710-710 1/2 S ALMA ST 90731
Certificate Information: 710-710 1/2 S ALMA ST 90731
- Application / Permit
- 21010-30000-06131
- Plan Check / Job No.
- B21WL05179
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 2-Story Duplex *** 1 of 2 ***
- Permit Issued
- Issued on 6/10/2022
- Issuing Office
- Current Status
- CofO Issued on 6/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | DAVID CASTILLO |
| Corrections Issued | 1/18/2022 | DAVID CASTILLO |
| Quality Review Completed | 2/14/2022 | CHIHARU SUZUKI |
| Plan Check Approved | 6/10/2022 | DAVID CASTILLO |
| Issued | 6/10/2022 | APPLICANT |
| Building Plans Picked Up | 6/15/2022 | APPLICANT |
| CofO in Progress | 6/16/2023 | ANSON MAGLASANG |
| CofO Issued | 6/16/2023 | ANSON MAGLASANG |
| Permit Finaled | 6/16/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/20/2022 | PATRICK MISCHLICH |
| Address approval | Cleared | 2/8/2022 | ANA VILLA |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2022 | ANA VILLA |
| Sewer availability | Cleared | 2/10/2022 | ANA VILLA |
| Permit | Cleared | 3/2/2022 | ANA VILLA |
| Hydrant and Access approval | Cleared | 3/5/2022 | CINDY JOSSELYN |
| Low Impact Development | Cleared | 3/21/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 4/1/2022 | ANA VILLA |
| Trees in Parkway | Cleared | 4/6/2022 | ADALBERTO VERA |
| Frnt yard landscape/Water mgmt | Cleared | 4/12/2022 | STEVEN WECHSLER |
Contact Information
| Architect | , ; Lic. No.: C35150 | 2355 WESTWOOD BLVD #900 LOS ANGELES, CA 90064 |
| Contractor | Owner-Builder | , |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/21/2022 | Corrections Issued | ANSON MAGLASANG |
| Footing/Foundation/Slab | 7/21/2022 | Corrections Issued | ANSON MAGLASANG |
| Footing/Foundation/Slab | 7/22/2022 | Approved | ANSON MAGLASANG |
| PLUMBING-Rough | 8/9/2022 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2022 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 11/8/2022 | Partial Approval | ANSON MAGLASANG |
| Green Building Rough | 11/8/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| HVAC-Rough | 11/8/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Verify Sprinkler Sign Off | 11/8/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 12/1/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| ELECTRICAL-Rough | 12/1/2022 | Approved | ANSON MAGLASANG |
| Green Building Rough | 12/1/2022 | Approved | ANSON MAGLASANG |
| HVAC-Rough | 12/1/2022 | Approved | ANSON MAGLASANG |
| PLUMBING-Rough | 12/1/2022 | Approved | ANSON MAGLASANG |
| Verify Sprinkler Sign Off | 12/1/2022 | Approved | ANSON MAGLASANG |
| Green Building Rough | 12/2/2022 | Approved | ANSON MAGLASANG |
| Rough-Elec/Plmb/HVAC | 12/2/2022 | Approved | ANSON MAGLASANG |
| Verify Sprinkler Sign Off | 12/2/2022 | Approved | ANSON MAGLASANG |
| Insulation | 12/9/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 12/22/2022 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 12/22/2022 | Partial Approval | ANSON MAGLASANG |
| Interior/Exterior Lathing | 2/14/2023 | Approved | JOHN KLARIN |
| Shower Pan | 2/14/2023 | Approved | JOHN KLARIN |
| HVAC-Final | 6/5/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 6/5/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 6/6/2023 | Not Ready for Inspection | ANSON MAGLASANG |
| Gas Test | 6/6/2023 | Approved | ANSON MAGLASANG |
| HVAC-Final | 6/6/2023 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 6/15/2023 | Approved | ANSON MAGLASANG |
| Final | 6/15/2023 | OK to Issue CofO | ANSON MAGLASANG |
| Green Building Final | 6/15/2023 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 6/15/2023 | SGSOV Approved | ANSON MAGLASANG |
| Service/Power Release | 6/15/2023 | Approved | ANSON MAGLASANG |
| Smoke Detectors | 6/15/2023 | Approved | ANSON MAGLASANG |