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 5/11/2022 | SAUL GARCIA |
| Hydrant and Access approval | Cleared | 5/20/2022 | CINDY JOSSELYN |
| Trees in Parkway | Cleared | 6/22/2022 | ADALBERTO VERA |
| Specific Plan | Cleared | 6/23/2022 | VALERIA CEJA |
| Low Impact Development | Cleared | 12/2/2022 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 12/7/2022 | AHMED AMARRAGY |
| GPI Written Notices | Cleared | 12/19/2022 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 12/19/2022 | SERGIO SILVA |
| Green Code | Cleared | 12/19/2022 | SERGIO SILVA |
Contact Information
| Architect | Halverson,, Stephanie Colleen; Lic. No.: C29855 | P O BOX 820102 PORTLAND, OR 97282 |
| Architect | Hodgdon,, Emily Elizabeth; Lic. No.: C30043 | 1331 BERKELEY STREET # 4 SANTA MONICA, CA 90404 |
| Contractor | Pagan Robert M Construction Company; Lic. No.: 509594-B | 8125 LOYOLA BLVD LOS ANGELES, CA 90045 |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
| Engineer | Babayan,, Raffi Samuel; Lic. No.: C72168 | 7718 DAY STREET LOS ANGELES, CA 91042 |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/29/2023 | Partial Approval | BOBBY KEY |
| Sewer | 10/23/2023 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2023 | Partial Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 11/2/2023 | Partial Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2023 | Conditional Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 11/9/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 11/15/2023 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2023 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2023 | Conditional Approval | TEMISTOCLES CAAL |
| Deputy Steel/Welding | 1/4/2024 | Conditional Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 2/23/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 2/23/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 2/23/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/29/2024 | Conditional Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 3/6/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 3/6/2024 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 3/6/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 3/7/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 3/29/2024 | Conditional Approval | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 3/29/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 4/5/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 9/27/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 9/27/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 9/27/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 9/27/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 9/27/2024 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 9/27/2024 | SGSOV Not Required | TEMISTOCLES CAAL |
| Service/Power Release | 9/27/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Smoke Detectors | 9/27/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 10/25/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 10/25/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 10/25/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 10/25/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 2/14/2025 | Approved | TEMISTOCLES CAAL |
| Final | 2/14/2025 | OK to Issue CofO | TEMISTOCLES CAAL |
| Service/Power Release | 2/14/2025 | Approved | TEMISTOCLES CAAL |