7226 S EL MANOR AVE 90045

Certificate Information: 7226 S EL MANOR AVE 90045

Application / Permit
21010-30000-06186
Plan Check / Job No.
B21WL05236
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
Permit Issued
Issued on 6/21/2023
Issuing Office
Current Status
CofO Issued on 2/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2021 APPLICANT
Assigned to Plan Check Engineer 12/21/2021 SERGIO SILVA
Corrections Issued 12/24/2021 SERGIO SILVA
Quality Review Completed 1/3/2022 TARIK SAOUD
Applicant returned to address corrections 5/6/2022 SERGIO SILVA
Applicant returned to address corrections 6/21/2022 SERGIO SILVA
Building Plans Picked Up 7/1/2022 APPLICANT
Applicant returned to address corrections 12/19/2022 SERGIO SILVA
Plan Check Approved 1/30/2023 SERGIO SILVA
Issued 6/21/2023 APPLICANT
CofO in Progress 2/20/2025 TEMISTOCLES CAAL
Permit Finaled 2/20/2025 RICHARD STEINBACH
CofO Issued 2/20/2025 RICHARD STEINBACH
Permit Finaled 2/20/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 4/30/2022 SAUL GARCIA
Permit Cleared 4/30/2022 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 5/11/2022 SAUL GARCIA
Sewer availability Cleared 5/11/2022 SAUL GARCIA
Hydrant and Access approval Cleared 5/20/2022 CINDY JOSSELYN
Trees in Parkway Cleared 6/22/2022 ADALBERTO VERA
Specific Plan Cleared 6/23/2022 VALERIA CEJA
Low Impact Development Cleared 12/2/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 12/7/2022 AHMED AMARRAGY
GPI Written Notices Cleared 12/19/2022 SERGIO SILVA
Grading Pre-Inspection Cleared 12/19/2022 SERGIO SILVA
Green Code Cleared 12/19/2022 SERGIO SILVA

Contact Information

Architect Halverson,, Stephanie Colleen; Lic. No.: C29855 P O BOX 820102      PORTLAND, OR 97282
Architect Hodgdon,, Emily Elizabeth; Lic. No.: C30043 1331 BERKELEY STREET # 4      SANTA MONICA, CA 90404
Contractor Pagan Robert M Construction Company; Lic. No.: 509594-B 8125 LOYOLA BLVD      LOS ANGELES, CA 90045
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/29/2023 Partial Approval BOBBY KEY
Sewer 10/23/2023 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Partial Approval RICHARD STEINBACH
PLUMBING-Rough 11/2/2023 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 11/7/2023 Conditional Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 11/9/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 11/15/2023 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/28/2023 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/28/2023 Conditional Approval TEMISTOCLES CAAL
Deputy Steel/Welding 1/4/2024 Conditional Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 2/23/2024 Approved TEMISTOCLES CAAL
HVAC-Rough 2/23/2024 Approved TEMISTOCLES CAAL
PLUMBING-Rough 2/23/2024 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 2/29/2024 Conditional Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 3/6/2024 Approved TEMISTOCLES CAAL
Green Building Rough 3/6/2024 Approved TEMISTOCLES CAAL
Verify Sprinkler Sign Off 3/6/2024 Approved TEMISTOCLES CAAL
Shower Pan 3/7/2024 Approved TEMISTOCLES CAAL
Insulation 3/29/2024 Conditional Approval TEMISTOCLES CAAL
Interior/Exterior Lathing 3/29/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 4/5/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 9/27/2024 Corrections Issued TEMISTOCLES CAAL
Final 9/27/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 9/27/2024 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 9/27/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 9/27/2024 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 9/27/2024 SGSOV Not Required TEMISTOCLES CAAL
Service/Power Release 9/27/2024 Not Ready for Inspection TEMISTOCLES CAAL
Smoke Detectors 9/27/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 10/25/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 10/25/2024 Approved TEMISTOCLES CAAL
HVAC-Final 10/25/2024 Approved TEMISTOCLES CAAL
PLUMBING-Final 10/25/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 2/14/2025 Approved TEMISTOCLES CAAL
Final 2/14/2025 OK to Issue CofO TEMISTOCLES CAAL
Service/Power Release 2/14/2025 Approved TEMISTOCLES CAAL