10534 W BLYTHE AVE 90064
Certificate Information: 10534 W BLYTHE AVE 90064
- Application / Permit
- 21010-30000-06059
- Plan Check / Job No.
- B21WL05139
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached 1-story ADU (574 sf) w./ att. covered patio (9' x 19'-4") (187 sf) per GCS 65852.2 (e) (1) (B) AND LAMC 12.22 A.33(c) , (d) AND (g)
- Permit Issued
- Issued on 4/14/2022
- Issuing Office
- Current Status
- CofO Issued on 6/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | REZA HAGHIGHAT |
| Corrections Issued | 12/4/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 12/14/2021 | TARIK SAOUD |
| Plan Check Approved | 4/14/2022 | REZA HAGHIGHAT |
| Issued | 4/14/2022 | APPLICANT |
| Building Plans Picked Up | 4/22/2022 | APPLICANT |
| CofO in Progress | 5/31/2023 | CLAYTON GRAHAM |
| Permit Finaled | 6/8/2023 | DANIEL ORRANTE |
| CofO Issued | 6/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2022 | DINAH GARIN |
| Sewer availability | Cleared | 1/12/2022 | DINAH GARIN |
| Low Impact Development | Cleared | 1/28/2022 | JORGE MEJIA LEMUS |
| Hydrant and Access approval | Cleared | 3/2/2022 | CINDY JOSSELYN |
| Roof/Waste drainage to street | Cleared | 3/7/2022 | JOSE HERNANDEZ |
| Specific Plan | Cleared | 3/7/2022 | VALERIA CEJA |
| Construction near power lines | Cleared | 3/25/2022 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 4/14/2022 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 4/14/2022 | REZA HAGHIGHAT |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/13/2022 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Subgrade | 6/16/2022 | Approved | KEVIN SARGSYAN |
| METHANE-Barrier | 6/24/2022 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 7/7/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Pre-Inspection | 7/8/2022 | No Access for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/11/2022 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Rough | 9/26/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/26/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 10/5/2022 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 10/5/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 10/7/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 10/7/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 10/12/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 10/18/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 10/18/2022 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 10/18/2022 | Approved | OGANES TARAKHCHYAN |
| Insulation | 10/25/2022 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 11/7/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 3/3/2023 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 3/3/2023 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 4/6/2023 | Approved | ASHLEY THOMPSON |
| Final | 4/6/2023 | Corrections Issued | ASHLEY THOMPSON |
| Gas Test | 4/6/2023 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 4/6/2023 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 4/6/2023 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 4/6/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 4/6/2023 | SGSOV Approved | ASHLEY THOMPSON |
| Service/Power Release | 4/6/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Smoke Detectors | 4/6/2023 | Approved | ASHLEY THOMPSON |
| Final | 4/18/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 4/18/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 4/18/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 4/18/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 4/18/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Service/Power Release | 4/18/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Final | 4/25/2023 | Corrections Issued | CLAYTON GRAHAM |
| Gas Test | 4/25/2023 | Approved | CLAYTON GRAHAM |
| Green Building Final | 4/25/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Final | 4/25/2023 | Approved | CLAYTON GRAHAM |
| Service/Power Release | 4/25/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Final | 5/30/2023 | OK to Issue CofO | CLAYTON GRAHAM |
| Service/Power Release | 5/30/2023 | Approved | CLAYTON GRAHAM |