3027-3029 S MALCOLM AVE 90034
Certificate Information: 3027-3029 S MALCOLM AVE 90034
- Application / Permit
- 21010-30000-06060
- Plan Check / Job No.
- B21WL05142
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story SFD (2,473 sf) w./ att. 2-car garage (347 sf) and ADU (460 sf) per GCS 65852.2 (e) (1) (A)
- Permit Issued
- Issued on 10/25/2022
- Issuing Office
- Current Status
- CofO Issued on 1/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | REZA HAGHIGHAT |
| Corrections Issued | 12/5/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 12/14/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 4/14/2022 | REZA HAGHIGHAT |
| Plan Check Approved | 5/16/2022 | REZA HAGHIGHAT |
| Issued | 10/25/2022 | APPLICANT |
| Building Plans Picked Up | 10/26/2022 | APPLICANT |
| CofO in Progress | 1/10/2025 | DANIEL VERA |
| CofO Issued | 1/16/2025 | RICHARD STEINBACH |
| Permit Finaled | 1/16/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2022 | DINAH GARIN |
| Low Impact Development | Cleared | 2/8/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 2/19/2022 | STEVEN JIN |
| Hydrant and Access approval | Cleared | 2/25/2022 | LAURINDA MEADE |
| Specific Plan | Cleared | 3/13/2022 | PEDRO AYALA |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2022 | DINAH GARIN |
| Sewer availability | Cleared | 3/22/2022 | DINAH GARIN |
| GPI Written Notices | Cleared | 4/13/2022 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 4/13/2022 | REZA HAGHIGHAT |
| Permit | Cleared | 4/18/2022 | CATHERINE ADROVER |
Contact Information
| Architect | Mebasser,, John A; Lic. No.: C19055 | 2525 PEARL STREET SANTA MONICA, CA 90405 |
| Contractor | Lumar Corporation; Lic. No.: 1027838-B | 11420 SANTA MONICA BLVD #252233 LOS ANGELES, CA 90025 |
| Engineer | Soleymani,, Habib K; Lic. No.: S2575 | 1917 PARNELL AVE LOS ANGELES, CA 90025 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/5/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 12/20/2022 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 12/27/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 12/27/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Underground Mechanical | 12/27/2022 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 2/10/2023 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/10/2023 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 2/14/2023 | No Access for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 4/14/2023 | Approved | JOHNNY MIRANDA |
| Grounding or Bonding | 4/14/2023 | Approved | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 4/19/2023 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 4/27/2023 | Approved | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2023 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Partial Approval | JESUS PINEDA |
| Deputy Wood Construction | 8/11/2023 | Conditional Approval | DAVID FEILER |
| Deputy Drilled-In Anchors | 8/16/2023 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2023 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 9/28/2023 | Approved | ARAM AVEDISIAN |
| Sewer | 9/28/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 10/3/2023 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/11/2023 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 10/11/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 10/11/2023 | Approved | JESUS PINEDA |
| HVAC-Rough | 10/11/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 10/11/2023 | Partial Approval | JESUS PINEDA |
| MERV13>=Rough | 10/11/2023 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 10/11/2023 | Not Ready for Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/17/2023 | Approved | CLAYTON GRAHAM |
| Verify Sprinkler Sign Off | 10/17/2023 | Approved | CLAYTON GRAHAM |
| Shower Pan | 10/24/2023 | Approved | JESUS PINEDA |
| Insulation | 10/27/2023 | Conditional Approval | BEN MOLSTAD |
| Interior/Exterior Lathing | 10/27/2023 | Corrections Issued | BEN MOLSTAD |
| Insulation | 11/3/2023 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 11/3/2023 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 11/16/2023 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 2/20/2024 | Partial Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 4/22/2024 | Approved | JESUS PINEDA |
| Service/Power Release | 4/22/2024 | Not Ready for Inspection | JESUS PINEDA |
| Gas Test | 5/7/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 5/7/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 5/7/2024 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 5/7/2024 | Approved | KENNETH NAGLE |
| Gas Test | 5/10/2024 | Approved | JESUS PINEDA |
| Final | 8/21/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 8/21/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 8/21/2024 | Corrections Issued | JESUS PINEDA |
| MERV13>=Final | 8/21/2024 | Corrections Issued | JESUS PINEDA |
| Smoke Detectors | 8/21/2024 | Approved | JESUS PINEDA |
| Final | 11/8/2024 | Partial Approval | KIRK SANDERS |
| HVAC-Final | 11/8/2024 | Corrections Issued | KIRK SANDERS |
| MERV13>=Final | 11/8/2024 | Approved | KIRK SANDERS |
| Final | 1/10/2025 | OK to Issue CofO | DANIEL VERA |