117 E WESTWIND MALL 90292
Certificate Information: 117 E WESTWIND MALL 90292
- Application / Permit
- 21010-30000-06138
- Plan Check / Job No.
- B21WL05192
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND ROOF TERRACE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 8/3/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 8/3/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | TARIK SAOUD |
| Plans on Hold | 12/28/2021 | TARIK SAOUD |
| Hold Released | 1/5/2022 | TARIK SAOUD |
| Corrections Issued | 1/5/2022 | TARIK SAOUD |
| Quality Review Completed | 1/7/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 1/7/2022 | APPLICANT |
| Applicant returned to address corrections | 12/19/2022 | SERGIO SILVA |
| Applicant returned to address corrections | 3/29/2023 | SERGIO SILVA |
| Plan Check Approved | 7/19/2023 | SERGIO SILVA |
| Issued | 8/3/2023 | APPLICANT |
Permit Application Clearance Information
| Hold | Cleared | 1/3/2022 | JAZELLE A TRINIDAD |
| Trees in Parkway | Cleared | 1/27/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 3/28/2022 | DWAYNE LAURENT |
| Specific Plan | Cleared | 4/29/2022 | EDUARDO HERMOSO |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2022 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 10/31/2022 | HISASHI KOBAYAKAWA |
| Miscellaneous | Cleared | 12/22/2022 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 12/22/2022 | HISASHI KOBAYAKAWA |
| Low Impact Development | Cleared | 4/7/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/26/2023 | DINAH GARIN |
| Coastal Zone | Cleared | 7/11/2023 | SPENCER WEJROWSKI |
| Miscellaneous | Cleared | 7/11/2023 | SPENCER WEJROWSKI |
| Miscellaneous | Cleared | 7/11/2023 | SPENCER WEJROWSKI |
| Miscellaneous | Cleared | 7/11/2023 | SPENCER WEJROWSKI |
| Miscellaneous | Cleared | 7/11/2023 | SPENCER WEJROWSKI |
| Specific Plan | Cleared | 7/11/2023 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 7/11/2023 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 7/11/2023 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 7/11/2023 | SPENCER WEJROWSKI |
Contact Information
| Architect | Landry,, Richard; Lic. No.: C21848 | 1818 S.SEPULVEDA BLVD LOS ANGELES, CA 90025 |
| Contractor | Owner-Builder | , |
| Engineer | Barajas,, Alejandro Leon; Lic. No.: S4773 | 565 PEARL ST STE 209 LA JOLLA, CA 92037 |
| Landscape Architect | Laforga,, David Martinez; Lic. No.: LA5555 | 956 3RD AVENUE LOS ANGELES, CA 90019 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Underground Mechanical | 6/9/2026 |
Inspection Request History
| PLUMBING-Rough | 1/19/2024 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 1/29/2024 | Corrections Issued | JESUS RODRIGUEZ |
| METHANE-Subgrade | 1/29/2024 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 2/14/2024 | Corrections Issued | HERBERT GIRON |
| METHANE-Barrier | 2/14/2024 | Not Ready for Inspection | HERBERT GIRON |
| METHANE-Subgrade | 2/14/2024 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 2/16/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 3/5/2024 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 3/29/2024 | Approved | HERBERT GIRON |
| METHANE-Barrier | 3/29/2024 | Approved | HERBERT GIRON |
| Pre-Inspection | 4/10/2024 | Partial Inspection | HERBERT GIRON |
| Deputy Steel/Welding | 4/17/2024 | Conditional Approval | HERBERT GIRON |
| Deputy Steel/Welding | 4/19/2024 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2024 | Corrections Issued | HERBERT GIRON |
| Deputy Wood Construction | 5/16/2024 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2024 | Partial Approval | HERBERT GIRON |
| Deputy Wood Construction | 5/20/2024 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2024 | Partial Approval | HERBERT GIRON |
| Masonry Wall/Backfill | 7/26/2024 | Partial Inspection | HERBERT GIRON |
| PLUMBING-Rough | 8/1/2024 | Corrections Issued | HERBERT GIRON |
| Sewer | 8/1/2024 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 8/16/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 8/19/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 8/26/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 10/25/2024 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 10/25/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 10/25/2024 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 11/8/2024 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 11/8/2024 | Not Ready for Inspection | HERBERT GIRON |
| Special/Order Compliance | 11/8/2024 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 12/6/2024 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 12/30/2024 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 1/6/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 1/6/2025 | Conditional Approval | HERBERT GIRON |
| HVAC-Rough | 1/6/2025 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 1/13/2025 | Conditional Approval | HERBERT GIRON |
| HVAC-Rough | 1/13/2025 | Approved | HERBERT GIRON |
| METHANE-Rough | 1/13/2025 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 1/13/2025 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 1/13/2025 | Approved | HERBERT GIRON |
| Insulation | 1/21/2025 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 1/24/2025 | Approved | HERBERT GIRON |
| Drywall Nailing | 1/24/2025 | Approved | HERBERT GIRON |
| Green Building Rough | 1/24/2025 | Approved | HERBERT GIRON |
| Shower Pan | 5/9/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 6/5/2025 | Approved | JAYLIN GRAVITTE |
| Pre-Inspection | 7/3/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/14/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/14/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 4/24/2026 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Final | 5/21/2026 | Approved | RUBEN RIVAS |
| Underground Mechanical | 5/26/2026 | Partial Approval | ANDREW NAVE |
| Gas Test | 6/5/2026 | No Result Entered | ANTHONY EGSON |