1205 N LAS LOMAS PL 90272

Certificate Information: 1205 N LAS LOMAS PL 90272

Application / Permit
21010-30000-06139
Plan Check / Job No.
B21WL05193
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1st and 2nd story addition (780 sf) to (e) single story SFD with att. 2-car garage, add solid roof patio cover (230 sf) and trellised roof patio cover (285 sf) to the rear side PORTION OF EXISTNG BLDG TO REMAIN
Permit Issued
Issued on 3/5/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 FELIPE HERNANDEZ
Corrections Issued 12/22/2021 FELIPE HERNANDEZ
Quality Review Completed 12/28/2021 TARIK SAOUD
Building Plans Picked Up 12/30/2021 APPLICANT
Applicant returned to address corrections 1/26/2022 FELIPE HERNANDEZ
Applicant returned to address corrections 2/7/2022 FELIPE HERNANDEZ
Plan Check Approved 3/5/2024 REZA HAGHIGHAT
Issued 3/5/2024 APPLICANT
CofO in Progress 5/5/2026 BOBBY KEY
Permit Finaled 5/9/2026 JUAN VALENZUELA
CofO Issued 5/9/2026 JUAN VALENZUELA
Permit Finaled 5/9/2026 JUAN VALENZUELA

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/10/2022 DINAH GARIN
BHO/Hillside ordinance Cleared 1/10/2022 DINAH GARIN
BHO/Hillside ordinance Cleared 1/10/2022 DINAH GARIN
BHO/Hillside ordinance Cleared 1/10/2022 DINAH GARIN
BHO/Hillside ordinance Cleared 1/10/2022 DINAH GARIN
Permit Cleared 1/10/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/28/2022 DINAH GARIN
Sewer availability Cleared 1/28/2022 DINAH GARIN
Street Frontage Cleared 1/28/2022 DINAH GARIN
CPC Cleared 12/4/2023 DAVID URITA
Coastal Zone Cleared 12/4/2023 DAVID URITA
ZA Case Cleared 12/4/2023 DAVID URITA
Watercourse Cleared 1/16/2024 HISASHI KOBAYAKAWA
GPI Written Notices Cleared 1/17/2024 FELIPE HERNANDEZ
Grading Pre-Inspection Cleared 1/17/2024 FELIPE HERNANDEZ
Trees in Parkway Cleared 2/6/2024 ADALBERTO VERA
Low Impact Development Cleared 2/7/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 2/12/2024 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 2/17/2024 GILBERT URREA
Excavation more than 5-ft deep Cleared 2/20/2024 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Naim,, Soleiman Israel; Lic. No.: C32208 403 21ST ST      SANTA MONICA, CA 90402
Engineer Naim,, Soleiman Israel; Lic. No.: S2454 403 21ST ST      SANTA MONICA, CA 90402
Geologist Feffer,, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 3/15/2024 Corrections Issued ANDREW BEELI
Excavation/Setback/Form/Re-Bar 3/15/2024 Approved ANDREW BEELI
Footing/Foundation/Slab 3/15/2024 Approved ANDREW BEELI
PLUMBING-Rough 4/17/2024 Corrections Issued ANDREW BEELI
Excavation/Setback/Form/Re-Bar 5/7/2024 Corrections Issued ANDREW BEELI
Excavation/Setback/Form/Re-Bar 5/9/2024 Corrections Issued JOHN MATTILLO
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Corrections Issued JOHN MATTILLO
PLUMBING-Rough 5/9/2024 Corrections Issued JOHN MATTILLO
Excavation/Setback/Form/Re-Bar 5/16/2024 Partial Approval JOHN MATTILLO
Pre-Inspection 5/16/2024 Corrections Issued JOHN MATTILLO
Reinforced Concrete Frame 5/28/2024 Partial Approval JOHN MATTILLO
Sewer 5/28/2024 Not Ready for Inspection JOHN MATTILLO
Structural Steel Frame 5/28/2024 Not Ready for Inspection JOHN MATTILLO
Underground Mechanical 5/28/2024 Not Ready for Inspection JOHN MATTILLO
Deputy Shotcrete 5/31/2024 Conditional Approval JOHN MATTILLO
Excavation/Setback/Form/Re-Bar 6/6/2024 Partial Approval JOHN MATTILLO
Floor/Roof Diaphrgm/Shear Wall 6/26/2024 Corrections Issued JOHN MATTILLO
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Partial Approval JOHN MATTILLO
Deputy Reinf. Concrete 7/1/2024 Conditional Approval JOHN MATTILLO
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Partial Approval JOHN MATTILLO
BUILDING-Rough-Frame 8/29/2024 Corrections Issued JOHN MATTILLO
ELECTRICAL-Rough 8/29/2024 Corrections Issued JOHN MATTILLO
FLOOD-Proofing Certificate 8/29/2024 Approved JOHN MATTILLO
Green Building Rough 8/29/2024 Approved JOHN MATTILLO
HVAC-Rough 8/29/2024 Approved JOHN MATTILLO
PLUMBING-Rough 8/29/2024 Approved JOHN MATTILLO
Verify Sprinkler Sign Off 8/29/2024 Approved JOHN MATTILLO
BUILDING-Rough-Frame 9/10/2024 Partial Approval JOHN MATTILLO
ELECTRICAL-Rough 9/10/2024 Approved JOHN MATTILLO
Floor/Roof Diaphrgm/Shear Wall 9/10/2024 Approved JOHN MATTILLO
Gas Test 9/10/2024 Approved JOHN MATTILLO
Green Building Final 9/10/2024 Not Ready for Inspection JOHN MATTILLO
HVAC-Rough 9/10/2024 Approved JOHN MATTILLO
PLUMBING-Rough 9/10/2024 Approved JOHN MATTILLO
Rough-Elec/Plmb/HVAC 9/10/2024 Approved JOHN MATTILLO
Insulation 9/26/2024 Not Ready for Inspection ANDREW BEELI
Interior/Exterior Lathing 9/26/2024 Not Ready for Inspection ANDREW BEELI
Shower Pan 9/26/2024 Not Ready for Inspection ANDREW BEELI
Insulation 11/21/2024 Conditional Approval JOHN MATTILLO
Interior/Exterior Lathing 11/21/2024 Not Ready for Inspection JOHN MATTILLO
Service/Power Release 11/21/2024 Not Ready for Inspection JOHN MATTILLO
Drywall Nailing 12/3/2024 Approved JOHN MATTILLO
Interior/Exterior Lathing 12/3/2024 Approved JOHN MATTILLO
Special/Order Compliance 4/3/2025 Corrections Issued JOHN MATTILLO
Pre-Inspection 4/8/2025 Partial Inspection BOBBY KEY
Underground Mechanical 4/8/2025 Partial Inspection BOBBY KEY
Service/Power Release 2/20/2026 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 5/5/2026 Approved BOBBY KEY
Final 5/5/2026 OK to Issue CofO BOBBY KEY
Green Building Final 5/5/2026 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/5/2026 SGSOV Approved BOBBY KEY
Smoke Detectors 5/5/2026 Approved BOBBY KEY