11420 W BIONA DR 90066

Certificate Information: 11420 W BIONA DR 90066

Application / Permit
21010-30000-06130
Plan Check / Job No.
B21WL05174
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
new two story S.F.D. w/ attached two car garage with roof trusses
Permit Issued
Issued on 5/17/2022
Issuing Office
Current Status
CofO Issued on 5/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2022 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 YASHAR EMAMI
Corrections Issued 2/3/2022 YASHAR EMAMI
Quality Review Completed 2/22/2022 CHIHARU SUZUKI
Applicant returned to address corrections 4/22/2022 YASHAR EMAMI
Building Plans Picked Up 4/25/2022 APPLICANT
Plan Check Approved 5/6/2022 YASHAR EMAMI
Issued 5/17/2022 APPLICANT
CofO in Progress 5/3/2023 JOHNNY MIRANDA
Permit Finaled 5/16/2023 DANIEL ORRANTE
CofO Issued 5/16/2023 DANIEL ORRANTE
Permit Finaled 5/16/2023 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 2/26/2022 JOSE HERNANDEZ
Specific Plan Cleared 3/2/2022 FREDDY GARCIA
Address approval Cleared 3/3/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 3/3/2022 JOSE HERNANDEZ
Sewer availability Cleared 3/3/2022 JOSE HERNANDEZ
Trees in Parkway Cleared 3/23/2022 YASHAR EMAMI
Hydrant and Access approval Cleared 4/5/2022 LAURINDA MEADE
Low Impact Development Cleared 4/6/2022 TA ANH
Roof/Waste drainage to street Cleared 4/12/2022 JOSE HERNANDEZ
GPI Written Notices Cleared 5/6/2022 YASHAR EMAMI
Grading Pre-Inspection Cleared 5/6/2022 YASHAR EMAMI

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26940 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/14/2022 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 6/27/2022 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 6/28/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 7/25/2022 No Access for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 7/28/2022 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 8/2/2022 Conditional Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/30/2022 Partial Approval JOHNNY MIRANDA
Deputy Wood Construction 8/31/2022 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Rough 9/8/2022 Approved JOHNNY MIRANDA
Deputy Wood Construction 9/12/2022 Conditional Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 10/12/2022 Not Ready for Inspection JOHNNY MIRANDA
Green Building Rough 10/12/2022 No Access for Inspection JOHNNY MIRANDA
HVAC-Rough 10/12/2022 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 10/12/2022 Not Ready for Inspection JOHNNY MIRANDA
Shower Pan 10/12/2022 Not Ready for Inspection JOHNNY MIRANDA
Verify Sprinkler Sign Off 10/12/2022 Not Ready for Inspection JOHNNY MIRANDA
Wood Frame 10/12/2022 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Approved JOHNNY MIRANDA
HVAC-Rough 10/13/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 10/13/2022 Approved JOHNNY MIRANDA
Shower Pan 10/13/2022 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 10/24/2022 Approved KENNETH NAGLE
Green Building Rough 10/24/2022 Approved KENNETH NAGLE
Interior/Exterior Lathing 10/24/2022 Partial Approval KENNETH NAGLE
Shower Pan 10/24/2022 Approved KENNETH NAGLE
Verify Sprinkler Sign Off 10/24/2022 Approved KENNETH NAGLE
Insulation 11/17/2022 Approved JOHNNY MIRANDA
Drywall Nailing 12/7/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 12/7/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 3/10/2023 Approved JOHNNY MIRANDA
Green Building Final 3/10/2023 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Final 3/10/2023 Approved JOHNNY MIRANDA
Service/Power Release 3/10/2023 Not Ready for Inspection JOHNNY MIRANDA
Verify Rec and Parks Fee Memo 3/10/2023 Approved JOHNNY MIRANDA
Gas Test 3/16/2023 Approved JOHNNY MIRANDA
Green Building Final 3/16/2023 Approved JOHNNY MIRANDA
PLUMBING-Final 3/16/2023 Approved JOHNNY MIRANDA
Smoke Detectors 3/16/2023 Approved JOHNNY MIRANDA
Service/Power Release 4/4/2023 Approved MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 4/5/2023 SGSOV Not Ready JOHNNY MIRANDA
Pre-Inspection 4/6/2023 Not Ready for Inspection CLAYTON GRAHAM
Final 4/12/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 4/12/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 4/12/2023 SGSOV Approved HERBERT GIRON
Final 5/2/2023 OK to Issue CofO JOHNNY MIRANDA