12252 W DOROTHY ST 90049
Certificate Information: 12252 W DOROTHY ST 90049
- Application / Permit
- 21010-30000-06044
- Plan Check / Job No.
- B21WL05125
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New two story S.F.R. with attached garage *** 1 of 3 ***
- Permit Issued
- Issued on 5/11/2022
- Issuing Office
- Current Status
- CofO Issued on 4/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 12/7/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 12/16/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 2/9/2022 | FELIPE HERNANDEZ |
| Plan Check Approved | 4/22/2022 | FELIPE HERNANDEZ |
| Plan Check Approved | 5/10/2022 | FELIPE HERNANDEZ |
| Issued | 5/11/2022 | APPLICANT |
| Building Plans Picked Up | 5/18/2022 | APPLICANT |
| CofO in Progress | 4/12/2024 | ASHLEY THOMPSON |
| Permit Finaled | 4/12/2024 | DANIEL ORRANTE |
| CofO Issued | 4/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/3/2022 | VALERIA CEJA |
| Low Impact Development | Cleared | 3/15/2022 | LONDY ALVARADO |
| Permit | Cleared | 3/19/2022 | SAUL GARCIA |
| Roof/Waste drainage to street | Cleared | 3/19/2022 | SAUL GARCIA |
| Hydrant and Access approval | Cleared | 3/20/2022 | CINDY JOSSELYN |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 3/22/2022 | SAUL GARCIA |
| Trees in Parkway | Cleared | 4/6/2022 | ADALBERTO VERA |
Contact Information
| Contractor | Sunset Built Inc; Lic. No.: 1005054-B | 8383 WILSHIRE BLVD #800 BEVERLY HILLS, CA 90211 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/18/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Special/Order Compliance | 7/26/2022 | Corrections Issued | JOHN KIDWELL |
| Underground Mechanical | 7/28/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 8/24/2022 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/24/2022 | Approved | JOHN KIDWELL |
| Deputy Reinf. Concrete | 8/26/2022 | Partial Approval | JOHN KIDWELL |
| Special/Order Compliance | 8/29/2022 | Partial Inspection | JOHN KIDWELL |
| Pre-Inspection | 9/22/2022 | Partial Inspection | JOHN KIDWELL |
| Special/Order Compliance | 9/22/2022 | Corrections Issued | RICHARD STEINBACH |
| Special/Order Compliance | 9/28/2022 | Partial Inspection | JOHN KIDWELL |
| Deputy Steel/Welding | 10/4/2022 | Conditional Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2022 | Partial Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2022 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/28/2022 | Corrections Issued | ASHLEY THOMPSON |
| Underground Mechanical | 12/28/2022 | Partial Approval | ASHLEY THOMPSON |
| HVAC-Rough | 1/20/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 1/20/2023 | Approved | CLAYTON GRAHAM |
| Shower Pan | 1/20/2023 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 2/3/2023 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 2/8/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 2/8/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 2/17/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 2/17/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Partial Approval | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 3/24/2023 | Conditional Approval | CLAYTON GRAHAM |
| Green Building Rough | 3/24/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Verify Sprinkler Sign Off | 3/24/2023 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 5/11/2023 | Approved | JEREMY TODD |
| Green Building Rough | 5/11/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 5/11/2023 | Approved | JEREMY TODD |
| Insulation | 5/18/2023 | Approved | JESUS PINEDA |
| Drywall Nailing | 5/26/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/26/2023 | Approved | JESUS PINEDA |
| HVAC-Final | 2/7/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 2/7/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 2/12/2024 | Approved | ASHLEY THOMPSON |
| Service/Power Release | 2/12/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Service/Power Release | 2/15/2024 | Approved | ASHLEY THOMPSON |
| Final | 3/20/2024 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 3/20/2024 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 3/20/2024 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 3/20/2024 | Partial Approval | CARLOS MATAMOROS |
| Final | 4/2/2024 | Conditional Approval | ASHLEY THOMPSON |
| Smoke Detectors | 4/2/2024 | Approved | ASHLEY THOMPSON |
| Final | 4/12/2024 | OK to Issue CofO | ASHLEY THOMPSON |